مدحت السيدعلى محمد يوسف يوسف, Senior Electrical Power Supply

مدحت السيدعلى محمد يوسف يوسف

Senior Electrical Power Supply

SYSTRA

البلد
مصر
التعليم
بكالوريوس, ELECTRICAL
الخبرات
28 years, 5 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :28 years, 5 أشهر

Senior Electrical Power Supply في SYSTRA
  • المملكة العربية السعودية - الرياض
  • أشغل هذه الوظيفة منذ ديسمبر 2013

Riyadh Metro Line 3 - P2 is consist of 22 stations, two depot and 6park &ride 9
Stations are deep underground stations, 3 stations are shallow stations and 10 stations
Are elevated stations on via duct total length of line 3 about 43 KM.My responsibility Supervise and followup design and construction team to achieve the following:-
* Power supply simulation report
* Medium Voltage Switch gear (33KV - 22KV - 15KV-11KV (Calculations - Installation - Testing )
* Medium Voltage Cables (33KV - 22KV - 15KV-11KV )(Sizing - Installation - Testing )
* Traction Cables 750V DC(Sizing - Installation - Testing )
* Traction transformer (Sizing - Installation - Testing )
* Rectifier Stations 590V / 750V DC(Sizing - Installation - Testing )
* DC Switchboard 750V DC(Sizing - Installation - Testing )
* DC Positive and Negative Dis connector Switches 750V DC
(Sizing - Installation - Testing)
*Stray Current system
* Auxiliary transformer (Sizing - Installation - Testing )
* Standby Diesel Generator (Sizing - Installation - Testing )
*UPS System (Sizing - Installation - Testing )
* CBS System (Sizing - Installation - Testing )
* Earthing and bonding system for rail projects
(Sizing - Installation - Testing)
* Low voltage Cables (Sizing - Installation - Testing )
* Race way systems for Cables (Sizing - Installation )
* Low Voltage Switch gears MDB, MCC, SMDB and DB
(Load Schedules - Sizing - Installation - Testing )
* Short Circuit Calculations for Medium Voltage, Dc Traction and LV Systems
* Lighting calculations for indoor and outdoor
* * Low voltage cable sizing and voltage drop calculations
* Earthing calculations
* Lightning Protection Report.
* Panel board load schedules calculations
* Cable tray sizing calculations
* Lighting system drawings
* Small power system drawings
* Single Line Diagram Drawings
* LV Cables Routes system drawings
* Fire alarm system Drawings
* Technical Specifications of all Electrical items.
* Material approvals of all Electrical items.
* Methods of statement installation of all Electrical items
* Testing and commissioning procedures of all Electrical items
* Supervise and followup construction team

Senior MEP في SYSTRA
  • الإمارات العربية المتحدة - دبي
  • نوفمبر 2012 إلى نوفمبر 2013

Dubai Tram project consist of 11 stations and one Depot total Length 12 KM my responsibility Supervise and follow up design and construction team to achieve MEP and Power Supply System items
- Power supply simulation report for rail projects
- Medium Voltage Switchgear (33KV - 22KV - 15KV-11KV )
(Calculations - Installation - Testing )
- Medium Voltage Cables (33KV - 22KV - 15KV-11KV )
(Sizing - Installation - Testing )
- Traction Cables 750V DC(Sizing - Installation - Testing )
- Traction transformer (Sizing - Installation - Testing )
- Rectifier Stations 590V / 750V DC(Sizing - Installation - Testing )
- DC Switchboard 750V DC(Sizing - Installation - Testing )
- DC Possitive and Negative Disconnector Switches 750V DC
(Sizing - Installation - Testing)
- Stray Current system
- Auxiliary transformer (Sizing - Installation - Testing )
- Standby Diesel Generator (Sizing - Installation - Testing )
- UPS System (Sizing - Installation - Testing )
- CBS System (Sizing - Installation - Testing )
- Earthing and bonding system for rail projects
(Sizing - Installation - Testing)
- Low voltage Cables (Sizing - Installation - Testing )
- Race way systems for Cables (Sizing - Installation )
- Low Voltage Switchgears MDB, MCC, SMDB and DB
(Load Schedules - Sizing - Installation - Testing )
- Short Circuit Calculations for Medium Voltage, DCTraction and LV Systems
Lighting calculations for indoor and outdoor
- Low voltage cable sizing and voltage drop calculations
- Earthing calculations
- Lightning Protection Report.
- Panel board load schedules calculations
- Cable tray sizing calculations
- Lighting system drawings
- small power system drawings
- Single Line Diagram Drawings
- LV Cables Routes system drawings
- fire alarm system Drawings
- Technical Specifications of all electrical power supply systems items.
- Material approvall of all electrical power supply systems items.
- Methods of statement installation of all electrical power supply items.
-Testing and commessioning procedures of all electrical power supply items.
- Supervise and following up electrical and mechanical construction team

