- Prepare a revised schedule loaded with the project budget, required resources, and narrative report including
manpower and equipment histograms using Primavera P18.
- Update schedule on weekly basis to monitor progress using Primavera P18.
- Review all weekly and monthly reports for the section under my responsibility according to the updated
schedules.
- Review Bi-weekly reports (Dashboard), management log, material tracking log, and one weekly look ahead
schedule report including target periodically.
- Monitor manpower and equipment histograms compared with planned resources.
- Operate and use Primavera P6 EPPM to monitor project progress in the lieu of the company resource pool and
its overall strategy.
- Prepare all required and needed presentations to illustrate project progress and obstacles.
- Attend all weekly and monthly progress meetings with the company head office, client.
Hassan Allam Construction company implements a complete water plant as Buildings, Roads, Fence,
Infrastructure, etc..
Delivery Pipe Lines with a total length of 29 km: 1400 mm, 1200 mm, 1000 mm & 800 mm.
Intake: Supply & Erection of intake raw water pump to transfer 500K m3/day to the
booster pump station.
Booster: Supply & Erection of pumps to transfer 500K m3/day from Booster pump station
to the water treatment plant site.
Project: Abu-Oweikal’ Water Purification Plant & pipelines 500, 000 m3/day
Client: Construction Authority for Potable Water and Wastewater(CAPW)
IN ADDITION TO PREVIOUS RESPONSIBILITIES.
- Update schedule on weekly basis to monitor progress using Primavera P17.7.
- Issue weekly and monthly reports according to the updated schedule.
- Origin Bi-weekly report (Dashboard), issue management log, material tracking log, and one weekly look
ahead schedule report including target periodically.
- Monitor manpower and equipment histograms compared with planned resources.
- Operate and use Primavera P6 EPPM to monitor project progress in the lieu of the company resource pool and
its overall strategy.
- Prepare delay analysis reports for all claims that have been issued according to recorded events using Time
Impact Analysis and Impacted as Planned methods.
- Prepare all required and needed presentations to illustrate project progress and obstacles.
- Attend all weekly and monthly progress meetings with the company head office, client, and sponsor.
Hassan Allam Construction (Egypt) - Veolia Water Technologies (Egypt) Consortium to build and design a wastewater treatment plant 33000 m3/day, Repair and develop 5 Main pump stations and 3 Sub pump stations, Construct 2 new Sub pump stations, Gravity pipelines with a total length of 72, 300 m.l, Repair gravity pipelines with a total length of 22, 000 m.l and Force main lines with a total length of 28, 500 m.l. in Al-SINBLAWEN SUSTAINABLE RURAL SANITATION SERVICES Project for Dakahlia Water & Sanitation Company and The World Bank as a sponsor.
- Origin the baseline schedule loaded with the project budget, required resources, and
a narrative report including manpower and equipment histograms using Primavera P17.7.
- Update schedule on weekly basis to monitor progress using Primavera P17.7.
- Issue weekly and monthly reports according to the updated schedule.
- Origin Bi-weekly report (Dashboard), issue management log, material tracking log, and one weekly look
ahead schedule report including target periodically.
- Monitor manpower and equipment histograms compared with planned resources.
- Operate and use Primavera P6 EPPM to monitor project progress in the lieu of company resource pool and its
overall strategy
- Prepare delay analysis reports for all claims that have been issued according to recorded events using Time
Impact Analysis and Impacted as Planned methods.
- Prepare all required and needed presentations to illustrate project progress and obstacles.
- Attend all weekly and monthly progress meetings with the company head office, client, and sponsor.
Hassan Allam Construction (Egypt) to repair and develop 2 Main pump stations and, Construct 2 new Sub pump stations, Gravity pipelines with a total length of 28, 000 m.l, Repair gravity pipelines with a total length of 22, 000 m.l and Force main lines with a total length of 10, 500 m.l.
In MEET AL-AMEL SUSTAINABLE RURAL SANITATION SERVICES Project for Dakahlia Water & Sanitation Company and The World Bank as a sponsor.
IN ADDITION TO THE PREVIOUS RESPONSIBILITIES
- Review Daily reports and compare them with look-ahead schedules.
- Review and assess baseline schedule and updated schedule based on DCMA-14 points using Primavera P17.7.
- Review Weekly and Monthly reports and check the KPI's generated by the main contractor.
- Prepare Monthly schedule for the client and the sponsor with KPI's from consultant point of view.
EHAF Consulting Engineers supervise and monitor all main contractor's activities (SIAC) in behalf of the client (Al-Azhar El-Sharif) and the sponsor (Ministry of Presidential Affairs (MOPA)-UAE) with cooperation with RW ARMSTRONG to construct AL-AZHAR NEW
LIBRARY-Cairo
- Collect data from site and monitor performance rates.
- Participate in preparing method statement for different zones of the project.
- Prepare interim schedules for different zones of the project loaded by driving resources and items' quantities using MS Project.
- Quantity surveying for all zones of the project using cad drawings and MS Excel.
- Prepare weekly revenue and participate in preparing monthly statement.
- Prepare daily report and participate in preparing weekly and monthly reports.
