محمد مغاوري محمود, Site Project Control Manager

محمد مغاوري محمود

Site Project Control Manager

Heavy Engineering Industries & Shipbuilding Company (HEISCO)

البلد
الكويت
التعليم
بكالوريوس, Bachelor of Since In Civil Engineering.
الخبرات
19 years, 1 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :19 years, 1 أشهر

Site Project Control Manager في Heavy Engineering Industries & Shipbuilding Company (HEISCO)
  • الكويت - الأحمدى
  • أشغل هذه الوظيفة منذ يونيو 2022

Project (I): General Construction Works for the CIVIL, STRUCTURAL, MECHANICAL, PIPING, TANKS AND E&I WORKS of the EPC&C of Jurasic Production Facilities (JPF) 4 at Kuwait Oil Company (KOC) North Kuwait-for SPETCO International Petroleum Company W.L.L. at State of Kuwait. From Jun 2022 till Now.
Project (II): Execution, Completion and Maintenance of the Access Link Road to Mubarak Al Kabeer Port (MKP) in Boubyan Island at State of Kuwait. From Oct 2020 till Now.
Project (III): Cleaning and disinfection of docks and berths at Shuaiba port at State of Kuwait. From April 2021 till Now.
Project (IV): NEW GATHERING CENTER GC-32, (EARLY CIVIL WORKS AND SUPPLY AND CONSTRUCTION OF BUILDING AND SHELTERS) for Kuwait Oil Company KOC and, for Petrofac International Limited at State of Kuwait. From Jan 2021 till Now.

Duties:
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Controls Manager / Project Director/ to initiate proper corrective actions.
- Creating / Establish Project Time Schedules as well as all reports (Internal & Client /Engineer).
- Preparing / Establish Acceleration/Recovery plan for the disciplines/Project when required.
- Preparing the Delay Analysis Log as per Retrospective single base additive modeling (Impacted Baseline Critical Path) (IB-CPM).
- Supporting in preparation of the Extension of Time (EOT) Claims.
- Preparing/Presenting to Top Management Project Presentation for the subjects required and steering meetings presentation.
- Developed an effective internal reporting system along with administering internal Bi-weekly meetings which resulted in decreasing schedule delays to less than 5%.
- Checked for accuracy and consistency in progress updates, critical path and near critical activity analysis, forecasts, recovery/revised plans, client and internal progress reporting.
- Contributed and highlighted to the management any foreseeable delays or risks.
- Participated in construction progress meetings across the projects to check the updated schedules and suggest corrective actions.
- Support the cost control team during the preparation of the project’s budget.
- Analyzed the change orders and evaluated their time and cost impact.

Lead Planning & Scheduling Engineer في at Heavy Engineering Industries & Shipbuilding Company (HEISCO)
  • الكويت - الأحمدى
  • أشغل هذه الوظيفة منذ يناير 2017

Project (I): General Construction Works for the Compressors, Utilities and Interconnection Sub-Areas of the EPC&C of Gas Train 5 Project at MAA Refinery for Kuwait National Petroleum Company (KNPC), for Tecnicas Reunidas S.A. (TR) at State of Kuwait.

Duties:

- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Control Manager / Project Manager/ to initiate proper corrective actions.
- Creating / Establish Project Time Schedules (Internal & Client /Engineer).
- Preparing Weekly/Monthly progress reports (Internal & Client /Engineer).
- Preparing / Establish Acceleration/Recovery plan for the disciplines/Project when required.
- Preparing the Delay Analysis Log as per Retrospective single base additive modeling (Impacted Baseline Critical Path) (IB-CPM).
- Supporting in preparation of the Extension of Time (EOT) Claims.
- Preparing/Presenting to Top Management Project Presentation for the subjects required.

Lead Planning Engineer في Heavy Engineering Industries & Shipbuilding Company (HEISCO)
  • الكويت - الأحمدى
  • مايو 2015 إلى يناير 2017

Project (1): Supply & Construction of Storage Tanks & Construction of Civil works related to New Gathering Center, GC29 in North Kuwait for Kuwait Oil Company KOC and, for Petrofac International Limited at State of Kuwait.

Project (2): Supply & Construction of Storage Tanks & Construction of Civil works related to New Gathering Center, GC30 in North Kuwait for Kuwait Oil Company KOC and, for Larsen & Toubro (L&T) at State of Kuwait.

Duties:
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Master work progress schedule updates.
- BOQ weekly reports (Planned-Actual).
- Man-hours progress report (Planned-Actual-Earned).
- Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer/Owner.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Control Manager / Project Manager/ to initiate proper corrective actions.
- Creating / Establish Project Time Schedules (Internal & Client /Engineer).
- Preparing Weekly/Monthly progress reports (Internal & Client /Engineer).

