Muhammad Maneeb Altaf, Projects Manager

Muhammad Maneeb Altaf

Projects Manager

Pace Track company limited.

Location
Saudi Arabia - Albaha
Education
Bachelor's degree, ELECTRICAL
Experience
13 years, 4 Months

Share My Profile

Block User


Work Experience

Total years of experience :13 years, 4 Months

Projects Manager at Pace Track company limited.
  • Saudi Arabia - Albaha
  • June 2014 to December 2018

Working as Branch manager in Pace track Company for Contracting projects of Saudi Electricity Company and Unified rate projects /Job orders.
New project study for bidding (Under Ground network, OHL up to 33 KV 13.8KV and LV distribution network) Material procurement for ongoing project
Project planning, Coasting and coast control, scheduling and Execution of projects
Have key Role in Establishing new company, setup the organization, Achieve SEC unified Contract with 4 star safety Qualification
Hiring new manpower and purchasing the Equipment. Manage the warehouse, workshops and Branch offices.

Have responsibility of Business development

Project Manager at SATEC
  • Saudi Arabia - Jeddah
  • January 2012 to May 2014

Job profile:

*New project study for bidding (Under Ground network, OHL up to 33KV.MV and LV distribution network )
*New project study for bidding (Telecom Project)
*Project planning, scheduling and Execution of projects
*Designing of Electrical system for SATEC Rental power project.
*Material procurement for ongoing project.

*****Ongoing Electrical Projects in KSA******

***33 KV Double circuit Overhead transmission line (Khules - Al Kameel 50KM)***

Working as project manager on the project of 33KV double circuit Overhead transmission line 50Km long project
Responsible of Complete project, planning, scheduling, procurement and supervision of Installation, of transmission line


****Major Completed Electrical Projects in KSA****

****Medium and low voltage distribution network installation at Flamingo Mall Project Jeddah:***

Work as project manager, my responsibilities was study of project, bidding, after assigning of project, planning, scheduling, procurement and supervision of MV/LV electrical equipment
(Unit substation, RMU, MDBS, Metering units, Cables) Installation, Commissioning, and Startup


***Installation of MV cables from 110/13.8 KV S/S to AL Fareedah residential community ***
(Project of 6 feeder 13.8 KV cables from Dahban S/S to AL Fareedah residential community)

Work as project manager, my responsibilities was study of project, bidding, after assigning of project, planning, scheduling, procurement and supervision of Installation, Commissioning, and Startup of (Unit-substation, RMU, and MV Cables

***17 MW Rental power project 33KV in KKMC Hafral batin****
Responsible for complete testing commissioning and energizing, 33KV SF6 Switch gears Step-up Transformers, LV Genset, MV cables for power rental project.
Coordination study of complete system and setting for protection relays of 33KV SF6 Switch gears

****Major Completed Telecom Projects in KSA****

**MOBILY FTTH Network Installation in Mohammadiya Jeddah more than 10 Km length***

Work as project manager, my responsibilities was study of project, bidding, after assigning of project, planning, scheduling, procurement and supervision of Installation, and PAT


***MOBILY FTTH Network Installation in AL rawdah Jeddah 9 Km length***

Work as project manager, my responsibilities was study of project, bidding, after assigning of project, planning, scheduling, procurement and supervision of Installation, and PAT

Project Engineer at SATEC
  • Saudi Arabia - Jeddah
  • November 2010 to January 2012

Job profile:

* Project Engineer LV/MV project of Sub satations, RMU, Under ground Cables and electrical equipment Installation.
* Testing and commissioning of projects
*Project study for bidding (Under Ground, OHL up to 33KV)
*Designing of Electrical system for SATEC Rental power project.
QA/QC control for Electrical projects


**33KV Under-ground Tie line project between Qurayat power plant & west substation:**

(Project of underground 33KV double circuit 1x500mm cables and 48 core fiber optics cable

installation between Qurayat power plant & west substation)
Work as Project Electrical Engineer in Qurayat project of 33KV double circuit underground cable
laying in 21Km and responsible for Electrical equipment Installation, testing, Commissioning and
final start up.


Design related projects in KSA:-
Design project Electrical schemes, sizing of Electrical equipment (Cable, transformer, switch gears,
Generators, etc.) material procurement for project),
(Load flow analysis, Short circuit current study) by Etap 7.0 &7.5 of following project

40MW RENTAL POWER PROJECT IN ARAR
10MW RENTAL POWER PROJECT IN RAFAH
10 MW RENTAL POWER PROJECT IN HAIL

Project team leader at packages ltd.
  • Pakistan - Lahore
  • September 2005 to November 2010

New pulp and paper mill (BSPM) project in Kasur
Position: project team leader from 2005 to Nov 2010

Job profile:

My responsibilities was in, project scheduling, complete Electrical Design, Procurement, Construction, Installation, Erection, Commissioning, Start up, Optimization. Of followings as project team leader
 41MW Power Plant,
 11MW Power Plant
 De-inking plant, & Paper Machine.
Responsibilities also include supervision of the department, installation & erection of plants, supervision of various contractor and suppliers etc.

