MEP Construction Manager
Domopan Qatar
Total des années d'expérience :9 years, 9 Mois
MEP works site supervision.
Site coordination with other trades.
Monitor the performance of site team and subcontractors.
Follow the subcontractor activities as per project master plan.
Prepare work schedule & sequence of activities
Supervise and advise site team work on daily basis.
Arrange the material request for MEP works. Management reporting.
Tests and inspections.
O&M manuals, method statement and T&C of the entire MEP works.
Draft weekly schedule, monthly schedule, material, labor requirement, and equipments.
• Engineering, erection testing & commissioning of MEP works.
• Supervise and advise site team work on daily basis.
• Draft weekly schedule, monthly schedule, material, labor requirement, and equipment per the project master plan.
• Investigate damage, accidents or delay at the site to ensure that proper procedures are being carried out
• Monitor the performance of site team and subcontractors to ensure the complete following of safety rules.
• Confirm with technical department to discuss and resolve matters such as shop drawing, method of statement and construction problems.
• Follow work activity in site with team work.
• Coordinate between technical office and the site team.
• Follow the subcontractor.
• Arrange the material request for MEP works.
Engineering, procurement, erection testing & commissioning of MEP works.
Supervise and advise site team work on daily basis.
Draft weekly schedule, monthly schedule, material, labor requirement, and equipment
according to the project master plan.
Investigate damage, accidents or delay at the site to ensure that proper procedures are
being carried out
Monitor the performance of site team and subcontractors to ensure the complete
following of safety rules.
Confirm with technical department to discuss and resolve matters such as shop drawing,
method of statement and construction problems.
Follow work activity in site with team work.
Coordinate between technical office and the site team.
Follow the subcontractor
Arrange the material request for MEP works.
Prepare the weekly work plan according to the time schedule.
Check the subcontractor invoices.
Mechanical Engineer