Studying and Reviewing Tender Drawing & Work Shop drawing.
* Installation and operation of HVAC, Fire Fighting and Plumbing Systems.
* Coordinate between Mechanical and Electrical works in the site.
* Installation of Building Management System for All System (BMS).
* Prepare As Built Drawings.
* Make Water balance for Chilled and Hot Water system.
* Make Air Balance & Validation of air condition system (HEPA Filters, DOP test, flow
Rates test, differential pressure test, and particle count test).
* Ensures compliance with the pharmaceutical needs and specification for the cooling
Systems temperature, humidity, pressure difference etc.
Practical Trainings
* Egyptian Company for Air Systems (E.C.A.S).
* Hyundai Maintenance Center in Alexandria.
* Egyptian Spinning and Weaving Company.
* Maamal power plant.
* Betty Dairy factory.
* San Stefano project.
* Gas Cool project (Absorption Refrigeration by Natural Gas) at smart village.
Sub-contractor: Al-Rashid Abetong for precast concrete buildings.
Contract Value: 300 million Saudi Riyal.
Responsibilities:
* Studying and Reviewing Tender Drawing.
* Studying and Reviewing B.O.Q and specification.
* Check design and coordinate between architectural with structural and MEP drawings.
* Prepare Mechanical materials for approval.
* Compare between contract and actual estimated quantities.
* Prepare shop drawings for HVAC, Fire Fighting, Plumbing and Infrastructures.
Construction of Housing for Armed Forces in Jazan Military City.
Estimated area for project is 35 km2.
General Grade: Good. Project Grade: Excellent.