Total years of experience :38 years, 1 Months

Director, Marine & Civil Construction at Advanced Consulting and Marine Technology
  • United Arab Emirates - Abu Dhabi
  • My current job since May 2020

An Integrated Marine Solutions Provider Company offering Shipyards a wide range of Marine Services. www.acmtuae.com
Responsible for all aspects of Marine and Civil Construction business unit in partnership with the company CEO to provide Clients with value added services to enhance production and capacity. Selected achievements include Yas Marina piling and Pier construction; major repair and new construction of quay wall in Mussafah for Oilfield Services; and Milaha Shipyard’s Qatar expansion proposal for project management and site supervision. (shiplift upgrade, dredging, new quay wall, and upgrade to construction halls)

OPERATIONS & MAINTENANCE SECTOR CONSULTANT at ROYAL COMMISSION IN JUBAIL
  • Saudi Arabia - Eastern Province
  • December 2018 to April 2020

Reporting and providing consultation and advice to the General Manager, Operation and Maintenance Directorate. Duties include: analysis and tracking the annual maintenance budget (SAR 650 m); management of the Infrastructure Asset Inventory and Condition Assessment; and implementation of a world class Enterprise Asset Management System to improve the efficiency of maintaining the city assets to achieve a saving of SAR 1.5B by the year 2030.

UAE Program Manager at Cubic Corporation
  • United Arab Emirates - Abu Dhabi
  • February 2017 to July 2018

Responsible for the management, performance, profit/loss, business development and completion of all aspects of Cubic Global Defense Inc. single or multiple projects in the region.
SELECTED CONTRIBUTIONS
Follow on Contract ITS O&M: Managing 40 system’s operators spread over 31 military sites across the UAE for the follow on Indoor Training Simulation (ITS) System Contract with UAE GHQ Armed Forces.

Projects Manager at BAE Systems
  • Australia
  • October 2012 to July 2016

Responsible for all Henderson shipyard upgrade projects and procurement of equipment. In addition, I managed the shipyard facilities overhead budget of over $8m yearly, run the maintenance department of 15 personnel, and set out the asset management plan across the Henderson Business Unit.

Projects completed were in excess of AUD $35m including:

• New Dry Berths and Turntable extension: This project was to increase the ship repair capabilities. I overcame a particular difficulty of encountering unexpected very hard rock during excavation by getting a revised design to the foundation that required less excavation; and I managed to keep the project on time and budget.
• New Heavy Lift Wharf (Capable of 1, 600 tons capacity): I increased the width, strength and provided a much enhanced bollards capacity for the same capital budget that was initially approved for a smaller 450 tons capacity wharf.
• Dredging to -6.0m CD: Key achievement was obtaining the development approval from numerous external stakeholders including: Fremantle Ports, Environmental Protection Agency, LandCorp, Local Council, and Joint Assessment Panel for projects over AUD $7m.
• New Office Building: A modern 2 story office building with a capacity for 110 Staff.
• New Wet Berth Mooring Piles and Fenders: Designed and constructed for use by our Oil & Gas Client’s barges in a record time of 6 weeks. I established a strong partnership with our contractor to overcome all obstacles and get this project completed on time and budget.

Equipment procured includes: 275 ton Crawler Crane (Sumitomo), 85 ton Rough Terrain mobile crane (Tadano), 450 ton Crawler Crane (Kobelco), Forklifts, manlifts, warehouse trucks, Steel fabrication and welding equipment, etc

Principal Infrastructure Consultant at ROYAL HASKONING
  • United Arab Emirates - Dubai
  • August 2011 to August 2012

ROYAL HASKONING, Dubai/Abu Dhabi, http://www.royalhaskoning.com
Royal Haskoning is an international consultant specialising in maritime, shipyards, and industrial facilities with over 3900 staff all over the world.
Principal Shipyard Consultant, Aug 2011 till date
• Representing the company's shipyard sector in the GCC and reporting to the Global Shipyards Director in the UK. Registered the company with various government authorities including CNIA and ADPC, and actively developing close relationships with all major GCC shipyards including: Nakilat Shipyard Qatar, ASRY, BASREC, AHI, and Drydocks World.
• Managing regional shipyards infrastructure projects including: Damen Shipyards Sharjah (employer's requirements for construction, conservation and workshops sheds; and site wide utilities distribution); Goa Shipyard Modernisation (design reviews of fire fighting system, potable water distribution, welding gases storage and distribution, pipe pickling plant, and services distribution inside workshops); and Topaz Engineering (new shipyard master plan proposal, and facilities operational enhancements)

Facilities Manager at ABU DHABI SHIP BUILDING CO
  • United Arab Emirates - Abu Dhabi
  • January 2003 to January 2011

ABU DHABI SHIP BUILDING CO, Abu Dhabi, http://www.adsb.net
ADSB is engaged in building and repairing naval and commercial ships and vessels.

