technical office Mechanical manager
Rowad modern engineering
مجموع سنوات الخبرة :16 years, 8 أشهر
1-Beni Suef combind cycle 4800 MW
- all buildings HVAC, fire protection and plumbing Works
- all company scope of work buildings ( GIS, CCB, Gas turbine, steam turbine and adminstration) coordination
2- AL Mostasmeren sub station 66 K.V.,
220K.V., CCB
3-ministeries project in New capital
تصميم اعمال التهويه والتكييف والاعمال الصحيه واعمال مكافحة الحريق
التنسيق بين اعمال الميكانيكا والكهرباء والاعمال المدنيه والمعماريه
تنفيذ اعمال الميكانيكا واعمال الموقع العام
1- designing the following machines(crushing m/c-cable sim cutter-balancing machine-tank 30 MVA)
2-marassi water pump station site manager
3-up town Cairo site manager for the installation of water pump station and sewage pump station
4-marassi irrigation pump station site manager
5- manager of installation of water meters and electerical meters in all clusters in marassi
1-testing and eraction of (v.c.v. line, drum twister 4000, strainding 61, drawing neihoff, hfsab lead, screening and opgw) m/c
2-performing predictive, preventive and sudden maintenance
3-performing spare part list for all machines
4-performing any modification when need
1-performing design calculation for all machines
2-performing design drawings
2007 Zagazig University * Faculty of Engineering * Mechanical Department, power branch * Grade: Good *Graduation Project: Central air conditioning for building