Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


User unblocked successfully
Thank you. Your report has been submitted and will be reviewed shortly.
nilesh kajabaje,   Commissioning Engineer

nilesh kajabaje

Commissioning Engineer·Samsung Saudi Arabia

India

Bachelor's degree, Mechanical Engineering

Work experience

Total years of experience: 10 years, 5 months

Commissioning Engineer

August 2012 - October 2013

Samsung Saudi Arabia

Jubail, Saudi Arabia

August 2012 - October 2013

Natural Gas line network air blowing & air freeing by nitrogen .
LPTT of natural gas line network by nitrogen on 7 bar.
Plant air network air blowing with target inspection on PMT presence & LPTT on 7 bar.
Co2 &Ar storage tank & their evaporator LPTT by nitrogen on 7 bar.
Co2 &Ar tank shell vacuum checking with Torr meter.
Ar tank shell vacuum creating by portable vacuum pump up to 350 torr.
First fill in Ar& Co2 tank according vendor procedure.
Chiller pipe line HPTT up to 25 bar by nitrogen with chiller vendor.
NH3 charging in chiller preparation & execution in presence of chiller vendor
Potable, cooling & process water network flushing & passivation.
Cooling water emergency overhead tank flow adjustment.
Water cooling plant flushing & passivation.
Ingot casting vendor BEFESA, pre commissioning machine adjustment mechanical support, pneumatic network air blowing & adjustment for cylinders movement.
Weighing scales & overhead cranes inside CAST HOUSE calibration work support to VELOSI & SASO.
Billet casting vendor HEARWITCH hydraulic network tuning & pneumatic network mechanical work support.
Hydraulic valve stand rectification work according vendor S/V.
Slab casting VDC vendor WAGSTAFF pre commissioning work support.
Billet holding furnace refractory dry outup to 800 degree Celsius.
Billet holding furnace entry blind list preparation & LOTO.
Blind list preparation for client hand over.
Chlorine gas line network chemical cleaning according to chlorine institute standards.
Purple tag walk down punch list preparation & closing.(Mechanical Completion).
Gray tag walk down punch list preparation & closing.9practical completion).
Hot Commissioning in cast house by ALCOA supporting work.
Spare part list for Operation handover to Ma’aden Operation.
LOTO preparation & application for initial energiation of gasline, waterline, airline.
Maintaining LOTO practice according PMT BECHTEL procedure.
Co-ordination for punch clearing with construction & client.
Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor’s representatives.
Support vendor’s representative to carry of pre commissioning test and during start-up.
Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
Estimation of manpower, equipment’s and materials necessary for each activity.Forwarding to management for approval and to construction contractor.
Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company industry:
Installation & Technical Services
Job role:
Oil and Gas

COMMISSIONING MECHANICAL SUPERVISOR

November 2010 - February 2011

QATAR SHELL GAS TO LIQUID (QSGTL

November 2010 - February 2011

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.

Job role:
Mechanical Engineering

MECHANICAL SUPERVISOR

May 2010 - June 2010

OMAN LNG

Oman

May 2010 - June 2010

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company industry:
Oil & Gas
Job role:
Mechanical Engineering

Commissioning Mechanical Engineer

April 2009 - March 2010

Saudi Armco

Saudi Arabia

April 2009 - March 2010

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.

Company industry:
Oil & Gas
Job role:
Mechanical Engineering

MECHANICAL SUPERVISOR

May 2008 - January 2009

BOROUGE-2 ADNOC UAE

May 2008 - January 2009

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.

Job role:
Mechanical Engineering

Mechanical Technician/ Foreman in Plant Maintenance Division

October 2007 - November 2007

AL-OSAIS INTERNAIONAL HOLDING CO

October 2007 - November 2007

➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.

Job role:
Maintenance, Repair, and Technician

MECHANICAL FOREMAN

October 2007 - November 2007

QATAR FARTILISER (QAFCO

October 2007 - November 2007

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.

Job role:
Engineering

Mechanical Foreman

August 2005 - August 2007

Merco

August 2005 - August 2007

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.

