Project: KJO-Laying of new Hout Crude Transmission Line (Contract # HQ466PC17)- New 20”OD Crude Transmission Line approximately 40 Km, RGS Platform Deck Extensions for installation, Scraper Launcher, Riser and riser clamps, Tie-ins with existing Facilities, Valves and piping, including utilities at Khafji Offshore Field.
Employer: Saipem/ Snamprogetti Offshore Division Dammam
Position: QC Coating Inspector
Period: Mar - 2023 to
Employer: Saipem/ Snamprogetti Offshore Division Dammam
Project: BERRI LTA-34-Berri Offshore Development Platforms and Flowlines BI-10-09501 (CRPO-650916456)
Project: MARJAN LTA-68- MRJN 2030, MRJN 2040 WI Platforms and One MRJN 770 Oil PDM and Associated Facilities (BI- 12-20000) (CRPO #6511040986)
Project: MARJAN LTA-35-Water Injection Facilities and Shallow Water Pipelines for Marjan Increment (CRPO #6510916460) (BI-10-12201/BI-10-12222) Its is an Offshore Project, and EPCI scope for 36’’ Subsea Pipeline, subsea valve skids and risers in Marjan Offshore Field.
Project: BERRI LTA-64 - Replacement of Water Injection Laterals, (BI-12-19000) This is an Offshore Project, and EPCI scope for the replacement of flexibles pipes, subsea valve skids and risers in BRRI Offshore Field.
Position: QC Coating Inspector
Period: Sep - 2022 to Mar 2023
Project: LTA-53 Long Term Agreement for Juaymah Offshore NGLF Facilities (BI-10-01914) This is an Offshore Project, and EPCI scope for the upgradation of Existing Platform and 36’’ Insulated Redundant Line to Offshore NGLF Loading terminal.
Project: Offshore Maintain Potential Program Zuluf Field PDM & Jacket (BI-12-19000) This is an Offshore Project under Aramco TUR. Installation of PDM & Jacket piping and Structural scope 51/246.
Position: QCI Coating/ Insulation
Period: Mar - 2021 to Aug 2022
Aramco Approved Coating Inspector and Bgas Grade I certified with more than 12 years of Quality experience in Coating Inspection, performing inspection activities for Offshore Jacket and Platform Installation, PDM, Pipeline field Girth weld internal and external coating system. Repair work for internal and external FBE coating. Atmospheric coating, concrete structure coating
APCS applied under current project, APCS-1B, 1C, 1E, APCS-12, APCS-19C, APCS-22A, APCS-26T, APCS-102, APCS-104,
Long Term Agreement for Juaymah Offshore NGLF Facilities LTA-53 (BI-10-01914) This is an Offshore Project, and EPCI scope for the upgradation of Existing Platform and 36’’ Insulated Redundant Line to Offshore NGLF Loading terminal.
Project: Offshore Maintain Potential Program Zuluf Field PDM & Jacket (BI-12-19000) This is an Offshore Project under Aramco TUR. Installation of PDM & Jacket piping and Structural scope 51/246.
Aramco Approved Coating Inspector and Bgas Grade I certified with more than 08 years of Quality experience in Coating Inspection, performing inspection activities for pipeline field Girth weld internal and external coating system. Repair work for internal and external FBE coating. aAtmospheric coating, concrete structure coating
APCS applied under current project, APCS-1A, APCS-1B, 1C, 1D APCS-3, APCS-10, APCS-22A APCS-26, APCS-26T, APCS-2A, APCS-2D, APCS-12, APCS-102, APCS-104, APCS-113A, APCS-120 etc.
Ensure adherence to project specification requirements related to Product, Personnel and Equipment Qualifications.
Perform “Hold”, “Witness” and “Surveillance” inspections at construction site to ensure compliance with SAUDI ARAMCO requirements and project specifications.
Inspect all painting & Blasting equipment and instruments prior to blasting and coating.
Verifying Humidity, Dew Point, Surface & Ambient Temperature & etc) Preliminary Blasting/Coating Inspection (Chloride Test, WFT, DFT, X Cut Test, Pull Out Adhesion Test & Holiday Test).
