Mahmoud Abdelsattar, Senior Electrical Engineer

Mahmoud Abdelsattar

Senior Electrical Engineer

Saudi Bin Laden Group SBG

Lieu
Arabie Saoudite - La Mecque
Éducation
Baccalauréat, Electrical power and machine department
Expérience
17 years, 5 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :17 years, 5 Mois

Senior Electrical Engineer à Saudi Bin Laden Group SBG
  • Arabie Saoudite - La Mecque
  • Je travaille ici depuis mars 2015

MALKAN reservoir & pump station (NEW EXTENSION OF HOLLY HARAM).
LOT#1 pump station (NEW EXTENSION OF HOLLY HARAM).
Study technical offers, direct and coordinate manufacturing, construction, for each pump station 6000KVA total load containing 13.8KV switchgear (25 panels), DC system, MV/LV transformer, VFDs, MV generators, LV panels.
Work as

Senior Electrical Engineer à Arabian Covenant Engineering Consultant (ACEC)
  • Arabie Saoudite - La Mecque
  • septembre 2013 à mars 2015

Erection of AIN SHAMS flour mills by BUHLER SWITZERLAND.
Ensure the installation and execution of electrical works including LV electrical substation, panel boards, cable routing installation, cables pulling and termination, lighting system, grounding system and light current systems installation with project specification and international standards.

Electrical residential Engineer à Integrated Engineering Economical Consultancy Formerly SABBOUR Associates
  • Egypte - Le Caire
  • juillet 2012 à mars 2013

Electrical networks installation for ELREHAB city.
Electrical erection for MV network including the distributor substation, MV cables and step down transformers.
Supervision of electrical erection for LV network including LV cables, distribution boards.
Supervision of electrical erection for the street lighting network

Electrical Engineer à Reliance Heavy Industries (RHI)
  • Egypte
  • avril 2007 à juillet 2012

DANGOTE Cement Plant. May (2012) - Oct (2012)
Participated the tendering phase including the technical specification and evaluations of the tender offers.
Review the basic design for electrical drawing and documents against the contract specifications.
Approval the electrical systems shop drawing for construction execution.

ELNAHDA Cement Plant. Oct (2011) - April (2012)
Supervision of electrical erection and Commissioning activities in cement mill area and cement mill substation including MV and LV equipment’s.
Prepare and issue the punch list for handover.

ALARISH Cement Plant (GOE). August (2010) - Oct (2011)
Participated the site electrical erection and commissioning activities.
Responsible for erection of ladders, trays cables pulling, termination and cable routing.
Responsible for MV power substation installation (66/11KV). .
Supervision on electrical installation for administration Buildings.
Supervision on electrical installation and Pre-commissioning for the complete electrical network including MV switchgear, step-down transformers, LV panels, motors, variable speed drive.

Sinai cement plant (Cement mill (4)) . February (2010) - July (2010)
Participated erection and commissioning of Sinai cement plant (4th Cement Mill):
Project engineer responsible for basic design and coordination meetings.
Review of electrical drawings, project specification, schedule and subcontractor’s contract.
Responsible for site electrical erection and commissioning activities with FLSmidth for MV/LV equipment.

MISR BENI SUEF cement plant (2nd line). June (2009)-January (2010)
Commissioning of MISR BENI SUEF cement plant (2nd line) with the following activities:
Pre-commissioning and commissioning work with ABB for LV distribution including main distribution boards and motor control center, continuity test and Megger test for all cables, Check all connections and wiring of power and control circuits.
Responsibility for No load and cold run test activities with POLYSIUS for production equipment.

Sinai White Cement Plant (2nd line). July (2008) - May (2009)
Installation and commissioning of Sinai white cement plant with the following activities:
Evaluation and supervision site activities and time schedule progress.
Prepare and issue the punch list.
Electrical erection activities in cement mill area and cement mill Substation including MV network (substation switchgear, MV cables, MV motors and MV/LV step down transformers)

Erection the of Arabian Cement Plant ACC (1st line). June (2007) - June (2008)
Participated supervision on erection of Ramliya cement plant with the following activities:
Ensure the installation and execution of Low Voltage Equipment’s such as Panel Boards, erection of ladders, trays, Cable pulling, grounding/lightning system indoor and outdoor lighting system corresponds the international standards.
Supervision on cables pulling, termination and cable routing for MV cables.
electrical installation for Cement line equipment, Central Control Building, work shop and ware house building
Prepare and issue the minutes of meeting.

Revamping line one of Ameryah Cement Company. February (2007) - June (2007)
Participated in commissioning of AMCC (line one) revamping with the following activities:
Precommissioning and commissioning activites for electrical equipments
No-load test and cold run test for motors

Electrical Engineer à Egyptian Group for Engineering Consultation (EGEC)
  • Egypte - Le Caire
  • août 2006 à mai 2007

Contributes in the designing and drawing for Elkhameal city and the police hospital ministry of interior

Éducation

Baccalauréat, Electrical power and machine department
  • à Ain Shams University
  • janvier 2006

very good -Project: distribution system planning for a newly developing area -Description: establishing a complete electrical network design for newly developing area starting with 66/11kv Substation ending with electrical installations in buildings.

Specialties & Skills

Network Design
Commissioning
Installation
Installations
CABLING
LIGHTING
NETWORKING
SUPERVISORY SKILLS
BUDGETING
MATERIALS MANAGEMENT
MICROSOFT WORKS
electrical distribution

Langues

Arabe
Expert
Anglais
Expert