Company industry:
Heavy Industry & Metallurgy
Job role:
Engineering

structural fabrication Supervisor

June 2005 - August 2005

Khaitan Agro Ltd

June 2005 - August 2005

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.

Job role:
Management

Installation Supervisor

January 2005 - May 2005

Pitle Engg. Private Ltd

January 2005 - May 2005

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.

Job role:
Engineering

Mechanical Supervisor

October 2004 - December 2004

Aluminum Africa Ltd

October 2004 - December 2004

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.
➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.

Job role:
Mechanical Engineering

Mechanical Supervisor

August 2004 - September 2004

Dassnagar Precision Engg. Pvt. Ltd

August 2004 - September 2004

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.

Job role:
Mechanical Engineering

May 2004 - July 2004

Ispat Metallic India Ltd

May 2004 - July 2004

➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.

Job role:
Other

Mechanical Supervisor

May 2004 - July 2004

Ispat Metallic India Ltd

May 2004 - July 2004

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.

Job role:
Mechanical Engineering

Mechanical Maintenance Technician

January 2002 - May 2004

Ispat Metallic India Ltd

January 2002 - May 2004

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.
➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.

Job role:
Maintenance, Repair, and Technician

plant MECHANICAL TECHNICIAN

January 2002 - October 2002

Ispat Metallic India Ltd

January 2002 - October 2002

Job role:
Mechanical Engineering

Mechanical Maintenance Technician

August 2000 - August 2001

Alta Laboratories Pvt. Ltd

India

August 2000 - August 2001

Company Alta Laboratories Pvt. Ltd. Khopoli
Designation Mechanical Maintenance Technician
Job Period 14. Aug 2000 to13 Aug. 2001
Job Responsibilities
Maintenance of ball mill reactor, centrifuge, centrifugal pump, electrical dryer, pneumatic dryer, roller mill, fire tube boiler, reciprocating pump, reciprocating compressor, glass lined reactor


Personal Details:



Contact No. (Residence) - +91-9220595072

Permanent Address - Behind Rajhans Bldg. Dev Ali, Pen,
Dist: Raigad, 402107

Job role:
Maintenance, Repair, and Technician

Pre commissioning Coordinator (Cast House)

-

Cast House

India

-

➢**Working for Maa'den Aluminum Cast House through Samsung Saudi Arabia as Pre Commissioning Engineer from 15 AUG 2012 to till 22 Oct 2013.
➢**Worked for TAREER SHUTDOWN 2012 as Mechanical Supervisor from Descon Engg. From 26 Jan 2012 to 18 Apr 2012.
➢**Worked for QSGTL plant as commissioning mechanical supervisor for THC (TOYO HUNDAI CONSORTIUM) from 5 Nov 2010 to 2 Feb 2011.
➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.
➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter

Company industry:
Media Production
Job role:
Other

Pre commissioning Coordinator (Cast House)

-

TAKREER ADNOC

India

-

➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company industry:
Oil & Gas
Job role:
Other

MECHANICAL SUPERVISOR

-

QATAR SHELL GAS TO LIQUID

India

-

➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.
➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company industry:
Oil & Gas
Job role:
Mechanical Engineering

COMMISSIONING MECHANICAL SUPERVISOR

-

Sur plant

India

-

➢**Worked for Oman Lng Sur plant as maintenance executive with vendor from 27 May to 25 June 2010.
➢**Worked for Saudi Aramco with KAUST Project as commissioning Mechanical Technician Designation) under Al-Hugayet Contracting Est. from 1 April, 2009 to 31 March 2010.
➢**Worked with BOROUGE as MECHANICAL SUPERVISOR through TECNIMONT from 11 MAY 2008 To 11 JAN 2009.
➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.
➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Job role:
Mechanical Engineering

COMMISSIONING MECHANICAL SUPERVISOR

-

BOROUGE-2 ADNOC UAE

India

-

➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.

