Operation coordination O&M In-charge Satellite Power Stations.
Qatar Electricity and Water Company.
Total years of experience :39 years, 2 Months
A) Worked independently (satellite) without errors.
Saliyah 2x62 MW GE Frame-9 IB GTs controlled by Mark-VIe.
Doha South super 1x68 MW frame -9-I B GT controlled by Mark-Vie.
Al-Wajbha 1x64 MW GE Frame-9-I B GT controlled by Mark-VIe and 2x117 MW SIEMENS V94.2 GTs Controlled by Teleperm-ME.
Coordination between Station and NCC for GT Synchronization, De-synchronizations and isolations.
B) As these three satellite stations are black start capable, I have to make sure that our BSDs are healthy to meet the emergencies of the State of Qatar.
C) Scheduling of maintenance, isolation and preparation of the equipment for safe maintenance and cancel the isolations after maintenance.
D) Monitoring, control and operations of 4x68 MW GE Frame - 9B GTs, 2x117MW V94.2 SIEMENS GTs.
E) Record and analyze the problems in the above system.
F) Making of DCMS and Security Passes.
G) Preparation of trip reports, daily reports, weekly report and monthly report.
H) Manpower planning, Leave Management.
I) To check the healthiness of Fire Fighting system of station and GTs and safety of MAN & MACHINES.
Planning and Scheduling Management Process that plans project activities, monitors
completion of those activities, predicts timing of future activities, and reports schedule status.
Scheduling of maintenance, isolation and preparation of the equipment for safe maintenance and cancel the isolations after maintenance.
Record and analyze the problems in the above system.
Making of DCMS and Security Passes.
Preparation of trip reports, daily reports, weekly report and monthly report.
Manpower planning, Leave Management.
Participated in erection and commissioning and testing of GE Frame-9FA 3x260MW Controlled by Mark-VI.
Also Participated in GT Start up Shutdown, 220GIS, 11KV, 0.4KV Breaker protection and interlock test, GT protection test, Generator protection test, Generator transformer protection testing, Station transformer protection and interlock test and interlock, BOP Fuel gas, Evaporative cooler, CCCW, and H2 generator & Co2 System performance test.
Participated in Startups, Shutdowns, Routine operations, Isolations, de-isolations, trouble shooting of 5x125.5 MW GT13E2, 5x315T/H WHRB, 2x315T/H Dump condenser controlled by DCS Procontrol-P. Fuel gas system, Fuel gas compressor house, UPS system, Battery chargers, SFC, 0.4KV, 2.1KV, 3.3KV, 11KV, 132KV and 220 KV systems.
Participated in erection and commissioning and testing re-commissioning of RAF-B1 Fuel gas system & ALSTHOM 3x125.5 MW GT13E2 controlled by DCS Advant Power control. Follow up, test checks.
Operating & controlling the two combined cycle block having four numbers of GE Co. USA frame-9E, Gas Turbine and, two number of stag 209-E steam Turbine each 100 MW along with four HRBs, with the controlling SPEED TRONIC MARK- II & IV, DATA TRONIC & DCS SYSTEM.
One combined cycle block having Two numbers of V/94 SEIMENS KWU Gas Turbines and one number of steam turbine, each 150 MW along with two HRBs with the controlling through schematic, telepram-E and madam-S controlling and monitoring system.
11/15/132/220/500KV switching distribution and operation control.