Total des années d'expérience: 12 Années, 0 Mois
mai 2019
A À présent
Contracts and Claims Section Head
à Egyptian Union for Construction-El Hazek
Lieu :
Egypte - Le Caire
o Study and implement construction contract
o Organize a risk management plan
o Prepare and negotiate claims.
o Communicate with Employer through letters and submittals
o Manage the communication between the departments for variation orders
o Prepare and follow up on guarantees and taxation documents
o Study pre-award contract documentations
o Prepare the contract qualifications for negotiations
o Projects Studied:
Alburouj Project Parcels 1.05 and 1.11
Neighborhood D & E (Multi-Family), for Villette Project
Podium in the Central Business District in the New Capital
Factory for Helwan Company for Engineering Industries
IKEA MOA Civil Works
New Giza University and infrastructure
TABA Desalination Plant
EMAAR Nursery Plant Project
CBD Towers in New Capital
Neighborhood F (Multi-Family), for Villette Project
EMAAR, Marassi Sidi Abd El Rahman Project
Central Bank District Package 8 tower in the New Capital
ZED Towers, Phase B
Shedwan Gouna Village
Phosphate Plant Civil Works
Package 18 in the Central Business District
Block work and Plaster for Package 8 in the Central Business District
o Projects Operated:
Villette, Neighborhood D&E, SOREAL
Package 08 crescent towers, New Capital CBD, CSCEC
o Organize a risk management plan
o Prepare and negotiate claims.
o Communicate with Employer through letters and submittals
o Manage the communication between the departments for variation orders
o Prepare and follow up on guarantees and taxation documents
o Study pre-award contract documentations
o Prepare the contract qualifications for negotiations
o Projects Studied:
Alburouj Project Parcels 1.05 and 1.11
Neighborhood D & E (Multi-Family), for Villette Project
Podium in the Central Business District in the New Capital
Factory for Helwan Company for Engineering Industries
IKEA MOA Civil Works
New Giza University and infrastructure
TABA Desalination Plant
EMAAR Nursery Plant Project
CBD Towers in New Capital
Neighborhood F (Multi-Family), for Villette Project
EMAAR, Marassi Sidi Abd El Rahman Project
Central Bank District Package 8 tower in the New Capital
ZED Towers, Phase B
Shedwan Gouna Village
Phosphate Plant Civil Works
Package 18 in the Central Business District
Block work and Plaster for Package 8 in the Central Business District
o Projects Operated:
Villette, Neighborhood D&E, SOREAL
Package 08 crescent towers, New Capital CBD, CSCEC
février 2018
A mai 2019
Senior Contracts and Claims Engineer
à ASGC
Lieu :
Egypte - Le Caire
o Analyze construction contract
o Negotiate and prepare variation orders and variation order log
o Organize a risk management plan
o Prepare and negotiate claims.
o Communicate with Employer through letters
o Prepare and follow up on bonds and taxation documents
o Communicate and follow up on subcontractors.
o Negotiate and prepare variation orders and variation order log
o Organize a risk management plan
o Prepare and negotiate claims.
o Communicate with Employer through letters
o Prepare and follow up on bonds and taxation documents
o Communicate and follow up on subcontractors.