Facilities Manager, 2003 till 2011
• Report to the VP Engineering and manage the civil, mechanical and electrical engineering departments.
• Coordinate and manage all shipyard expansion contracts, major and minor capital expenditure projects, and plant improvement projects, processing on average 200 requests a year ranging from procurement of new production equipment to small refurbishment projects.
• Manage the effective delivery of plant maintenance services entertaining over 1400 maintenance requests per year including planned maintenance and repairs, tracking progress on a computerised maintenance management system.
• Manage several concurrent expansion projects including 155 m quay wall extension (contractor: Dutco Balfour Beatty) 3-storey administrative building and a twin warehouse.
• Completed contracts valued at AED 450 m including contracts for developing a master plan, detailed design and value engineering, dredging, fabrication and installation of a 2000t Syncholift for lifting ships and marine and heavy civil works and construction of industrial workshops, administrative offices and camp facilities.

Site Project Manager at ABU DHABI SHIP BUILDING CO
  • United Arab Emirates - Abu Dhabi
  • January 1999 to January 2003

Site Project Manager, Shipyard Construction, 1999 to 2003
• Coordinated the construction of shipbuilding facilities including 90 m ship lift piers, a 70 m quay wall, a 4 rail system serving several dry berths and a side transfer pit, and a 37 m high, 68 m wide ship construction hall with 35 t overhead cranes.
• Led a site team of engineers, inspectors and surveyors drawn from Halcrow, the consultant and DG Jones and Partners, the quantity surveyors along with in-house engineers and surveyors.
• Coordinated the work at site of multiple contractors like Overseas AST Arabtec JV, Al Hamed, Square General and ASCON maintaining cohesiveness in project execution.
• Played a key role in the project from concept design to commissioning and completed all contracts within budget and with highest standards of quality.

Senior Facilities Engineer at ABU DHABI SHIP BUILDING CO
  • United Arab Emirates - Abu Dhabi
  • January 1997 to January 1999

Senior Facilities Engineer, 1997 to 1999
• Managed facilities process teams with members from the production department, First Marine International (shipyard consultant), and Halcrow and Parsons Brinkerhoff (civil and MEP designers) to finalize overall dimensions, layout and services required.
• Managed the process of selection of consultants through RFPs and contractors through tender documents.

Resident Engineer at LAHMEYER INTERNATIONAL
  • United Arab Emirates - Al Ain
  • January 1995 to January 1997

LAHMEYER INTERNATIONAL, Abu Dhabi, http://www.lahmeyer.de/en
The Lahmeyer Group is one of the largest independent German engineering companies, with headquarters in Bad Vilbel near Frankfurt am Main. For over 40 years they have been active in more than 140 countries as consultants, technical experts and project managers in all infrastructure fields.

Resident Engineer, 1995 to 1997
• Successfully completed civil works for erection of 33 kV overhead transmission lines in Abu Dhabi and Al Ain for the Abu Dhabi Water and Electricity department at a value of AED 850 m.
• Managed all technical, financial and contractual aspects for the project involving soil investigation, construction of 85 km of access roads, installation of piled foundations and erection of 850 double circuit towers.

Technical Manager at MIDMAC CONTRACTING COMPANY
  • Qatar - Doha
  • January 1994 to January 1995

MIDMAC CONTRACTING COMPANY, Doha, Qatar, http://www.midmac.net
MIDMAC is one of the largest Qatari contracting organizations employing a total workforce of over 6, 000 employees. It has a proven track record for delivering large and challenging projects on schedule, within budget, and according to required quality & specifications.

Technical Manager, 1994 to 1995
• Managed the execution of the civil works package for the QAFCO III expansion project covering installation of 2, 500 bored piles, foundations for urea and ammonia plants, 5 control buildings and a seawater pump house.
• Developed subcontractor's packages for concrete protection, painting and cladding based on FIDIC and local conditions of contracts.

Section Manager at MIDMAC CONTRACTING
  • Qatar - Doha
  • January 1993 to January 1994

Section Manager, 1993 to 1994
• Led a team of section engineers and foremen in executing civil works for the construction of the Ras Abu Fontas 'B' gas turbine power project. Installed pedestals for 5 120 kV gas turbines with associated foundations, 5m high columns, cable tunnel, chimneystacks and silencers. Executed the concreting of pedestals in 500 m3 pours over 10 hour periods with thermal insulated curing.
• Responsibilities included organization of all resources including machinery and manpower, development of construction method statements and design of formwork and monitoring and ensuring achievement of project milestones.