Conduct surface profile measurements with the press-O-film paper.
Monitoring ongoing site Blasting and painting activities as per client requirements.
Ensure surface cleanliness prior to coating application (primer / topcoat).
Monitor and check wet film / dry film requirements as per client specs.
Inspect coatings for any paint defects for touch up and repair.
Perceiving Coating and Insulation activities as per client requirements and standards.
Ensure the use of correct procedure for the paint mixing and applications.
Ensure that correct type of equipment and instruments are used for blasting and coating activities.
Perform holiday testing of underground piping to ensure that all coating defects are repaired prior to backfilling.
Responsible for Inspection Works for sandblasting and Painting of weld joints / Tie-In spools, platforms, pipe Supports, Application of VE coating and other miscellaneous painting works.
Raise RFI for final inspection / acceptance of Client inspector.
Monitoring, Witnessing, Inspection & Documentation of all painting & coating activities offsite & onsite.
Abrasive blasting; coating applications, priming, intermediate coat & top coat of various sizes of pipe spools to be insulated & un-insulated lines for various services.
Prepare inspection report for final inspection & acceptance of owner’s representative.
Issue INCR for any violations and submit it to the QA/QC Department /Client.
Attend daily/weekly quality meeting internal and client as assigned.
Ensure that all works are inspected as per the requirements of approved quality plan, inspection and test.
Ensure the use of correct blasting material and inspect and verify certificate.
Inspection and verifying the Blasting Equipment, Compressor, pressure gauge, air receiver, air hoses and air cooler.
Monitoring and verifying the blasting optimum pressure and technique.
Conducting Inspection for the degree of cleanliness of the substrate.
Check for contaminants before blasting and painting likewise oil & grease, millscale, chloride & sulphate and moisture test.
Surface cleanliness and profile measurements with the press-O-film paper.
Inspecting the roughness of the blasted area by clemtex method and surface profile measurement using dial micrometer and Testex tape.
Coating blasting material inspection and verification as per applicable SAES.
Inspecting and advice to maintain the storage requirements as per PDS.
Verify the Qualification of crew supervisor, Blasters and applicators as per SAEP-316.
Monitoring the weather condition air temperature, relative humidity, dew point and surface temperature.
Inspection & surveillance during the application of all stages and after.
Inspecting the WFT and DFT microns using appropriate gauge.
Identify and verify the rectifications of coating defects.
Stoppaq Application:
Ensure Material storage of Visco-Elastic coating system components as per manufacturer recommendations.
Verify Weather conditions Aramco product data sheet in SAES-H-002V.
Surface preparation inspection as per product data sheet and application requirements in SAES-H-002V.
Inspect Visco-Elastic coating application and overlapping as Aramco standards.
Inspection of outer wrap application and overlapping requirements.
Repairing of any damaged coating during inspection as per repair procedure.
Conduct Holiday detection test as required.
Coating inspection as per SAES H 001.
Coating inspection as per SAES H 003.
Coating inspection as per SAES H 101V
Inspection as per SAES H 102
Inspection as per SAES-B-067
and other applicable standards.
Pre inspection for concrete surface preparation inspection, moisture test, surface free from contaminants.
Monitoring the air temperature, relative humidity, dew point and surface temperature.
Repair of cracks, honey combs, pop-outs, and other irregularities of concrete Surface contaminants that inhibit coating adhesion or induce early coating deterioration shall be removed.
Roughen the smooth surfaces to improve coating adhesion, remove any weak surface layers to provide strong base as required for many coating system.
Prepare the surface by abrasive blasting, hand tools or power tools as per coating system applied.
Salt test or other contaminant test perform and remove if any, remove laitance layer from the surface.
Coating applied must be according to approved WMS and Aramco standards.
Check WFT & DFT should be in max-min limits of applied APCS.
Ensure Inter-coat intervals to be observed as per PDS or SAES-H-001/SAES-H-003.
Use correct application equipment as specified in PDS of coating materials.