Job role:
Mechanical Engineering

COMMISSIONING MECHANICAL SUPERVISOR

-

QATAR FARTILISER

India

-

➢**Worked with QATAR FARTILISER (QAFCO) as MECHANICAL FOREMAN through QCON from 23 OCT 2007 to 26 NOV 2007.
➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.
➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
Company BOROUGE-2 ADNOC UAE
Designation MECHANICAL SUPERVISOR
Job Period 11 MAY 2008 to 11 JAN 2009
Job Responsibility

➢**Reports to the Construction Manager and deputizes as the senior representative from site.
➢**Oversees and provides advice regarding the work activities performed by .site based organization and the Third Party Inspection ..
➢**Monitors the Construction activities in the field from a performance management perspective against requirements.
➢**Reviews method statements, plans, schedules and procedures.
Participates in site safety audits.
➢**Witness key hold points during construction on an as-required basis.
➢**Chairs the Weekly Progress and HSE Meetings
➢**Assists in the handover of systems to the Commissioning team

Job role:
Mechanical Engineering

COMMISSIONING MECHANICAL SUPERVISOR

-

Merco

India

-

➢**Worked with Merco (AL-OSAIS INTERNAIONAL HOLDING CO.) as a Mechanical Technician/ Foreman in Plant Maintenance Division from 18 Aug.2005 to 20 Aug 2007 in SAUDI ARABIA.
➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
Company BOROUGE-2 ADNOC UAE
Designation MECHANICAL SUPERVISOR
Job Period 11 MAY 2008 to 11 JAN 2009
Job Responsibility

➢**Reports to the Construction Manager and deputizes as the senior representative from site.
➢**Oversees and provides advice regarding the work activities performed by .site based organization and the Third Party Inspection ..
➢**Monitors the Construction activities in the field from a performance management perspective against requirements.
➢**Reviews method statements, plans, schedules and procedures.
Participates in site safety audits.
➢**Witness key hold points during construction on an as-required basis.
➢**Chairs the Weekly Progress and HSE Meetings
➢**Assists in the handover of systems to the Commissioning team

Company . QATAR FARTILISER (QAFCO)
Designation MECHANICAL FOREMAN
Job Period 23 OCT 2007 to 26 NOV 2007
Job Responsibility
➢**Replacement of tube hit exchanger.
➢**Replacement of casing of air blower.
➢**Replacement of butterfly valve 12"14".
➢**Replacement of gate valve 12"14".
➢**Fabrication of 80th schedule pipe 12"14".
➢**Handling technique of technical worker.
➢**Rectification of heavy scheduled pipe according to drawing.
➢**Replacement of tube bandle of tube heat exchanger.

Company industry:
Heavy Industry & Metallurgy
Job role:
Mechanical Engineering

COMMISSIONING MECHANICAL SUPERVISOR

-

Khaitan Agro Ltd

India

-

➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
Company BOROUGE-2 ADNOC UAE
Designation MECHANICAL SUPERVISOR
Job Period 11 MAY 2008 to 11 JAN 2009
Job Responsibility

➢**Reports to the Construction Manager and deputizes as the senior representative from site.
➢**Oversees and provides advice regarding the work activities performed by .site based organization and the Third Party Inspection ..
➢**Monitors the Construction activities in the field from a performance management perspective against requirements.
➢**Reviews method statements, plans, schedules and procedures.
Participates in site safety audits.
➢**Witness key hold points during construction on an as-required basis.
➢**Chairs the Weekly Progress and HSE Meetings
➢**Assists in the handover of systems to the Commissioning team

Company . QATAR FARTILISER (QAFCO)
Designation MECHANICAL FOREMAN
Job Period 23 OCT 2007 to 26 NOV 2007
Job Responsibility
➢**Replacement of tube hit exchanger.
➢**Replacement of casing of air blower.
➢**Replacement of butterfly valve 12"14".
➢**Replacement of gate valve 12"14".
➢**Fabrication of 80th schedule pipe 12"14".
➢**Handling technique of technical worker.
➢**Rectification of heavy scheduled pipe according to drawing.
➢**Replacement of tube bandle of tube heat exchanger.