Team leader في ARAB CONSULTANT ENGINEERS
  • مصر - القاهرة
  • نوفمبر 2009 إلى أكتوبر 2011

Greater Cairo metro project Line 3 - phase 3 consist of three phases Phase 3A from ATTABA TO KITKAT SHAFT total length 5km included 4stations and 5 annexed structure Nasser station - maspero station - zamalek station - kit kat station .Annexed structure (3A-1) - Annexed structure (3A-2) - Annexed structure (3A-3). Annexed structure (3A-4) - Annexed structure (3A-5) - kit kat diversion shaft Phase 3B from kit kat shaft station to ring road station total length 4km included 5 stations and 4 annexed Structure. Sudan station - almonira station - imbaba station elwehdastation - ring road station - Annexed structure (3B-1) - Annexed structure (3B-2) .Annexed structure (3B-3)-Annexed structure (3B-4) Phase 3C from kit kat shaft to Cairo university station total length 5km included 5 stations and 5 annexed Structure. Tawfikia station - wadielnile station - shehab station - boulaq station - cairo University station -annexed structure (3C-1) - Annexed structure (3C-2)
Annexed structure (3C-3) Annexed structure (3C-4) - Annexed structure (3C-5)

Greater Cairo metro project Line4 from elmalek elsaleh station to hadaekel ahram Station Total length 17.5 km included 16 stations.Elmalek Elsaleh station - Elroda StationElgiza square station - Elgiza station - Elmesaha square station - madkour
StationEltalbea station - Elmatbaa station - Elareash station - Maryoutia station Alahramat station - Elremayah station - G.E Museum station - Elnasr stationHadaekelahram station - hadaekelahram station.

My responsibility Supervise and following up design team to achieve the following documents:-
1. Design Drawings of Public utility diversion for 220kv cables, 66kv cables, 11kv cables, low voltage cables 380v and 220v and Telephone network.
2. Task description of Public utility diversion for 220kv cables, 66kv cables, 11kv cables, low voltage cables 380v and 220v and Telephone network .
3. Bill quantity of Public utility diversion for 220kv cables, 66kv cables, 11kv cables, low voltage cables 380v and 220v and Telephone network .
4. Technical specifications for 220kv cables, 66kv cables, 11kv cables, low voltage cables 380v and 220v and Telephone network .
5. Design cariteria of lighting and small power system for stations and annexed structure
6. Technical specifications of lighting and small power system for stations and annexed structure.
7. Design drawings of lighting and small power system for stations and annexed structure.
8. Design drawings of cables route system for stations and annexed structure.
9. Design drawings of single line diagram system for stations and annexed structure.
10. Cable sizing, voltage drop and short circuit calculations for stations and annexed structure.
11. Lighting calculations by software program ( DIALUX ) for stations and annexed structure.
12. Load schedule calculations for stations and annexed structure.
13. Bill quantity for stations and annexed structure

Senior Electrical Power Supply في SYSTRA
  • الإمارات العربية المتحدة - دبي
  • نوفمبر 2007 إلى نوفمبر 2009

Project Overview : Dubai metro project consist of Red Line total length 32km, 28 stations 4 stations underground and 24 elevated stations, and 3 independent traction power stations. Green line total Length 20 km 20 stations 6 underground stations and 14 elevated Stations. 2 independent traction power stations.Three main powers Substations MPS1, MPS2 and MPS3.Three Depot jebel Ali depot, Alrashidiya depot and Alqusais depot.Three car parks. Jumira car park with capacity 3000 cars, rashidyia.Car park with capacity 3000 cars and Alqusis car park with capacity 2000 cars