COMMISSIONING:
I completed the commissioning of 11MW, 41MW Power Plant, De-inking plant, Paper Machine 7 as commissioning

 Commissioning of 11KV switch gears(Vacuum circuit breakers) and startup of 11KV system in 11MW & 41MW power plan
 Commissioning & Startup of HV (11KV ) incoming, outgoing protection system
 Power transformers Hi Pot Test, insulation resistance test, OIL DI-electric strength test. Ratio test, winding resistance test.
 HV and MV cables insulation resistance HI POT tests.
 Bus bar including switch gears insulation resistance test and Hi POT test and Tightening of Bolts with Torque Wrench.
 Startup of LV MV transformers and incoming outgoing panels
 Meager Insulation test of LV, MV motor’s & Cables
 Startup of MCC, s variable frequency drives panels and Startup of LV, MV motors
 Dc drives & AC, DC Multi Drive system on paper machine
 Commissioning of PLC, DCS including Analogue input, Analogue output, Digital input,
Digital output Remote & I/O’s
 I/O testing of instruments (On-off valve, Control valve, Temperature transmitter, flow transmitter, weight transmitter & Different type of sensors) & Auma Actuators.
 Have experience of commissioning with foreigners’ of ABB, EXOR, SIEMENS, ANDRITS,


VARIABLE FREQUENCY DRIVES:

 Get training of VFD, s & Multi drive system
(ACS800, DCS600 & DCS 800 sectional drives) From ABB
 Commissioning & parameterization of Drives by its different Software’s

PLC & DCS:

 Have experience of working on different type of PLC, s
 Have experience of working on Siemens PLC S 7 and its Software Semitic manager & Win CC Flexible making program (Logic), HMI’s modifying & downloading in PLC
 Starting and Restarting of PLC System.
 Commissioning of DCS Panels AC 800M
 Replacement and repairing of Modules, I/O Cards.

DESIGNING:

 work experience on ETAP (Load flow analysis, Short circuit current study, ground fault, )
 Have Designing experience of power factor improvement panel
 Power Cables size calculation & involve in its procurement
 Load distribution on transformers and making single line drawings
 Have experience of Cable schedule & termination plan making of Power & control cables
 Have experience of instrument JB, s designing according to PLC & DCS based system
 Cable & cable tray root designing
 MCC.s and PDC’s (power distribution control) panel designing & involve in its procurement

MAINTENANCE:
 Have work experience of maintenance of Low voltage (380, 500 V) 3phase motors & starters from 0.25 KW ----1500 KW
 Have work experience of maintenance of Medium voltage (3.3, 6 & 11K V)
3-phase motors & its Switch Gears from 560 KW ----2000KW
 Have work experience of maintenance & trouble shouting of High voltage
(11000V) 900 KW slip ring motor & it’s starter
 Have work experience of maintenance of Low voltage (500V) Heavy duty DC motor & DC drives
 Power factor improvement panels.
 DC supply system (Batteries and Batteries Charges).& UPS
 Motors Power and Control Circuits.
 Variable frequency drives of varies companies (ABB, Danfuss, Omron, Siemens, Watt, Reliance)
 High and Low voltage protection systems.
 AC & DC sectional Drives (multi drives )
 Online trouble shouting of PLC & DCS based MCC, s and other control system

Education

Bachelor's degree, ELECTRICAL
  • at Preston Institute of Management Science and Technology
  • August 2011

B.Tech. (Hons) Bachelor in Electrical Technology (Hons)

Bachelor's degree, ELECTRICAL
  • at Preston Institute of Management Science and Technology
  • August 2009

B.Tech. Bachelor in Electrical Technology

Diploma, Electronics & Electrical
  • at Punjab Board of Technical Education Lahore
  • June 2005

Specialties & Skills

Electrical Engineering
Transmission Lines
Distribution Systems
Testing
Switchgear
Primavera
MS Office
Ms project

Languages

English
Expert
Arabic
Intermediate
Urdu
Expert

Memberships

Saudi council of Engineering
  • Engineering Accreditation
  • November 2012

Training and Certifications

Occupational safety and health manager (OSHA) (Certificate)
Date Attended:
January 2017
General industry safety and health (OSHA) (Certificate)
Date Attended:
March 2017
Primaver P6 (Certificate)
Date Attended:
January 2013
Valid Until:
January 2013

Hobbies

  • Book Reading
  • Net surfing