Company Merco (AL-OSAIS INTERNAIONAL HOLDING CO.)
Designation Mechanical Foreman
Job Period 18 Aug.2005 to 20 Aug 2007
Job Responsibility
➢** Pump house periodic and breakdown maintenance.
➢**R.O. Water treatment plant schedule maintenance.
➢**Boiler house periodic and breakdown maintenance.
➢**Nitrogen gas storage tank maintenance.
➢**Maintaining warehouse log sheet.
➢**Cracking reactor agitator maintenance.
➢**Cooling reactor agitator maintenance.
➢**Cracking and cooling reactor annual chemical cleaning.
➢**Gearbox maintenance.
➢**Forklift operating and maintenance.

Job role:
Mechanical Engineering

structural fabrication Supervisor

-

Pitle Engg. Private Ltd

India

-

➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
Company BOROUGE-2 ADNOC UAE
Designation MECHANICAL SUPERVISOR
Job Period 11 MAY 2008 to 11 JAN 2009
Job Responsibility

➢**Reports to the Construction Manager and deputizes as the senior representative from site.
➢**Oversees and provides advice regarding the work activities performed by .site based organization and the Third Party Inspection ..
➢**Monitors the Construction activities in the field from a performance management perspective against requirements.
➢**Reviews method statements, plans, schedules and procedures.
Participates in site safety audits.
➢**Witness key hold points during construction on an as-required basis.
➢**Chairs the Weekly Progress and HSE Meetings
➢**Assists in the handover of systems to the Commissioning team

Company . QATAR FARTILISER (QAFCO)
Designation MECHANICAL FOREMAN
Job Period 23 OCT 2007 to 26 NOV 2007
Job Responsibility
➢**Replacement of tube hit exchanger.
➢**Replacement of casing of air blower.
➢**Replacement of butterfly valve 12"14".
➢**Replacement of gate valve 12"14".
➢**Fabrication of 80th schedule pipe 12"14".
➢**Handling technique of technical worker.
➢**Rectification of heavy scheduled pipe according to drawing.
➢**Replacement of tube bandle of tube heat exchanger.

Company Merco (AL-OSAIS INTERNAIONAL HOLDING CO.)
Designation Mechanical Foreman
Job Period 18 Aug.2005 to 20 Aug 2007
Job Responsibility
➢** Pump house periodic and breakdown maintenance.
➢**R.O. Water treatment plant schedule maintenance.
➢**Boiler house periodic and breakdown maintenance.
➢**Nitrogen gas storage tank maintenance.
➢**Maintaining warehouse log sheet.
➢**Cracking reactor agitator maintenance.
➢**Cooling reactor agitator maintenance.
➢**Cracking and cooling reactor annual chemical cleaning.
➢**Gearbox maintenance.
➢**Forklift operating and maintenance.

Company Khaitan Agro Ltd
Designation structural fabrication Supervisor
Job Period 2 June 2005 to 10 Aug. 2005.
Job Responsibility

➢**Checking fabrication drawing.
➢**Preparing Bill Of Material according to drawing.
➢**Fabricate erection MKD according to drawing.
➢**Inspection of each fabricated item according to drawing.
➢**Erection of fabricated item according to erection drawing

Job role:
Management

COMMISSIONING MECHANICAL SUPERVISOR

-

Aluminum Africa Ltd

India

-

➢**Worked with Khaitan Agro Ltd., as a structural fabricator on solvent extraction plant in Ratlam in MP. From 2 June 2005 to 10thAug. 2005.
➢**Worked with Pitle Engg. Private Ltd., as as machine assembly and alignment fitter for Continuous Galvanizing Line (CGL) in Gujrat from 25 Jan. 2005 to 30 May 2005.
➢**Worked with RSB Engg. As a Mechanical Technician recently completed dismantling coding, packing, loading ACHANBANCH 4 HI COLD ROLLING MILLin Aluminum Africa Ltd., Dar Es Salaam, Tanzania from 5 Oct. 2004 to 8 Dec. 2004.
➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
Company BOROUGE-2 ADNOC UAE
Designation MECHANICAL SUPERVISOR
Job Period 11 MAY 2008 to 11 JAN 2009
Job Responsibility

