Project Manager, Nobles 101 complex:
-Perform on-site inspections for quality of workmanship, quality of materials, conformity with plans & specifications, code compliance, on-site safety, project schedule vs progress, and general progress of the project.
-Attend, or conduct, construction meetings with contractor, architect, and major subcontractors that are on site.
-Review progress billings and when necessary negotiate revisions.
-Prepare and review contracts with the selected consultants, contractors and vendors
-Review plans and specifications for suitability; quality; building code compliance; fire code compliance and budget.
-Ensure a reasonable, realistic, budget is developed and maintained without compromising the quality or integrity.
-Report directly to the head of engineering department and the CEO
-Manage the design and construction
-Defect management using SnagR for the first time in Syria, Lebanon and Jordan.
-Ensure all lien/claim releases are executed with all progress and final payments.
-Project close out.
-Assist with Post-Occupancy.
- Report directly to the Senior Project Manager
- Assist with controlling the Project Programmes and Costs
- Coordinate with the Design Team on all aspects of the Design
- Raise relevant correspondence on assigned project as directed
- Assist in preparing any Project Reports as required by the line manager
- Assist the Project Director and Senior Project Manager with completing and handing over the project to the client in the manner so required and to ensure a smooth transition of demobilization by all parties
- Assist the Project Director and Senior Project Manager with ensuring all project documentation is correctly archived throughout the correct channels and procedures with EDARA Head Office
- Assist with post completion/defects liability issues
- Suggest value engineering solutions where possible and to the benefit to the project
- Suggest solutions that will be beneficial to the overall success of EDARA
- Insure that best practice Health and Safety procedures are enforced at all times
-Initiating project and develop project charter
-Planning project tasks and create WBS
-Direct and manage projects execution after the concept stage
-Information distribution
-Request seller responses
-Select sellers
-Monitor and control project work
-Perform quality control
-Manage project team
-Contract administration
-Close project
-Contract closure
1-Royal Ascot Hotel, Dubai- Project manager
Developing the preliminary architectural and interior designs
Coordinating with client, main consultant and main contractor
Preparing working drawings and selecting finishing material
Nominating subcontractors and following sum Items with the suppliers.
Site supervising and attending meetings
2- Jeddah Gate Towers for Emaar, Jeddah - Project manager
Studying the architectural drawings and preparing the interior design
Coordinating with client and main consultant
Preparing interior design drawings and specifying finishing materials, light fittings and furniture
Managing a team of 10 architects and draftsmen
3- Omniyat Properties Headquarter, Dubai -Project Manager
Developing the interior design
Preparing shop drawings and details
Coordinating with client, landlord and the PM company
4- Crown Plaza Hotel in, Dubai- Architect
Documenting the interior design proposed by an international design studio
Preparing detailed interior design drawings for all guest rooms
Finalizing finishing materials’ details and specifications
5- G+52 Majestic tower, B+G+25 Al Burj tower and G+10 residential buildings, G+2 offices building in Dubai Airport Free Zone, G+1 offices building, B+G+1 palace and A ground floor Villa- Architect & owner representative
Developing architectural and interior designs with the clients
Preparing presentation renderings & shop drawings
Obtaining approvals from the authorities like (Dubai, Sharjah municipalities and Dubai Air port free Zone)
Selecting finishing materials
Getting quotations for different sum Items.
Managing site meetings and site supervising
Preparing snagging list
Handing over projects
I traveled to Riyadh- Kingdom of Saudi Arabia for lunching the first tower owned by khamas Group in Sharjah (Al Burj Tower).
I traveled to Beirut- Lebanon to study renovating a luxury penthouse and to nominate the ID studio that will prepare the interior design study.
Projects: G+15, G+3 Residential buildings, hotels, villa complex and warehouses
Job Description:
-Designing residential buildings, hotels and warehouses
-Preparing 3D perspectives for residential buildings and villas
Projects: Multi stories buildings, Villas, Mosques and hotels.
Job Description:
-Preparing schematic and preliminary designs
-Rendering 3D perspectives
-Preparing working drawings and obtaining approvals from Sharjah municipality and authorities
-Meeting clients
-Coordinating with civil and MEP engineers
-Site supervising
Project: Renovation The ancient University of low - Damascus, Syria
Job Description:
-Site survey and preparing a report about the old building situation
-Preparing detailed drawings highlighting the damaged components that needs repairing
5 years, faculty of Architecture