- Prepare as-built schedule loaded by manpower, equipment and quantities using Primavera P6.8.2.
Trevi (Italy) - Arab Contractors Company (Egypt) Joint Venture construct all foundations and diaphragm walls needed in Tunnels under Suez Canal project - South Port Said.
- Prepare baseline schedule loaded by resources for package 3 and 4 using Primavera P6.8.2.
- Prepare narrative resource report and generate resources histograms for package 3 and 4.
- Collect data from site and prepare daily reports and update the schedule using these data.
- Prepare 15-days look-ahead schedule using Primavera P6.8.2 for weekly meetings.
- Prepare monthly progress reports contained the updated schedule, all required earned value KPI's, S-curves, resources narrative report and photographic reports.
- Use earned value tool for monitoring performance without using Primavera P6.8.2.
- Prepare presentation for monthly progress meetings, and coordinate with my colleagues from Hitachi and OTV to issue the final updated schedule and monthly progress presentation.
- Organize and participate in weekly meetings in Iraq and monthly progress meetings in Dubai (Hitachi's offices).
- Participate in preparing documents for claims that had been submitted to the client and to the other members in the joint venture and illustrated the effect of events on the project baseline using window analysis method.
- Project Coordinator in Dubai (Hitachi offices).
HITACHI (Japan)- OTV (France)- Arab Contractors Company (Egypt) joint venture supply,
install, construct, operate and maintain of RO plant capacity of 199000-meter cubic/day and 132 kV / 33 kV GIS substaon.
HITACHI for electrical and electronics works - OTV for mechanical works - Arab Contractors Company for civil and erection works
At El-Hartha site in Basrah water supply improvement project/package 3 and 4.
- Check, review all bidding documents especially drawings and quantity surveying items.
- Analyze and decompose bidding items for pricing.
- Collect data for material prices from expected vendors.
- Collect data for labor and equipment prices.
- Cost estimate for biding items and calculate contingency and profit to calculate items' prices.
- Prepare tender documents include the priced bill of quantity.
Tenders:
1. The new Suez general hospital.
2. Al-Amal factory for polyethylene pipelines in 10th
of Ramadan city.
3. Social habitation project (9 Buildings with car garage) in Suez.
4. Infrastructure project (sewer and water networks) in 10th of Ramadan city.
5. 15 grain silos - phase No.2 in Fayed - Ismailia.
- Prepare baseline schedule for contract scope.
- Prepare cash-flow according to the approved baseline.
- Update the schedule according to site performance and compare with baseline schedule.
- Prepare all technical letters which had been sent to the client.
- Prepare contractual documents for all subcontractors.
- Quantity surveying all items that had been implemented.
- Prepare Re-bar bending schedule for skeleton.
- Prepare detailed sketches for site engineers.
- Prepare the monthly payment certificates for the client with all required documents.
- Prepare the interim payment certificates for all subcontractors.
- Cost monitoring using code of accounts for inventory, subcontractors and other financial burdens.
- Prepare comparison balance for incomes and outcomes.
- Prepare final payment certificates with all required documents, final quantity surveying calculation sheets and handover letters that had been submitted to the client.
The Arab Contractors company supply, install and construct 11 commercial buildings and 3
clinic complexes within the scope of The National Habitation Project.
- Prepare contractual documents for subcontractors.
- Quantity surveying items that had been implemented.
- Prepare the monthly payment certificates for the client with all required documents.
- Prepare the interim payment certificates for subcontractors.
The Arab Contractors company supply, install and construct 22 buildings (5-storey buildings) within the scope of The National Habitation Project.
- Managing skeleton, masonry, finishing works.
- Setting out and organizing site.
- Checking technical designs and drawings to ensure that they are followed correctly.
- Supervising subcontractor staff.
- Ensuring project had met agreed specifications, budgets and time schedule.
- Liaising with clients, subcontractors and other professional staff, especially quantity surveyors and the overall project manager.
- Providing technical advice and solving problems on site.
The Arab Contractors company supply, install and construct 22 buildings (5-storey buildings) within the scope of The National Habitation Project.
- Managing skeleton, masonry, finishing works.
- Setting out and organizing site.
- Checking technical designs and drawings to ensure that they are followed correctly.
- Prepare Re-bar bending schedule for skeleton.
- Supervising subcontractor staff.
- Ensuring projects meet agreed specifications, budgets or timescales.
- Liaising with clients, subcontractors and other professional staff, especially quantity surveyors and the overall project manager.
- Providing technical advice and solving problems on site.
The Arab Contractors company supply, install and construct Faculty of Engineering buildings - petroleum and mining department - Suez University Project.
Implement structural design, structural drawings, and inspect a veterinary unit and a post-harvest
center for CARE-Egypt (USAID), and prepare preliminary design and bill of quantities for a 3-storey school building for COSPE (Italian organization)
- Implement and inspect acvies for construcon "5" ammunition store buildings and "1" tanks hangar for The Egyptian Armed Forces.
- Implement and inspect acvies for construcon "1" electrical panel building in addition to its fences and gates for Ismailia Electricity Distribution Company.