At First Saudi Company, I am responsible to handle high rise building projects here I am responsible that includes but not limited…
• Prepare weekly & Monthly reports for the presentation of comparison between actual Progress and planned targets.
• Responsible to prepare & present Extension of time
• Participate in meetings to present the current status of the project.
• Resource planning and Resource loading in the Schedule.
• Preparation of the Critical Path Analysis by Identifying the Critical Activities using Critical Path Method technique.
• To identify the long lead items
• Let the team know about the critical factors to avoid bottle neck
• Make analysis with comparison b/w Baseline Program and Updated Program.
• Preparation of Recovery Schedule to recover any delay.
Here at FSCC, I have experience of handling Etlal Tower & Ramla tower located at king Fahd Road, Riyadh. I have also worked on Ma’aden City Center Mall & Offices Project that is located King Abdullah Project for Waad Al Shamaal & City Development, Turaif.
At Steuker-KCH, I was responsible to handle different project planning related to rubber lining in phosphate tanks that includes but not limited…
• To conduct contractors meeting to review progress and compile MOM
• To prepare a Master Schedule for all component of the Program
• Responsible to track inventory for material used in rubber lining
• Prepare weekly & monthly reports for the presentation of comparison between actual Progress and planned targets.
• Responsible to prepare, review & present EOT.
• Preparation of the Critical Path Analysis by Identifying the Critical Activities using Critical Path Method technique.
• Preparation of Presentations to show current trends and to have an analytical idea of the project.
• Review the baseline schedule prepared by the contractor for the project.
• Estimation and Allocation of the Budget manhours required for the completion
At AlFaal United, I was responsible to handle different project planning at Royal Commission Yanbu that includes but not limited…
• Responsible for the development schedule to indicate specific milestones agreed upon in the Contract
• To coordinate with the different team based in Jeddah, Jazan and Yanbu
• To work with client planning team and is able to manage and negotiate project expectations and deliverables independently.
• To prepare weekly & monthly reports for the presentation of comparison between actual Progress and planned targets.
• To provide analysis of the progress and schedule performance including productivity and critical path
• To assist with development of change order notifications by highlighting impact on schedule and assist with related tracking and re-baselining effort
At Descon Construction Company, I was responsible to handle coordinating different aspects of the project that includes but were not limited…
• To understand the scope of work and preparation/approval of Planning Package Preparation of Manpower and Equipment Deployments and forecasting for succeeding months
• Generation of reports on a daily, weekly, and monthly basis as part of project monitoring with the use of planning tools as per requirements & application with inclusion of latest forecast & look-ahead plans.
• Monitoring of Engineering, Procurement, and Construction activities on approved registers and coordinating with Company and Client for mitigation of risks and delays.
• To preparation of Contractual Letters for highlighting major issues affecting or with the potential to affect the project with submission of notifications to allow robust backup for claims management.
• To prepare earned value analysis and key performance indicators.