avril 2015
A février 2018
Contract Administrator
à Orascom Construction
Lieu :
Egypte - Le Caire
o Analyze construction contract and risks
o Direct and supervise the insurance and financial bid requirements
o Organize a risk management plan
o Prepare the commercial figures for the insurance and financial bid quotations
o Prepare a cash flow in coordination with cost estimation and planning
o Projects studied:
Jiji and Mulembwe Hydroelectric Plant, Burundi
ADIA Power Project in Nigeria
Al Alamein Hotel Refurbishment main works
Ashuganj Power Station in Bangladesh
ASORC Naphtha Complex Project
Water Supply Development Project of Santiago Island - Republic of Cabo Verde
Ain Sokhna IWPP - 150, 000 m3/day & 475 MW Plant
Hamrawiin Coal Power Plant
Ataqa and Mahmoudia Power Plants
El Orman Cancer Hospital in Luxor
New Capital Power Plant
El Brullus Power Plant
El Aouj FEED Project in Mauritania
Hassi Massoud Power Plant in Algeria
Hassi Tidjerane Plant in Algeria
El Beida Cement Factory in Algeria
Nasareya (Iraq) Power Plants
Qudruple bundle 500 KV Double Circuit OHTL
ZARAT Project desalination Plant in Tunisia
Nairobi Nakuru Mau Summit Road PPP project in Kenya
Bir Seba Power Plant in Algeria
o Direct and supervise the insurance and financial bid requirements
o Organize a risk management plan
o Prepare the commercial figures for the insurance and financial bid quotations
o Prepare a cash flow in coordination with cost estimation and planning
o Projects studied:
Jiji and Mulembwe Hydroelectric Plant, Burundi
ADIA Power Project in Nigeria
Al Alamein Hotel Refurbishment main works
Ashuganj Power Station in Bangladesh
ASORC Naphtha Complex Project
Water Supply Development Project of Santiago Island - Republic of Cabo Verde
Ain Sokhna IWPP - 150, 000 m3/day & 475 MW Plant
Hamrawiin Coal Power Plant
Ataqa and Mahmoudia Power Plants
El Orman Cancer Hospital in Luxor
New Capital Power Plant
El Brullus Power Plant
El Aouj FEED Project in Mauritania
Hassi Massoud Power Plant in Algeria
Hassi Tidjerane Plant in Algeria
El Beida Cement Factory in Algeria
Nasareya (Iraq) Power Plants
Qudruple bundle 500 KV Double Circuit OHTL
ZARAT Project desalination Plant in Tunisia
Nairobi Nakuru Mau Summit Road PPP project in Kenya
Bir Seba Power Plant in Algeria
janvier 2014
A janvier 2015
Teaching Assistant
à American University in Cairo
Lieu :
Egypte - Le Caire
o Prepared and gave tutorials to students about how to use Revit and Navisworks
o Directed and supervised students with their projects
o Proctored exams with the professor
o Directed and supervised students with their projects
o Proctored exams with the professor
août 2014
A septembre 2014
Construction Management intern
à Dar El Mimar, DMG learning academy
Lieu :
Egypte - Le Caire
o Attended a concentrated course in contractual management, design development and quantity surveying
o Learnt working on primavera
o Worked on a sample project to apply the learned lessons
o Learnt working on primavera
o Worked on a sample project to apply the learned lessons
septembre 2013
A février 2014
Engineering assistant
à American University in Cairo, Rare library
Lieu :
Egypte - Le Caire
o Prepared Hassan Fathy, Gamal Bakry and Sayed Karim projects for scanning
o Directed the students in their research about Hassan Fathy
o Sorted and restored the projects
o Directed the students in their research about Hassan Fathy
o Sorted and restored the projects
janvier 2012
A janvier 2013
Teaching assistant
à American University in Cairo, Islamic art and architecture course
Lieu :
Egypte - Le Caire
o Organized and went on field trips in old Cairo
o Educated and directed students in projects and research
o Educated and directed students in projects and research
juin 2011
A août 2011
Engineering Trainee
à Aga Khan Foundation
Lieu :
Egypte - Le Caire
o Assisted Dr. Dina Bakhoum in old Islamic monuments restoration in old Cairo.
o Advised/Supervised workers during restoration
o Collaborate with the design office to restore the points of the building that were being surveyed
o Taught and educated the kids that lived in the neighborhood about the goals and ethics of our work
o Advised/Supervised workers during restoration
o Collaborate with the design office to restore the points of the building that were being surveyed
o Taught and educated the kids that lived in the neighborhood about the goals and ethics of our work
mai 2011
A mai 2011
Team Leader in Junior Summer Program
à American University in Cairo
Lieu :
Egypte - Le Caire
o Guided/Supervised a group of teens and helped in exposing them to different experiences
juin 2009
A août 2009
Counselor
à Wellspring
Lieu :
Egypte - Le Caire
o Guided the team in their experiences and exponential learning
o Recruited/Trained and educated the schools and universities to work as a team
o Recruited/Trained and educated the schools and universities to work as a team
Partager sur Facebook
Partager sur Twitter
Partager via Email