Line Superintendent-I
Lahore Electric Supply Company Limited
Total years of experience :24 years, 9 Months
1. Pole erection
2. Grounding counter position
3. Stringing of HV/LV conductors
4. Inspection/Testing & installation of distribution transformers.
5. Under ground cable laying, testing on pole and inside substation breakers.
6. Project completion & final taking over of the project.
7. Also responsible for material, quality & quantity on site.
8. The other responsibilities were to monitor contractor’s construction to be in compliance with approved drawing and methods of construction.
We are Consultants of the External Electrification of the Housing Societies, Commercial Buildings etc and my Job detail is as under:
1. Survey of the suites (Housing Societies, Big Plaza’s & Commercial Buildings etc)
2. Prepare the Load Assessment.
3. Prepare the Estimates and B.O.Q’s.
My role including control the main generator panel, generators synchronize with 11kv bus bar and after connected to main transmission line with SF6 circuit breakers.
My role is assist and takes the readings of all parameters who are installed on the main control panel.