محمد اسماعيل, Senior planning Engineer

محمد اسماعيل

Senior planning Engineer

Hassan Allam Construction

البلد
الإمارات العربية المتحدة - أبو ظبي
التعليم
بكالوريوس, Civil Construction and Civil Engineering
الخبرات
11 years, 5 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :11 years, 5 أشهر

Senior planning Engineer في Hassan Allam Construction
  • مصر - القاهرة
  • أشغل هذه الوظيفة منذ مايو 2019

- Project: Maspero Towers Project.

- Project Description: Tower (1) B+G+15 Residential Storey, Tower (2) 4 storey Podium (Parking, Commercial, Upper Parking, Administrative) & 22 Residential Storey.

- Responsibilities:
 Developing Project Baseline schedule, Resources and Cost loading.
 Developing Project Progress Reports using Earned Value Management Techniques.
 Developing Project Direct & Indirect Manpower Deployment Plan and subcontracting Plan.
 Weekly Schedule update and Preparation of periodic Reports/ Presentations.
 Follow up Technical office submittals and procurement process, assuring meeting schedule.
 Managing weekly progress meeting with Project team, and prepare minutes of meeting.
 Attending Weekly Meeting with owner/consultants, reviewing project status and obstacles.

Planning Engineer في Elsewedy Power Systems Projects (PSP)
  • العراق - البصرة
  • مارس 2018 إلى مايو 2019

- Project: 400/132KV 4 Substations EPC Project - Iraq.
- Main Contractor: Toyota Tsusho Corporation.
- Responsibilities:
 Developing Project Baseline schedule, Resources and Cost loaded.
 Developing Project Progress Tracking Sheets and periodic Reports.
 Developing Project Direct & Indirect Manpower Deployment Plan and subcontracting Plan.
 Update Project Schedule, highlighting delays and work on recovering such delays.
 Managing Engineering & Procurement Scope to meet targeted schedule.
 Prepare Weekly look ahead and hold meetings with various teams to assure meeting schedule.
 Review Subcontractors Schedules, and incorporate it in Project Master Schedule.
 Managing Resolution of Subcontractor claims and Extension of Time.

Planning Engineer في Elsewedy Power Systems Projects (PSP)
  • مصر - القاهرة
  • مايو 2017 إلى فبراير 2018

- Responsibilities:
 Developing Project Baseline schedule, Resources and Cost loaded.
 Developing Project Progress Tracking Sheets and periodic Reports.
 Developing Project Direct & Indirect Manpower Deployment Plan and subcontracting Plan.
 Update Project Schedule, highlighting delays and work on recovering such delays.
 Managing Engineering & Procurement Scope to meet targeted schedule.
 Prepare Weekly look ahead and hold meetings with various teams to assure meeting schedule.
 Review Subcontractors Schedules, and incorporate it in Project Master Schedule.
 Managing Resolution of Subcontractor claims and Extension of Time.

Planning Engineer في Mohammed AL Rashid CO (MARCO)
  • المملكة العربية السعودية - الرياض
  • مايو 2014 إلى أبريل 2017

- Imam Muhammad Bin Saud Islamic University Projects - Riyadh- KSA:
 SUPPORTING ACADEMIC AREA AND CAR PARKING
Project Budget: 1, 150, 000, 000 SR
 STUDENT LOBBY IN MALE ACADEMIC AREA - (Design & Built Project)
Project budget: 220, 000, 000 SR
 REHABILITATION OF MALE STUDENTS ACADEMIC AREA
Project Budget: 210, 000, 000 SR
- Projects Consultant: TYPSA Spain.
- Responsibilities:
 Developing Baseline schedule.
 Updating Schedule highlighting delayed activities and recommend corrective action.
 Following up Engineering submittals, material procurement and subcontractors’ status.
 Attending periodic progress meeting with top management, consultant and client.
 Preparing of Time Extension Requests/Time Claims.
 Update project budget in accordance with approved design, drawings and V.Os.
 Prepare and update project cash flow periodically.
 Supervising and monitoring Site Labor Force and Subcontractors Productivity.

Planning Engineer في DETAC
  • مصر - القاهرة
  • فبراير 2013 إلى أبريل 2014

- Project: Hanging Gardens - Porto Sokhna - Egypt.
- Project Budget: 100, 000, 000 L.E.
- Project Management Consultant: Hill International.
- Responsibilities:
 Updating Program of works weekly according to actuals.
 Preparing Daily, Weekly and Monthly progress Reports.
 Following up engineering submittals (shop-drawings, materials).
 Following up project progress and highlighting delayed activities.
 Work on Delay Analysis for the project and Prepare Time Extension request.

الخلفية التعليمية

بكالوريوس, Civil Construction and Civil Engineering
  • في Cairo University
  • يوليو 2012

Bachelor of Civil Engineering - Construction Management

Specialties & Skills

Project Control
Primavera P6
Project Management
Project Planning
AUTOCAD
Primavera P6
MS Office
COMMUNICATION & PRESENTATION SKILLS
Presentation Skills
Team Work
procurement
planning
primavera
ms project

حسابات مواقع التواصل الاجتماعي

الموقع الشخصي
الموقع الشخصي

لقد تم حذف الرابط بسبب انتهاكه لسياسة الموقع. يرجى التواصل مع قسم الدعم لمزيد من المعلومات.

اللغات

العربية
متمرّس
الانجليزية
متمرّس

التدريب و الشهادات

Project Management Professional Program (PRMG) (تدريب)
معهد التدريب:
American university in Cairo
تاريخ الدورة:
July 2014
المدة:
216 ساعة

الهوايات

  • Reading & Swimming