Total Years of Experience: 10 Years, 9 Months
September 2017
To October 2018
Project Engineer
at Al kifah contracting company
Location :
Saudi Arabia
ject Engineer \[Jazan economic city port and infrastructure (onshore package) (Saudi Aramco project))\]:
• Responsible for , soil improvement with our subcontractors as TRAVI responsible for ( dynamic compaction (DC), dynamic replacement (DC)), KELLER responsible for soil improvement for dynamic replacement (stone columns )
• infrastructure work like electrical, telecom duct banks, firefighting pipes, high must foundations and CBGM paving and concrete pads for container yard and bulk terminal
• Led a team of site engineers, supervisors, technicians & workers to carry out work in container yard starting from infrastructure, roads, foundations up to fixing cranes for container yard
• Examining construction drawings and highlighting any discrepancies, performing
Quantity Take-off calculations, preparing method statements, material approval requests and
preparing daily & weekly reports.
• Responsible for , soil improvement with our subcontractors as TRAVI responsible for ( dynamic compaction (DC), dynamic replacement (DC)), KELLER responsible for soil improvement for dynamic replacement (stone columns )
• infrastructure work like electrical, telecom duct banks, firefighting pipes, high must foundations and CBGM paving and concrete pads for container yard and bulk terminal
• Led a team of site engineers, supervisors, technicians & workers to carry out work in container yard starting from infrastructure, roads, foundations up to fixing cranes for container yard
• Examining construction drawings and highlighting any discrepancies, performing
Quantity Take-off calculations, preparing method statements, material approval requests and
preparing daily & weekly reports.
August 2016
To September 2017
section engineer
at modern Arabic construction
Location :
Saudi Arabia - Jizan
• Responsible for controlling lift station & oily water treatment plant from excavation until hand over as per drawing and Aramco standard
• Led a team of site engineers, supervisors, technicians & workers to carry out work in accordance with maps, specifications and other contract documents to ensure efficient and effective use of all resources
• Examining construction drawings and highlighting any discrepancies, performing
Quantity Take-off calculations, preparing method statements, material approval requests and
preparing daily & weekly reports.
• Led a team of site engineers, supervisors, technicians & workers to carry out work in accordance with maps, specifications and other contract documents to ensure efficient and effective use of all resources
• Examining construction drawings and highlighting any discrepancies, performing
Quantity Take-off calculations, preparing method statements, material approval requests and
preparing daily & weekly reports.
January 2013
To June 2016
project engineer
at al osais contracting company
Location :
Saudi Arabia - Dammam
As Project Engineer \[Royal Commission Recreational Villas-Industrial Jubial (500 Villas)\]:
• Rendering full assistance to the Project Manager in all activities required to be delivered at the site in timely manner and as per required quality/quantity
• Defining the project materials, manpower and equipments needed to finish the work assigned on time without delays,
issuing the internal supply requests at least before 4 working days of material needs and forwarding it to the Project Manager for approval
• Assessing the subcontractor who finishes work within a period, in coordination with the Project Manager; liaising with Main Store’s Storekeeper and Purchasing Managers for material delivery & receiving in coordination with Project Manager
• Administering the project staff (as mentioned in the project organizational chart) and making sure that all of them are executing tasks in accordance to the approved procedures & forms
• Ensuring that all employees in the project are aware of the company’s quality policy
• Led a team of supervisors, technicians & workers to carry out work in accordance with maps, specifications and other contract documents to ensure efficient and effective use of all resources
• Ensure project's milestones are met.
• Supervising & leading the finishing works
• Coordinating with MEP engineers to follow up the completion of their activities on schedule time.
• Conducting site meetings with sub-contractors to discuss their productivity & resolve any problem occurring on site
• Rendering full assistance to the Project Manager in all activities required to be delivered at the site in timely manner and as per required quality/quantity
• Defining the project materials, manpower and equipments needed to finish the work assigned on time without delays,
issuing the internal supply requests at least before 4 working days of material needs and forwarding it to the Project Manager for approval
• Assessing the subcontractor who finishes work within a period, in coordination with the Project Manager; liaising with Main Store’s Storekeeper and Purchasing Managers for material delivery & receiving in coordination with Project Manager
• Administering the project staff (as mentioned in the project organizational chart) and making sure that all of them are executing tasks in accordance to the approved procedures & forms
• Ensuring that all employees in the project are aware of the company’s quality policy
• Led a team of supervisors, technicians & workers to carry out work in accordance with maps, specifications and other contract documents to ensure efficient and effective use of all resources
• Ensure project's milestones are met.
• Supervising & leading the finishing works
• Coordinating with MEP engineers to follow up the completion of their activities on schedule time.
• Conducting site meetings with sub-contractors to discuss their productivity & resolve any problem occurring on site
January 2008
To January 2013
site engineer
at al osais contracting company
Location :
Saudi Arabia - Dammam
As Site Engineer \[Manifa Industrial & Support Buildings Facilities (for Saudi Aramco Company)\]:
• Responsible for controlling cast-in buildings such as administration building (4200 SQM) & dining hall
• Accountable for starting infrastructure, foundations & slabs and finishing them
• Controlled and coordinated the activities of sub-contractors at site and ensured work implementation on time & as per the required quality
• Responsible for concrete Sewell, stone rip rap & stone gabion
• handle team of engineers and foreman's & workers to close all punish list & expiation items made by owner
As Site Engineer \[Khurais Mega Project Residential Recreational & Industrial Complex (for Saudi Aramco Company)\]:
• Responsible for controlling precast & pre-engineered buildings, starting from infrastructure & foundations and finishing up to turn over the project to the owner, while following Aramco standard
• Accountable for planning and coordinating work with other engineers, contractors, management & Aramco consultant
• Led a team of supervisors, technicians & workers to carry out work in accordance with maps, specifications and other contract documents to ensure efficient and effective use of all resources
• Examining construction drawings and highlighting any discrepancies, performing
Quantity Takeoff calculations, preparing method statements, material approval requests and
preparing daily & weekly reports.
• Ensure that all site activities are conducted under controlled conditions as per shop Drawings, method statements, & specification.
• Ensuring safe work environment
• Participating in the handover of the project, establishing defect list, establishing Punch List with the client and ensuring closure of all punch list items
• Responsible for controlling cast-in buildings such as administration building (4200 SQM) & dining hall
• Accountable for starting infrastructure, foundations & slabs and finishing them
• Controlled and coordinated the activities of sub-contractors at site and ensured work implementation on time & as per the required quality
• Responsible for concrete Sewell, stone rip rap & stone gabion
• handle team of engineers and foreman's & workers to close all punish list & expiation items made by owner
As Site Engineer \[Khurais Mega Project Residential Recreational & Industrial Complex (for Saudi Aramco Company)\]:
• Responsible for controlling precast & pre-engineered buildings, starting from infrastructure & foundations and finishing up to turn over the project to the owner, while following Aramco standard
• Accountable for planning and coordinating work with other engineers, contractors, management & Aramco consultant
• Led a team of supervisors, technicians & workers to carry out work in accordance with maps, specifications and other contract documents to ensure efficient and effective use of all resources
• Examining construction drawings and highlighting any discrepancies, performing
Quantity Takeoff calculations, preparing method statements, material approval requests and
preparing daily & weekly reports.
• Ensure that all site activities are conducted under controlled conditions as per shop Drawings, method statements, & specification.
• Ensuring safe work environment
• Participating in the handover of the project, establishing defect list, establishing Punch List with the client and ensuring closure of all punch list items
Share on Facebook
Share on Twitter
Share Via Email