➢**Reports to the Construction Manager and deputizes as the senior representative from site.
➢**Oversees and provides advice regarding the work activities performed by .site based organization and the Third Party Inspection ..
➢**Monitors the Construction activities in the field from a performance management perspective against requirements.
➢**Reviews method statements, plans, schedules and procedures.
Participates in site safety audits.
➢**Witness key hold points during construction on an as-required basis.
➢**Chairs the Weekly Progress and HSE Meetings
➢**Assists in the handover of systems to the Commissioning team

Company . QATAR FARTILISER (QAFCO)
Designation MECHANICAL FOREMAN
Job Period 23 OCT 2007 to 26 NOV 2007
Job Responsibility
➢**Replacement of tube hit exchanger.
➢**Replacement of casing of air blower.
➢**Replacement of butterfly valve 12"14".
➢**Replacement of gate valve 12"14".
➢**Fabrication of 80th schedule pipe 12"14".
➢**Handling technique of technical worker.
➢**Rectification of heavy scheduled pipe according to drawing.
➢**Replacement of tube bandle of tube heat exchanger.

Company Merco (AL-OSAIS INTERNAIONAL HOLDING CO.)
Designation Mechanical Foreman
Job Period 18 Aug.2005 to 20 Aug 2007
Job Responsibility
➢** Pump house periodic and breakdown maintenance.
➢**R.O. Water treatment plant schedule maintenance.
➢**Boiler house periodic and breakdown maintenance.
➢**Nitrogen gas storage tank maintenance.
➢**Maintaining warehouse log sheet.
➢**Cracking reactor agitator maintenance.
➢**Cooling reactor agitator maintenance.
➢**Cracking and cooling reactor annual chemical cleaning.
➢**Gearbox maintenance.
➢**Forklift operating and maintenance.

Company Khaitan Agro Ltd
Designation structural fabrication Supervisor
Job Period 2 June 2005 to 10 Aug. 2005.
Job Responsibility

➢**Checking fabrication drawing.
➢**Preparing Bill Of Material according to drawing.
➢**Fabricate erection MKD according to drawing.
➢**Inspection of each fabricated item according to drawing.
➢**Erection of fabricated item according to erection drawing

Company Pitle Engg. Private Ltd
Designation Installation Supervisor
Job Period 25 Jan. 2005 to 30 May 2005.
Job Responsibility
➢**Checking the foundations pockets according to the erection drawing.
➢**Assembly the machines parts according to the assembly drawing.
➢**Erect the machines, level the machines according to the erection drawing.
➢**Checking the swing of each roller of each machine to pass line given in the drawing.
➢**Fabrication & erection of hydraulic pipeline network.
➢**Fabrication & erection of pneumatic pipeline network.
➢**Commissioning total line.

Job role:
Mechanical Engineering

structural fabrication Supervisor

-

Dassnagar Precision Engg. Pvt. Ltd

India

-

➢**Worked with Dassnagar Precision Engg. Pvt. Ltd .in National Steel Indore as Hydraulic Technician from 1 Aug. 2004 to 10thSep. 2004.
➢**Worked with Technological engineering contractors for Ispat Metallic India Ltd. In coal injection plant as a structure fabricator from 25 May 2004 to 28 July. 2004.
➢**Worked with Ispat Metallic India Ltd. From 10 Oct. 2002 to 24 May 2004 as a Maintenance Technician in Hot roll mill.
➢**From Jan. 8 2002 to Oct. 9 2002 working for Ispat Metallic India ltd. Dolvi. Through prigo engg. As a plant MECHANICAL TECHNICIAN (operation & maintenance) Consisting.
➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
Company BOROUGE-2 ADNOC UAE
Designation MECHANICAL SUPERVISOR
Job Period 11 MAY 2008 to 11 JAN 2009
Job Responsibility

➢**Reports to the Construction Manager and deputizes as the senior representative from site.
➢**Oversees and provides advice regarding the work activities performed by .site based organization and the Third Party Inspection ..
➢**Monitors the Construction activities in the field from a performance management perspective against requirements.
➢**Reviews method statements, plans, schedules and procedures.
Participates in site safety audits.
➢**Witness key hold points during construction on an as-required basis.
➢**Chairs the Weekly Progress and HSE Meetings
➢**Assists in the handover of systems to the Commissioning team

Company . QATAR FARTILISER (QAFCO)
Designation MECHANICAL FOREMAN
Job Period 23 OCT 2007 to 26 NOV 2007
Job Responsibility
➢**Replacement of tube hit exchanger.
➢**Replacement of casing of air blower.
➢**Replacement of butterfly valve 12"14".
➢**Replacement of gate valve 12"14".
➢**Fabrication of 80th schedule pipe 12"14".
➢**Handling technique of technical worker.
➢**Rectification of heavy scheduled pipe according to drawing.
➢**Replacement of tube bandle of tube heat exchanger.