Lead Planning Engineer for Power Plant Project في Alghanim International General Trading & Contracting Co
  • الكويت
  • سبتمبر 2013 إلى مايو 2015

Project: Supply, Erection, Operation and Maintenance of Gas Turbines to Upgrade Power Capacity at Sabiya Power and Distillation Plant Site.
“Sabiya OCGT Power Plant - EPC Project and O&M in Kuwait - Main Contractor”

- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Master work progress schedule updates.
- BOQ weekly reports (Planned-Actual).
- Man-hours progress report (Planned-Actual-Earned).
- Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer/Owner.
- Establish all disciplines progress curves (S-Curves) Weekly/Monthly (Internally and for Client/Engineer).
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Manager/Director to initiate proper corrective actions.
- Creating / Establish project Schedule (Level 1, Level 2 and Level 3) and approved from the client.
- Preparing Weekly/Monthly progress to Owner/Engineer.
- Preparing Weekly/Monthly Minutes of Meetings

Lead Planning Engineer في Alghanim International General Trading & Contracting Co & ALSTOM Power System Plant
  • الكويت - الزور ميناء سعود
  • نوفمبر 2011 إلى سبتمبر 2013

Project: Design& Build and O & M for the Conversion of the Second Stage Az-Zour South Gas Turbines to Combined Cycle Plant.
“Az-Zour CCGT-2 Power Plant 2X275 MW- EPC Project and O&M in Kuwait - Main Contractor”
Duties:

-Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
-Estimating the type and quantities of resources required to perform each schedule Activity.
-Master work progress schedule updates.
-BOQ weekly reports (Planned-Actual).
-Man-hours progress report (Planned-Actual-Earned).
-Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer.

-Establish all disciplines progress curves (S-Curves) Weekly/Monthly

Senior Planning Engineer في ORASCOM Construction Industries & ALSTOM
  • الجزائر
  • فبراير 2008 إلى نوفمبر 2011

Senior Planning Engineer for Power Plant Project

TERGA Power Plant combined cycle 3X400 MW in Algeria - EPC Project -Main Contractor .
Duties:

Identifying the specific schedule activities that need to be performed to produce the various project deliverables.
- Estimating the type and quantities of resources required to perform each schedule Activity.
- Estimating the number of work periods that will be needed to complete individual schedule activities.
- Analyzing activity sequences, durations, resources, requirements, and schedule constraints to create the project schedule.
- Master work progress schedule updates.
- Monitoring daily-weekly-monthly work progress and reporting the output in the form of Weekly, Monthly Progress Reports to the Project Engineer.
- Three weeks look-ahead programs.
- Controlling changes to the project schedule.
- Preparation of the Subcontractors sub-schedules and monitoring the progress of each and reflecting their output in the Master progress Schedule.
- Assist in preparation of the consortium Monthly Progress Report to Management.
- Man-hours progress report (Planned-Actual-Earned).
- BOQ weekly reports (Planned-Actual).
- Assist in the Preparation of the Extension of Time Claims documents and schedule impacts.
- Coordination with the Contract Administration to highlight the areas of potential time impacts.
- Highlight the delays and the possible consequences of disruptions in the schedule and report the same to the Project Control Manager to initiate proper corrective actions.
- Present to top management project presentation in each monthly meeting.
- Teach talent program engineers in planning phase.(teach 5 Eng. “ 1 civil+3 Mechanical+1 Electrical”)

Planning Engineer , Assistant Contract Management Engineer في CACPEC"Consortium of Arab Contractors and Parson Energy & Chemical group Inc."
  • مصر - القاهرة
  • أغسطس 2006 إلى فبراير 2008

"El-Kureimat II power Station (750 MW Combined Cycle)"
CONSULTANT : Power Generation Engineering and Service Company "PGESCo" BECHTEL & Ministry of Electricity and Energy& CIB
Duties:

-Planning & Time Schedule.
-Contract Administration.
-Change Notices & Claims
-Contractual Correspondence to and from all Parties.
-Monitoring all Contractual aspect under the main Contract.
-Remeasurement of the Works & Monthly Client Invoice.
-Project Monthly progress Report
-Time Impact, Cost Impact

Planning Engineer , Assistance Contract Management Engineer في Construction Consulting Group(Basha &Associates)
  • مصر - القاهرة
  • مايو 2005 إلى أغسطس 2006

TANTA UNIV.HOSPITAL"BUDGET :150 M.L.E For "ARAB CONTRACTORS "Osman Ahmed Osman &Co
Duties:

-Planning & Time Schedule
-Tender Planning
-Contract Management
-Project Time Management
-Project Cost Management
-Project Procurement Management
-Project Communication Management
-Monthly Progress Reporting
-Claims management

الخلفية التعليمية

بكالوريوس, Bachelor of Since In Civil Engineering.
  • في Zagazig University_Benha Branch_ Shoubra Faculty of Engineering
  • مايو 2005

Final Year Grade: V.GOOD. Overall Grade: GOOD (72.30%) 10th on the Class Cumulative. PROJECT: Construction Project Management. GRADE: EXCELLENT (96.5%).1st on the Class

Specialties & Skills

Schedule Planning
Progress Monitoring
CPM Scheduling
Primavera P6
Microsoft Office
Planning and schedule
PLANNING USING LINE OF BALANCE (L.O.B), TIME LOCATION METHOD,(CPM)
. PRIMAVERA PROJECT PLANNER
. MICROSOFT OFFICE
AUTOCAD PROGRAM
STRUCTURAL ANALYSIS PROGRAM (SAP)
INTERNET
Training Course In Technology & Management Institute (TMI) In Arab Contractors Company
Deferent Method To Execute Structure Works In Technology & Management Institute (TMI) in Arab Cont

اللغات

العربية
متمرّس
الانجليزية
متمرّس

العضويات

Egypt Engineers Syndicate
  • 01500/30
  • August 2005

التدريب و الشهادات

Deferent Method To Execute Structure Works (تدريب)
معهد التدريب:
Technology & Management Institute (TMI) In Arab Contractors Company
تاريخ الدورة:
February 2007

الهوايات

  • Reading
    Reading and learning for Management Books