My Responsibilities : Supervise and following up design and construction team to achieve design, installation, testing and commissioning for the following items :-
1. 33 kv switchgear ( G.I.S )
2. Auxiliray Power transformer dry type 500 KVA, 1000 KVA, 1500 KVA, 2000 KVA and 2500 KVA.
3. Rectifier transformer 2700 KVA . 33 kv / 590 v.
4. Rectifier unit 2500 kw. 590 vac / 750 v DC
5. DC Switchboard
6. DC Chopper
7. BRU breaking resistance unit
8. UPS 10 KVA, 50 KVA, 100 KVA and 200 KVA UPS
9. Battery and battery charger
10. Main low voltage switch gear
11. Intermediate terminal board ( I.T.B )
12. 33 kv cables, 750 v Traction Cables, 590 v cables, 400v / 230 v cables and 110v DC cables
13. Lighting calculations
14. Cable sizing and voltage drop calculations
15. Short circuit calculations
16. Load schedule calculations
17. Earthing system calculations
18. Cable tray size calculations
19. Transformer sizing calculations
20. Generator sizing calculations
21. Ups sizing calculations
22. Battery and battery charger sizing calculations
23. Design drawings for lighting and small power system.
24. Design drawings for single line diagram.
25. Design drawings for cables route.
26. Design drawings for earthing system.
27. Design drawings for lightning protection system.
28. Bill quantity
29. Manage and guide site engineers
30. Review and approve material
31. Review technical specifications
32. Review detailed design, and shop drawings
33. Management of testing & commissioning activities
34. Review and approve method of statement
35. Follow-up with local authorities and service providers
36. Brief and update client on progress of MEP and ECS activities.
37. Coordinate the imlpementation of the BMS & E&M design

Senior Electrical Design Engineer في ACE Consulting Engineers
  • مصر - القاهرة
  • أغسطس 2004 إلى أكتوبر 2007

My Responsibilities : Supervise and follow up design team to achieve design reports, design drawings, calculations, bill of quantity and technical specifications for the following projects:-

Saudi Arabia Projects
1- Jabal Omar Project S3&S4
2- Safola Panda Distribution Center in - Riyadh

United Arab Emirates Projects

1- Dubai Metro Red & Green Line
2-Tram Dubai tender documents
3- AMWAJ RESORT UMM AL QUWAIN tender documents

Egypt Projects

1- Cairo Metro Line 3 tender documents
2- ADERA PROJECT
3- Noor Ala Noor Hospital
4- DAMAC Park Avenue
5- Royal Factory for Ceramic and Porcelains
6-Egypt Air Workshop for Heavy Engine Maintenance
7- HamamatPharaoon Resort in Sinai - Egypt
8- Courts South Cairo, Dekhela, Tall Elk peer and Mania - Egypt
9- Bags Plant for Cement Pack Elamiria Factory - Alexandria - Egypt
10- Hot & Cold Rolling Mill Project - Egypt
11- Hilton Nabq Resort SharmElsheikh
12- Dahshoor Project Ministry of Defender
13- American Express Bank Main Branch in Cairo.
14 - Rafah Port in Sinai
15 - Shark Insurance City in New Cairo City

Libya Projects

1. Noflia treatment plant
2. Zawia treatment plant
3. Noflia pump station
4. Tripoli fair networks
5. Zliten city networks
6. Wadan elfergan road Lighting system

Technical Office Engineer في Alexandria Companyfor Electrical Contractors
  • مصر - الإسكندرية
  • أكتوبر 1999 إلى يوليو 2004

Suppervise and following up MEP construction team for
Reviewing Shop Drawings, material approval,
method statement of installation and monthly
payment for the following projects:-

1 - Hilton Nabq Resort SharmElsheikh
2 - Dahshoor Project Ministry of Defender
3 - American Express Bank Main Branch in Cairo.
4 - Rafah Port in Sinai
5 - Shark Insurance City in New Cairo City

Site Engineer في Crown Home Consultant Office
  • مصر - شرم الشيخ
  • ديسمبر 1998 إلى سبتمبر 1999

Suppervise and following up MEP construction team for
Reviewing Shop Drawings, material approval,
method statement of installation and monthly
payment

Electrical site Engineer في ELAF COMPANY
  • المملكة العربية السعودية - مكة المكرمة
  • يناير 1995 إلى نوفمبر 1998

My Responsibilities : Suppervise and following up MEP construction team for Reviewing Shop Drawings, material approval, method statement of installation and monthly payment for the following projects:-
1. MakkahTechnicalCollege
2. Makkah Commercial Institute
3. Makkah Training Institute
4. MadinahTechnicalCollege

electrical power engineer في Menoufeya University
  • مايو 1994 إلى يناير 1994
Project في AL KHALYGEYA COMPANY
  • مصر
  • يناير 2004 إلى

1 and ADERA

MEP Manager
  • إلى
Manager في MEP
  • عمان
  • إلى

Design and review Ligting calculations for indoor and outdoor
Design and review transformer sizing calculations
Design and review Generator sizing calculations
Design and review Low voltage cable sizing and voltage drop calculations
Design and review UPS sizing calculations
Design and review CBS sizing calculations
Design and review Earthing calculations
Design and review Lightning Protection Report.
Design and review panel board load schedules calculations
Design and review cable tray sizing calculations
Design and review Ligting system drawings
Design and review smal power system drawings
Design and review Single Line Diagram Drawings
Design and review LV Cables Routes system drawings
Design and review fire alarm system Drawings
Review Technical Specifications of all Electrical items.
Review Material approvall of all Electrical items.
Review Methode of statement installation of all Electrical items
Review Testing and commessioning procedures of all Electrical items
Supervise and follow up MEP team

Senior في MEP
  • الإمارات العربية المتحدة
  • إلى
Project في U.A.E
  • الإمارات العربية المتحدة
  • إلى

Dubai Tram
Project Overview: Dubai Tram project consist of 11 stations and one Depot total Length 12 KM

في Noor Ala Noor Hospital
  • إلى

Project Overview: The hospital consists of Basement + Ground+ 7 floors total area about 45000 m2
350 Bed. The total powers for the project 6 MVA.

