Engage in the development of resource and cost loaded baseline schedules.
Monitor and notify project progress and delays with respect to the baseline schedule.
Preparation of Look ahead schedules.
Monitored and recorded productivity of labor and equipment.
Engage in preparation of Project Daily, Weekly and Monthly Reports and Presentations.
Assist in preparation of timely and accurate interim payments.
Prepare Extension of Time claim.
Attend Weekly Progress and other meetings as applicable.
Projects:
Lusail and Ras Abu Aboud Stadium (FIFA World Cup 2022)
Responsibilities:
Engage in detailed review / monitoring of Contractor’s submitted programme and records Contractor’s performance and trends.
Responsible in monitoring project progress / delays to approved execution programme and determines issues instigated the deviation in time for completion.
Supervise in preparation of interim reports for submission to Client including but not limited to Weekly, Monthly, What-If Analysis and End User Reports.
Evaluate time impact of approved scope changes and analysis of Contractor’s Extension of Time Claims.
Convening workshops with the team to discuss project risks, opportunities and any mitigation strategies to maintain scheduled completion date.
Review and certifies Contractor’s Interim Payment Application.
Attend Weekly Progress and other meetings as applicable.
Projects:
All Company Projects
Responsibilities:
Prepare project baseline schedule package.
Daily monitoring report and updating of project accomplishment.
Weekly updating of Project schedule and generating S-curve.
Generating planned vs. actual resource curves.
Preparation of Look ahead schedules.
Preparation of Weekly and Monthly Reports and Dashboards for Client and Head Office.
Preparation of Monthly Forecast of manpower and equipment.
Attends weekly progress meetings with project team and client.
Regular coordination with Clients.
Notification of Engineering, Procurement and Construction delays.
Preparation of Monthly Progress Presentation.
Preparation of Extension of Time claims.
Projects:
Lusail Office Tower COM-18
Responsibilities:
Engage in the development of resource and cost loaded baseline schedules.
Monitor and notify project progress and delays with respect to the baseline schedule.
Monitored and recorded productivity of labor and equipment.
Engage in preparation of Project Daily, Weekly and Monthly Reports and Presentations.
Prepare timely and accurate interim payments.
Prepare of Extension of Time claim.
Prepare Monthly Project Execution Reports (PERs) with updates on major commitments and baseline cost breakdown.
Attend Weekly Progress and other meetings as applicable.
Projects:
Construction of MEEZA Data Center MV2
Texas A&M University Fit-out
Construction of QSTP Tech-4 Building
Responsibilities:
Engage in detailed review/ monitoring of Contractor’s submitted programme and records Contractor’s performance and trends.
Responsible in monitoring project progress/delays to approved execution programme and determines of issues instigated the deviation in time for completion.
Prepare interim reports for submission to Client including but not limited to Weekly, Monthly, What-If Analysis and End User Reports.
Evaluate time impact of approved scope changes and analysis of Contractor’s Extension of Time Claims.
Convening workshops with the team to discuss project risks, opportunities and any mitigation strategies to maintain scheduled completion date.
Attend Weekly Progress and other meetings as applicable.
Projects:
Construction of Rocco Forte Hotel - Abu Dhabi
Mechanical and Piping Erection, Electrical and Instrumentation works for King Abdullah Financial District - District Cooling Plant - Riyadh, Saudi Arabia.
Erection of Chilled Water Pipelines for Dubai Metro Project.
Rehabilitation of Hangars at Al Bateen Executive Airport - Abu Dhabi
Responsibilities:
Engage in the development of resource and cost loaded baseline schedules.
Monitor and notify project progress and delays with respect to the baseline schedule.
Monitored and recorded productivity of labor and equipment.
Engage in preparation of Project Daily, Weekly and Monthly Reports and Presentations.
Studying the contract scope, requirements, challenges, direct and indirect cost assessments, cost allocations, analyzing budget vs. actual and produce reports on cost variance.
Prepare timely and accurate interim payments.
Prepare of Extension of Time claim.
Attend Weekly Progress and other meetings as applicable.
Projects:
Chilled Water Piping for Dubai Metro
Responsibilities:
Engage in the development of resource and cost loaded baseline schedules.
Monitor and notify project progress and delays with respect to the baseline schedule.
Monitored and recorded productivity of labor and equipment.
Engage in preparation of Project Daily, Weekly and Monthly Reports and Presentations.
Studying the contract scope, requirements, challenges, direct and indirect cost assessments, cost allocations, analyzing budget vs. actual and produce reports on cost variance.
Prepare timely and accurate interim payments.
Prepare of Extension of Time claim.
Attend Weekly Progress and other meetings as applicable.
Projects:
Construction of G.A. Tower 2 Building (2 buildings 30 floors each)
Erection of Steel Structures for Hanjin Shipyard
Responsibilities:
Engage in the development of resource and cost loaded baseline schedules.
Monitor and notify project progress and delays with respect to the baseline schedule.
Monitored and recorded productivity of labor and equipment.
Engage in preparation of Project Daily, Weekly and Monthly Reports and Presentations.