Acting Finishing Manager
Al Ali Construction and Development
مجموع سنوات الخبرة :17 years, 8 أشهر
InterContinental Resort and Hotel Mina Al Arab - Ras Al Khaimah /UAE
Client: RAK Properties LLC
Project Management: Currie & Brown Consultant: P&T Architect and Engineers Ltd. Contract Value: 480 Million AED
Responsibilities:
Key Skills:
⬧ Building relationships and a reputation in a team environment.
⬧ Organization and time management.
⬧ Effective Communications.
⬧ Creative and Problem-solving.
⬧ Attention to detail.
⬧ Tracking and Accurate reporting.
⬧ Building process and sequence Knowledge.
• Review the drawings, specifications & ensure the understanding of site engineers.
• Coordination and monitoring of the day to day activities on site for fit-out, architectural packages.
• Prepare weekly, monthly reports, and progress tracking report whenever required.
• Monitor, direct reporting project progress and details to Project Manager.
• Collaborate with engineers, subcontractors, buildings specialist and QA/QC.
• Coordinating with MEP Engineers related to interior fit-out, architectural and civil works.
• Planning & scheduling the work efficiently and organize the work trades to follow schedules.
• Ensured design specifications and safety standards on the project site.
• Issue RFI’s, FAF’s in line with technical team according to site survey and condition.
• Following up with the consultant and project management to resolve outstanding issues.
• Attend Technical, Progress and Coordination meetings.
Position: Sr. Project Engineer
- Project: Tiara United Towers (3B+G+Car Park+50th Two Residential Towers) - Dubai /UAE
Client: Zabeel Investments
Project Management: Meraas Development
Consultant: ADP INGENIERIE (ADPI)
Contract Value: 1, 200 Billion AED
- Project: Twin Tower (3B+G+3P+48th Floor Hotel & Office Towers) - Doha /Qatar
Owner: Sheikh Khalid Bin Hamad EL Thani
Project Management: Hamilton Project Management & Development (HPM)
Consultant: Architectural Consulting Group LLC (ACG)
Contract Value: 699 Million QAR
Responsibility For:
- Review the drawings, specifications & ensure the understanding of site engineers.
- Co-ordination and monitoring of the day to day activities on site for fit-out, architectural packages.
- Prepare weekly, monthly reports, and progress report whenever required.
- Monitor, direct reporting project progress and details to Project Manager.
- Collaborate with engineers, subcontractors and buildings specialist.
- Coordinating with MEP Engineers related to interior fit-out, architectural and civil works.
- Planning & scheduling the work efficiently and organize the work trades to follow schedules.
- Ensured design specifications and safety standards on the project site
- Following up with the consultant and project management to resolve outstanding issues.
- Attend Technical, Progress and Coordination meetings.
1- Sidi Krir Power Station - Construction of Two Residential Building.
Position: Construction Engineer (Client Representative)
Responsibility For:
- Supervision and inspection execution of all Civil and Architectural works.
- Day-to-day Monitoring site activities.
- Follow up Operation on Materials, Building and Finishing Operations.
- Manage Site Surveying activities and levelling, checking drawings, quantities &
Ensuring that the calculations are accurate for the work execution.
- Answering RFIs related to architecture & Coordination inquiries.
- Coordinate work between Architects, Civil, and MEP Site Engineers.
- Propose architectural solutions and alternative design.
- Preparing & Controlling Progress reporting to ensure contractor plan was maintained.
- Review contractor’s correspondence to prepare replies within contract.
- Quantity surveys.
2-Sidi Krir Power Station - 750 MW Combined Cycle Project.
Position: Construction Engineer (Client Representative)
Consultant: Power Generation Engineering and Service Co. (PGESCo).
Civil work Contractor: Orascom Construction Industry / Besix SAJV Consortium.
Contract Value: 398, 278, 097 LE + 27, 596, 986 Euro
Off shore work Contractor: Archirodon Construction (Overseas) Co.S.A.
Contract Value: 134, 936, 903 LE + 72, 229, 319 $
Responsibility For:
- Supervision and inspection execution of all Civil and Architectural works in Project:
Earth work and site grading
Driving sheet piles
Installation offshore pipes
Concrete works
Steel Structure works
Masonry works
Finishing works
Asphalt works
Landscaping works
- Day-to-day Monitoring site activities.
- Manage Site Surveying activities and levelling, checking drawings, quantities &
Ensuring that the calculations are accurate for the work execution.
- Answering RFIs related to Site activites & Coordination inquiries.
- Preparing & Controlling Progress reporting to ensure contractor plan was maintained.
- Review contractor’s correspondence to prepare replies within contract.
- Coordinating with all contractors (civil, mechanical, electrical) and client.
- Review civil contractor’s submittals including (drawings and materials).
- Making 3D Models for Construction methods (attached photo).
- Assisting all weekly & monthly meetings.
3- Sidi Krir Power Station - Construction of Administration Building.
Position: Construction Engineer (Client Representative)
Responsibility For:
- Supervision and inspection execution of all Civil and Architectural works.
- Day-to-day Monitoring site activities.
- Follow up Operation on Materials, Building and Finishing Operations.
- Manage Site Surveying activities and levelling, checking drawings, quantities &
Ensuring that the calculations are accurate for the work execution.
- Answering RFIs related to architecture & Coordination inquiries.
- Coordinate work between Architects, Civil, and MEP Site Engineers.
- Propose architectural solutions and alternative design.
- Preparing & Controlling Progress reporting to ensure contractor plan was maintained.
- Review contractor’s correspondence to prepare replies within contract.
Responsibility: Making Architectural Designs, 3D Modelling, Presentations.
Work in Two Motor Exhibition in Alexandria (Downtown)
Responsibility: Making a Strict Supervision and Follow up Operations on Materials, Building
and Finishing Operations.
Installation and finishing the following items:
- Masonry works. - Tiles work.
- Plaster works. - Paint works.
- Water proofing. - Gypsum Board, False ceiling.
- Security glazing. - Granite and Marble works.
- Aluminium cladding. - HVAC.