Electrical Engineer
Sejong Corporation
Total years of experience :8 years, 8 Months
Preparing Test Plan and Ready for Inspection (RFI) schedule for consultant approval and compliance with necessary standards as per the client requirements.
Working Experience in Erection of Panels, MCC's, LCC’s, EPA and PMCC's as per the
approved GA Drawings.
Supervise Installation of 0.4kv, 11kv & 33kv Switch Gear, Control and Protection Panels, Power Transformers, Auxiliary Transformers, 110v, 220v & 415v Battery Bank, Cable Trays, GI Conduits, Grounding System.
Coordinate inspection activities between Client Inspectors/Engineers, Vendors, Inspection Agency, and Project Team.
Check carefully electrical materials and equipments delivered in site to assured specifications are base on client requirement.
Follow and maintain company standards of Quality in accordance with company Quality system requirement.
Knowledge in Nuclear Power Plant Construction Management System (NPCMS).
Easy handling of location diagrams and P&ID.
Supervised the erection of LT Bus ducts (Non-segregated bus ducts).
Following-up of HT< Cable laying as per the cable schedules
Supervised the Cable tray routing works for the total plant and design
of the cable tray routing according to the site conditions.
Supervised the erection of Isolated Phase Bus Duct (IPB Duct).
Working experience in Switchgears, protection of the switchgear, and maintenance of the electrical equipment's.
Installation and commissioning of the Batteries.
Ensuring WPS & PQR in accordance with Eng. Standards and Project Specification.
Prepare details of the field inspection requirements for activities in accordance with the applicable standards of the contract Specifications.
Verification of documents, review of material test certificates for plates, filler materials, flex, electrodes.