Engineer في RTA
  • الإمارات العربية المتحدة
  • إلى

Project Overview: Dubai metro project consist of Red Line total length 32km
28 stations 4 stations underground and 24 elevated stations
And 3 independent traction power stations. Green line total
Length 20 km 20 stations 6 underground stations and 14 elevated
Stations. 2 independent traction power stations.
Three main powers Substations MPS1, MPS2 and MPS3
Three Depot jebel Ali depot, Alrashidiya depot and Alqusais depot
Three car parks. Jumira car park with capacity 3000 cars, rashidyia
Car park with capacity 3000 cars and Alqusis car park with capacity
2000 cars

My Responsibilities : Member of design review, intallation, testing and commissioning
team to achieve the following :-

Shop drawings, test procuder, cable sizing and short circuit and earthing calculations of Traction power substation included the following :-
33 kv switchgear ( G.I.S )
Auxiliray Power transformer dry type 500 KVA, 1000 KVA, 1500 KVA, 2000 KVA and 2500 KVA.
Rectifier transformer 2700 KVA . 33 kv / 590 v.
Rectifier unit 2500 kw. 590 vac / 750 v DC
DC Switchboard
DC chooper
BRU breaking resistance unit
UPS 10 KVA, 50 KVA, 100 KVA and 200 KVA UPS
Battery and battery charger
Main low voltage switchgear
Intermediat terminal board ( I.T.B )
33 kv cables, 750 v Traction Cables, 590 v cables, 400v / 230 v cables and 110v DC cables
Lihgting calculations
Cable sizing and voltage drop calculations
Short circuit calculations
Load schedule calculations
Earthing system calculations
Cable tray size calculations
Transformer sizing calculations
Generator sizing calculations
Ups sizing calculations
Battery and battery charger sizing calculations
Design drawings for lighting and small power system.
Design drawings for single line diagram.
Design drawings for cables route.
Design drawings for earthing system.
Design drawings for lightning protection system.
Bill quantity
Manage and guide site engineers
Review and approve material
Review technical specifications
Review detailed design, and shop drawings
Management of testing & commissioning activities
Review and approve method of statement
Follow-up with local authorities and service providers
Brief and update client on progress of MEP and ECS activities.
Coordinate the imlpementation of the BMS & E&M design

في Royal Factory for Ceramic and Porcelains Egypt Air Workshop for Heavy Engine Maintenance HamamatPharaoon Resor
  • مصر
  • إلى

Courts South Cairo, Dekhela, Tall Elk peer and Mania - Egypt
Bags Plant for Cement Pack Elamiria Factory

الخلفية التعليمية

بكالوريوس, ELECTRICAL
  • في MENOUFIA UNIVERSITY
  • أغسطس 1994

Bachelors Degree

Specialties & Skills

Transformer
Low Voltage
Lightning Protection
CABLEADO
CONSULTING
CUSTOMER RELATIONS
ENGINEERING
LA CREACIÓN DE REDES
LEADERSHIP
LIGHTING
MICROSOFT OFFICE
MICROSOFT WINDOWS 2000
PROGRESS
cabling

اللغات

العربية
متمرّس
الانجليزية
متمرّس

العضويات

Egyptian Engineers Syndicate
  • 1. Egyptian Engineers Syndicate Member number 04/01164 approval degree Consultant
  • October 2012
2. Saudi Council of Engineers
  • Member number 209858 approval degree Consultant.
  • September 2014

التدريب و الشهادات

1. Electrical Systems Design (تدريب)
معهد التدريب:
SCHNIDER ELECTRICAL EGYPT
تاريخ الدورة:
January 2010
المدة:
160 ساعة
Value Engineer Course (تدريب)
معهد التدريب:
SAVE International
تاريخ الدورة:
January 2012
المدة:
160 ساعة
Value Engineer Course (تدريب)
معهد التدريب:
SAVE International
تاريخ الدورة:
January 2012
المدة:
160 ساعة

الهوايات

  • Reading , Traveling , outgoing with family and friends