Construction Manager
CMEC
Total years of experience :12 years, 10 Months
My work responsibilities: -
• Lead and direct technical and administrative project team
• Execute and monitor project activities
• Manage changes to scope, cost and schedule of project work.
• Prepare and update project plans and status reports.
• Provide updates on customer and corporate issues participating in scheduled operational meetings as in routine with team leads and employees.
• Coordinate cross-functional meetings of personnel related to project.
• Facilitate sessions to effectively resolve issues if any.
• Allocate appropriate resources to ensure projects are completed within given time and budget.
• Utilize corporate ISO processes to track project schedule and cost.
• Report status develop project-related documentation and implement lessons learned.
• Participate in project performance review meetings and discussions. • Report status, develop project-related documentation and implement lessons learned
• Manage project team responsible for document preparation, scanning, indexing and document OCR imaging.
• Update and maintain production and quality metrics of projects.
My work responsibilities: -
• Lead and direct technical and administrative project team
• Execute and monitor project activities
• Manage changes to scope, cost and schedule of project work.
• Coordinate priorities and resources between multiple projects.
• Prepare and update project plans and status reports.
• Provide updates on customer and corporate issues participating in scheduled operational meetings as in routine with team leads and employees.
• Coordinate cross-functional meetings of personnel related to project.
• Facilitate sessions to effectively resolve issues if any.
• Allocate appropriate resources to ensure projects are completed within given time and budget.
• Utilize corporate ISO processes to track project schedule and cost.
• Report status develop project-related documentation and implement lessons learned.
• Participate in project performance review meetings and discussions. • Report status, develop project-related documentation and implement lessons learned
• Manage project team responsible for document preparation, scanning, indexing and document OCR imaging.
• Update and maintain production and quality metrics of projects
My work responsibilities: -
• Lead and direct technical and administrative project team
• Execute and monitor project activities
• Manage changes to scope, cost and schedule of project work.
• Coordinate priorities and resources between multiple projects.
• Prepare and update project plans and status reports.
• Provide updates on customer and corporate issues participating in scheduled operational meetings as in routine with team leads and employees.
• Coordinate cross-functional meetings of personnel related to project.
• Facilitate sessions to effectively resolve issues if any.
• Allocate appropriate resources to ensure projects are completed within given time and budget.
• Utilize corporate ISO processes to track project schedule and cost.
• Report status develop project-related documentation and implement lessons learned.
• Participate in project performance review meetings and discussions. • Report status, develop project-related documentation and implement lessons learned
• Manage project team responsible for document preparation, scanning, indexing and document OCR imaging.
• Update and maintain production and quality metrics of projects.
Project Name: (A-LSAFAWI FOR GREEN ENERGY PSC 50MWac SOLAR PV PLANT MAFRAQ )
Project budget 60, 000, 000JD
Position: CIVIL SITE MANAGER
Scope of work:
o Managing subcontractors site team and make sure they follow contract and project documents (QHSE plan, construction drawings, ITP’s…etc.)
o Make sure all works on site are performed on safely manner.
o Schedule and monitor program activity to achieve an “on time “result.
o Review method statements and discuss them with the team.
o Prepare required documents for site works such as safety permits.
o Reviews and monitors project progress to assure quality and adherence to requirements of contract documents.
o Initiate request for inspections and coordinate with QA/QC and consultant.
o Responsible for control of work-in-progress on site.
o Coordinate with store team and QA/QC inspectors for checking and inspecting the delivered materials
Project Name: (Quweira 103 MWp PV Power Plant Project)
Project budget 130, 000, 000JD
Position: Project Civil Engineer
Scope of work: o Managing subcontractors site team and make sure they follow contract and project documents (QHSE plan, construction drawings, ITP’s…etc.)
o Make sure all works on site are performed on safely manner.
o Schedule and monitor program activity to achieve an “on time “result.
o Review method statements and discuss them with the team.
o Prepare required documents for site works such as safety permits.
o Reviews and monitors project progress to assure quality and adherence to requirements of contract documents.
o Initiate request for inspections and coordinate with QA/QC and consultant.
o Responsible for control of work-in-progress on site.
o Coordinate with store team and QA/QC inspectors for checking and inspecting the delivered materials
• February 2014 - January 2015
Project Name: (Aldrees petroleum gas station project)
Project budget 9, 000, 000SR
Position: Project Manager
Scope of work:
o Mobilization
o Supervisor on shop drawing
o All construction work on the site for all facilities
o Coordinator between civil and electro mechanical work
o Prepare the steel and concrete quantity
o Finishing work (block, plastering, painting, tiles with all accessories)
• January 2015 - October 2016
Project Name: (Unicharm Industries project)
Project budget 60, 000, 000SR
Position: Construction Manager
Scope of work:
o Mobilization
o Supervisor on shop drawing
o All construction work on the site for all facilities
Like electrical and transformer rooms
o Coordinator between precast and cast on situ civil work and electro mechanical work
o Prepare the steel and concrete quantity
o Finishing work (block, plastering, painting, tiles and fall ceiling with all accessories)
• January 2010 - February 2012
Project Name: (AYLA Oasis) (www.aylaoasis.com)
Position: Site engineer
Scope of work:
o Supervisor on frame, steel & concrete work
o Supervisor on shop drawing, bar bending
o Prepare mobilization for the site
o Representative for the company with the consultant
• February 2012 - January 2014
Project Name: (kUFRANJA Dam)
Position: Construction Manager
Scope of work:
o Mobilization
o Supervisor on shop drawing
o All construction work on the site for all facilities
o Coordinator between the site and technical office
o Prepare the steel and concrete quantity