Project Manager at MIDMAC CONTRACTING COMPANY
  • Qatar - Doha
  • January 1993 to December 1993

Project Manager, 1993
• Project: Doha Golf Course, Qatar: Construction of 18 and 9 hole golf courses involving excavation, hauling and backfilling of 400, 000m3 of soil and hard rock; importing of 300, 000m3 of dune sand for tree mounds; construction of 88, 000m2 of lined lakes with associated waterfalls, wires and bridges; and the construction of 3000m of drainage lines.
• Looked after all financial and contractual aspects of the project including planning, procurement of materials, submission of monthly valuations and final accounts including claims.
• Monitored work at site and coordinated with architects and resident engineers to ensure targeted outputs from labour and plant and complete the project on time.

Design Engineer at TRAFALGAR HOUSE
  • United Kingdom
  • January 1991 to December 1992

TRAFALGAR HOUSE, London UK (now a part of Aker-Kvaerner, http://www.akersolutions.com)

Design Engineer, 1991 to 1992
• Project: Stabilization of Kingston Bridge, London: Conducted analysis of piling and retaining walls, calculated settlement and bearing capacity, determined slope stability and recommended ground treatment solutions.

Senior Site Engineer at TRAFALGAR HOUSE
  • United Kingdom
  • January 1989 to January 1991

Senior Site Engineer, 1989 to 1991
• Project: An office building at 101 Martin's Lane London: The project covered demolition of the existing building, installation of a secant pile wall, excavation of a deep basement and construction of a new building with 12 reinforced concrete floors.
• Supervised subcontractors and own labour and coordinated all temperorary work and planned sections of the work and monitored progress at site.
• Liaised with environmental and health inspectors, District Surveyors, architects, designers and resident engineers to resolve issues and ensure adherence to project schedules.

Senior Site Engineer at JOHN LAING CONSTRUCTION
  • United Kingdom
  • January 1988 to January 1989

JOHN LAING CONSTRUCTION, London UK, http://www.laing.com

Senior Site Engineer, 1988 to 1989
• Participated in the construction of the Guardian Royal Exchange, a £40 m refurbishment project in London. The project called for demolition of interiors while retaining the exterior facade and construction of a new reinforced concrete frame.
• Ensured safe and smooth progress by exercising extreme caution, careful planning and adherence to health and safety regulations.

Site Engineer at JOHN LAING CONSTRUCTION
  • United Kingdom
  • January 1985 to January 1988

Site Engineer, 1985 to 1988
• Project: City Harbour, a £80 m business centre in the Docklands involving installation of 2000 piles, construction of 5 buildings, a structural steel frame car park, associated access roads and services: Was responsible for installing bored and driven cast in situ piles, foundations and all structural frames.
• Project: Westworld, a10-storey office building in Ealing: Managed all structural work including installation of 1.5 m diameter under-reamed bored cast in situ piles, foundations and all reinforced concrete structural works employing jack-up tables and cup-lock scaffolds for supporting soffits.

Education

Master's degree, Civil Engineering
  • at Case Western Reserve University
  • January 1985

• Master of Science, Civil Engineering, Case Western Reserve University, USA, 1985. Honours. Fully sponsored by the US Army Research Office.

Bachelor's degree, Engineering
  • at Case Western Reserve University
  • January 1984

• Bachelor of Science in Engineering, Civil Engineering, Case Western Reserve University, USA, 1984, Honours, GPA: 3.6

Specialties & Skills

Project Management
Maintenance Management
CONCRETE, STRUCTURAL STEEL WORKSHOPS
PROJECT MANAGEMENT, CONTRACTS
DREDGING, PILING, MARINE STRUCTURES
SITE WIDE UTILITIES, INFRASTRUCTURE
MAINTENANCE
PLANT MAINTENANCE
PRODUCTION EQUIPMENT
PROGRESS, MONITORING, AND CONTROLLING PROJECTS
Master Planning
Facilities
Program Management

Languages

Arabic
Expert
English
Expert
Spanish
Intermediate

Memberships

American Society of Civil Engineers (MASCE)
  • Full Member
  • June 2001
Project Management Institute (PMI)
  • PMP
  • January 2008

Training and Certifications

PMP (Project Management Professional) (Certificate)