Company Merco (AL-OSAIS INTERNAIONAL HOLDING CO.)
Designation Mechanical Foreman
Job Period 18 Aug.2005 to 20 Aug 2007
Job Responsibility
➢** Pump house periodic and breakdown maintenance.
➢**R.O. Water treatment plant schedule maintenance.
➢**Boiler house periodic and breakdown maintenance.
➢**Nitrogen gas storage tank maintenance.
➢**Maintaining warehouse log sheet.
➢**Cracking reactor agitator maintenance.
➢**Cooling reactor agitator maintenance.
➢**Cracking and cooling reactor annual chemical cleaning.
➢**Gearbox maintenance.
➢**Forklift operating and maintenance.

Company Khaitan Agro Ltd
Designation structural fabrication Supervisor
Job Period 2 June 2005 to 10 Aug. 2005.
Job Responsibility

➢**Checking fabrication drawing.
➢**Preparing Bill Of Material according to drawing.
➢**Fabricate erection MKD according to drawing.
➢**Inspection of each fabricated item according to drawing.
➢**Erection of fabricated item according to erection drawing

Company Pitle Engg. Private Ltd
Designation Installation Supervisor
Job Period 25 Jan. 2005 to 30 May 2005.
Job Responsibility
➢**Checking the foundations pockets according to the erection drawing.
➢**Assembly the machines parts according to the assembly drawing.
➢**Erect the machines, level the machines according to the erection drawing.
➢**Checking the swing of each roller of each machine to pass line given in the drawing.
➢**Fabrication & erection of hydraulic pipeline network.
➢**Fabrication & erection of pneumatic pipeline network.
➢**Commissioning total line.

Company Aluminum Africa Ltd., Dar Es Salaam, Tanzania
Designation Mechanical Supervisor
Job Period 5 Oct. 2004 to 8 Dec. 2004.
Job Responsibility
➢**Checking through points and center points and preparing drawing.
➢**Checking levels of different rolls and preparing drawing.
➢**Removing oil and coolant (oil) from lubrication network.
➢**Checking distance between different couplings.
➢**Dismantling rotating machines from their prime movers.
➢**Assembled machines parts.
➢**Loading all parts of 4 hi aluminum rolling mill in container.

Job role:
Management

Mechanical Maintenance Technician

-

Alta Laboratories Pvt. Ltd

India

-

➢**Working with Alta Laboratories Pvt. Ltd. Khopoli. As a shift Engg. of14. Aug 2000 to13 Aug. 2001

DETAILS OF EXPERIENCE
Company. Maa'den Aluminium Smelter
Designation Pre commissioning Coordinator (Cast House)
Job Period 15 AUG 2012 TO 22 Oct 2013
Job Responsibility
➢**Reviewing final issued PID's from point of view of pre commissioning and start-up, issuing of PID's modification according with project standards and regulations.
➢**Preparing scope and the responsibilities for pre-commissioning activities.
➢**Identifying systems and sub-systems by marking up of PFD's and PID's - system definition.
➢**Assisting construction departments by defining of priority systems according with overall construction and pre-commissioning planning and schedule.
➢**Preparation of pre-commissioning, execution plan.
➢**Developing safety procedures to be used during pre-commissioning activities such as tagging, vessels entry for inspections, isolation & blind installation procedures and work permit procedures in collaboration with HSE department.
➢**Developing punch list procedure and exception list for handover.
➢**Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
➢**Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
➢**Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor's representatives.
➢**Support vendor's representative to carry of pre commissioning test and during start-up.
➢**Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards.
➢**Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre-commissioning.
➢**Estimation of manpower, equipments and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
➢**Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
➢**Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
➢**Assure technical assistance for commissioning and start-up of units on request of client operation group.

