Resident Electrical Engineer
Hill International
Total years of experience :14 years, 5 Months
Riyadh Metro Project - Package 3, Line 5 King Abdulaziz Rd
•Manage and supervise Electrical engineering PMCM team (8 Engineers) for Riyadh Metro project LINE 5 (Green) for Metro stations, Park + Ride, Bus Integration, Ventilation shafts and Emergency Exits along way King Abdulaziz RD (18KM) for Royal Commission for Riyadh City (RCRC).
•Reviewed Metro stations design and Shop-drawings and As-built's for Review of Electrical systems, Landscaping, lighting, ICT, BMS, Fires detection and protection systems.
•Implemented and controlled high quality standard and procedures of execution works by consistent monitoring of the scope and specification delivery, based on ISO 9001 standard.
•Headed engineering meetings and applied effective coordination plans.
•Resolved project's technical hinders and provide technical solutions within project specifications and requirements.
•Maintained health & Safety procedures implementation of all relevant project's assets.
Riyadh Metro Project - Package 3, Line 4 Prince MBS Rd
•Executed and supervised PMCM plan of Riyadh Metro project for Metro Stagons, Park + Ride, Bus Integragon, Venglagon Shahs and Emergency Exits in Prince MBS RD (23KM) for Royal Commission for Riyadh City (RCRC).
•Reviewed Metro Stagons design and Shop-drawings and As-built drawings of Electrical systems, Landscaping, Lighgng, ICT, BMS, Fires detecgon and protecgon systems.
•Controlled and ensured beier quality standards of the works by consistent monitoring of the scope and specificagon delivery.
•Inspected and audited site works to idengfy issues and non-compliances and follow close out acgons of NCRs.
•Assisted junior engineers and guided them to achieve Quality procedures and standards are for project's scope.
•Ensured the implementagon of Health & Safety and fire safety plans under construcgon.
QC: Review subcontractor and supplier quality document submittals (Quality Plans, Inspection Test & procedures), to ensure effective controls are in place in key areas.
•Supervision: Monitoring and reporting on the status of implementation of the Project Quality Management System and its effectiveness for more than 40 power substations. Maintenance: Performed systems installations and maintenance duties in addition to backup systems.