Total Years of Experience: 32 Years, 9 Months
November 2010
To June 2012
Production Responsible
at ConVerpro
Location :
Venezuela
Refinery construction at Puerto La Cruz Venezuela as RP. (Production Responsible).
Project over 485 MM $ (Phase I and II)
Project over 485 MM $ (Phase I and II)
November 2009
To November 2010
Mayor Preservation Consultant
at PDVSA GAS
Location :
Venezuela
Responsible over all the preservation teams and works to the entire project (PGA) (Fields CSR, CSJ, CZMT, CSA, main stores and warehouse) (1800 MM $) in order to guarantee the functionality of equipments during construction according to specification API-686.
February 2005
To June 2009
Construction Superintendent
at PDVSA - Project Gas Anaco
Location :
Venezuela
Construction of the complex “Centro Operative San Joaquin” Installation of nine turbines Mars 100 to increases production to 1400 MQFD, and 36000 BPD of Crude Oil, coordination of all the activities between the ten different contractors working in the complex of Gas & Oil; recollections lines (100 km.) and pipe lines interconnection, also the modification of the five station of recollection to handle the increase of production; Project over 1200 MM $
January 2004
To May 2004
Project Engineer
at CCIC – Subcontractor
Location :
Qatar - Doha
Construction activities of Train 4 utility area, LNG Plant.
Head of Plant Shut Down, Train 3 Flare repairs, 146mts high, I.D 42” & 64”.
Specifications followed ASME/ANSI, API, AWS, ASTM, Job Spec. Project over 1500 MM $
Head of Plant Shut Down, Train 3 Flare repairs, 146mts high, I.D 42” & 64”.
Specifications followed ASME/ANSI, API, AWS, ASTM, Job Spec. Project over 1500 MM $
February 2002
To January 2004
Preservation Material Maintenance Management, and Section Mechanical Engineer Utility Area.
at FLOUR DANIEL – INELECTRA
Location :
Venezuela
Responsibility over all the preservations teams, for the up grading plant of synthetic oil, (Use of new technology in Gas, Liquid and solid Corrosion inhibitors, Desiccants etc) during construction. Rotary and Stationary equipment installation using laser Tech. Vibration analysis etc, Design of routines and procedures for Preventive Maintenance, and Standardisation of lubricants, Leader of subcontractor’s teams for the Pre-commissioning activities of utilities areas. Specifications followed ASME/ANSI, API, AWS, ASTM & AMERIVEN Job Spec. Project over 870 MM $
July 2001
To January 2002
Construction Coordinator Manager.
at PDVSA GAS– Dit Harris. Consultant
Location :
Venezuela
Construction of pipelines from oilfields San Joaquin, Santa Ana, Guario, El Roble to compression plats of Santa Ana 1, 2 and 3 as well of the Compression plant of San Joaquin, pipelines of 16” and 26” diameter and hot interconnection between Station and Plants. Anaco.
Pre-commissioning and commissioning activities.
Specifications followed ASME/ANSI, API, AWS, ASTM & PDVSA GAS Job Spec Project over 100 MM $
Pre-commissioning and commissioning activities.
Specifications followed ASME/ANSI, API, AWS, ASTM & PDVSA GAS Job Spec Project over 100 MM $
August 2000
To July 2001
Section Mechanical Engineer
at Foster Wheeler Contractor (DSD-CGI Subcontractor)
Location :
Venezuela
Construction and installation of isometrics, Modifications of spools as required by process
Field Engineer in charge of Hydro testing and Pneumatic testing
Pre commissioning activities on COKE plant
Specifications followed ASME/ANSI, API, AWS, ASTM & Sincor / Foster Wheeler Job Spec. Project over 800 MM $
Field Engineer in charge of Hydro testing and Pneumatic testing
Pre commissioning activities on COKE plant
Specifications followed ASME/ANSI, API, AWS, ASTM & Sincor / Foster Wheeler Job Spec. Project over 800 MM $
November 1998
To July 2000
Preservation Materials Management
at Kellogg Brown & Root- Parson- Technip- Dit Harris Contractor
Location :
Venezuela
Preservation, Preventive and Corrective Maintenance. Corrosion Management for all facilities, responsible of all equipment used in the heavy oil plant up grading units, ( Utility, Coke, Crude up grader, Gas plant, Hydrogen plant, Sulphur plant etc) Rotary and Stationary equipment installation Design of routines and procedures for Preventive Maintenance. Leader of subcontractors teams for the Pre-commissioning activities of utilities areas. Standardisation of lubricants. Specifications followed ASME/ANSI, API, AWS, ASTM & Petrozuata. Project over 1200 MM $
September 1997
To November 1998
Office Manager and Field Engineer.
at CONOCO – Systems MULTIPLEXOR Consultant
Location :
Venezuela
Coordination of construction activities in the 200 km of pipelines ( 36” and 20” I.D) Cross country pipelines from ZUATA to JOSE Inspection of Subcontractors during Construction of pipelines. Hydro testing, pre-commissioning and commissioning of pipelines.
Specifications followed ASME/ANSI, API, AWS, ASTM & Petrozuata Job Spec. Project over 500 MM $
Specifications followed ASME/ANSI, API, AWS, ASTM & Petrozuata Job Spec. Project over 500 MM $
March 1994
To August 1997
Corporation Maintenance Manager.
at R.M PROJECT
Location :
Venezuela
Lead Engineer of the Maintenance Departments for Preventive and Corrective Maintenance. Design of maintenance routines for the subcontractors during operations. Supervision of subcontractors
Coordination of all the requirements to keep full operation
Coordination of all the requirements to keep full operation
August 1989
To March 1994
Mechanical Construction Manager
at CABLE BELT – ABB- EDIVIAGRO Contractor
Location :
Venezuela
Construction of a cable belt system to transport bauxite from the mine to field storage (I.P.C.) 4, 2 Km long with a drop of 394 Mts. Regenerative system at 4000 Ton per hour. Coordination of the mechanical design & Project Construction, Responsible of Commissioning and turn - over to the client. Project over 120 MM $
June 1984
To August 1989
Project Mechanical Engineer, Maintenance Manager
at EDIVIAGRO, C.A.
Location :
Venezuela
Responsible for the maintenance and repairs of all the heavy equipment to support the construction sites. Maintenance and rebuild of asphalt plant, rock crushers and concrete plants, Mechanical Engineer, Maintenance Department high way Barlovento - Miranda. Conintur Dam - Tachira, Maintenance Department high way Valera - Trujjillo, Acarigua - Guanare and Guatire - Kempis
February 1982
To June 1984
Section Mechanical Engineer – Preventive Maintenance
at EDIVIAGRO, VINCCLER, TONORO Contractors
Location :
Venezuela
Responsible for preventive maintenance over 2000 different types of heavy equipment, used in the dam construction of Guri. Design, construction and installation of the lubrication module to attend
all the equipment Construction, Installation, Training and Operation of Lubrication Lab spectrograph analysis, Dynamometers for diesel engines, Hydraulic test banks, Diesel injection test banks and Drill Training and Operation with Rotamec, injection of concrete to the base of the dam.
Project over 600 MM $
all the equipment Construction, Installation, Training and Operation of Lubrication Lab spectrograph analysis, Dynamometers for diesel engines, Hydraulic test banks, Diesel injection test banks and Drill Training and Operation with Rotamec, injection of concrete to the base of the dam.
Project over 600 MM $
Share on Facebook
Share on Twitter
Share Via Email