Company. TAKREER ADNOC
Designation MECHANICAL SUPERVISOR
Job Period 26 JAN 2012 TO 18 APR 2012
Job Responsibility
➢**Pre-Shutdown Planning - preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/equipments.
➢**Shutdown Planning - preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
➢**Shutdown Maintenance Activities - execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc), coordinating with the other service departments for fabrication, machining, etc.
➢**Post Shutdown Reporting - preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
➢**Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and deblinding.
➢**Fabrication/Erection of Steel structures.
➢**Experience in hydro testing/pneumatic/nitrogen testing of tubes.
➢**Exposure to DP Testing and Other types of NDT Test.
➢**Able to read process drawings (PID/PFD), MIG and Arc welding.
➢**Preparing Job Completion Report & Site Handover to Project/Plant Personnel.
➢**Ability to supervise a multi-national workforce.

Company . QATAR SHELL GAS TO LIQUID (QSGTL)
Designation COMMISSIONING MECHANICAL SUPERVISOR
Job Period 5 NOV 2010 to 02 FEB 2011
Job Responsibility-

➢**Carried out inspection for MRT of pumps with client.
➢**Preservation of pumps up to handover to company.
➢**Pre MRT checklist preparation.
➢**Document preparation for inspection.
➢**Condition monitoring within pump MRT.
➢**Spring support adjustment & released.

Company . OMAN LNG (SUR PLANT)
Designation MECHANICAL SUPERVISOR
Job Period 27 MAY 2010 to 26 JUNE 2010
Job Responsibility--

➢**Handling technique of technical worker.

➢**Spading means isolation for reciprocating compressor for its maintenance

➢**Preparation lockout & tag out for maintenance job.

➢**Conducting bump test for piston.

➢**Conducting run out test for piston rod

➢**Checking gap between piston rings & cylinder head

➢**Replacement of crosshead sliding plates

➢**Suction & discharge valves replacement

Company Saudi Armco with KAUST Project
Designation Commissioning Mechanical Engineer Job Period 1 April 2009 to 31 March 2010.
Job Responsibility:
➢**Coordinating construction of the project on site and ensure smooth running of all on site tasks.
➢**Acting as a link between the on-site project team subcontracted operatives.
➢**Coordinating the construction of the project on site on a daily basis.
➢**Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
➢**Reviewing all drawings, RFI's where required, via the contractor, to establish sufficient information to construct.
➢**Site Diary is updating and reviewing on a daily basis.
➢**Implementing strict adherence to safety rules and regulations on a daily basis.
➢**Dialoging with all subcontractors to ensure the program is complied to.
➢**Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
➢**Inspecting requests for work completed.
➢**Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
➢**Checking all installations in preliminary stage.
➢**Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
Company BOROUGE-2 ADNOC UAE
Designation MECHANICAL SUPERVISOR
Job Period 11 MAY 2008 to 11 JAN 2009
Job Responsibility

➢**Reports to the Construction Manager and deputizes as the senior representative from site.
➢**Oversees and provides advice regarding the work activities performed by .site based organization and the Third Party Inspection ..
➢**Monitors the Construction activities in the field from a performance management perspective against requirements.
➢**Reviews method statements, plans, schedules and procedures.
Participates in site safety audits.
➢**Witness key hold points during construction on an as-required basis.
➢**Chairs the Weekly Progress and HSE Meetings
➢**Assists in the handover of systems to the Commissioning team

Company . QATAR FARTILISER (QAFCO)
Designation MECHANICAL FOREMAN
Job Period 23 OCT 2007 to 26 NOV 2007
Job Responsibility
➢**Replacement of tube hit exchanger.
➢**Replacement of casing of air blower.
➢**Replacement of butterfly valve 12"14".
➢**Replacement of gate valve 12"14".
➢**Fabrication of 80th schedule pipe 12"14".
➢**Handling technique of technical worker.
➢**Rectification of heavy scheduled pipe according to drawing.
➢**Replacement of tube bandle of tube heat exchanger.

Company Merco (AL-OSAIS INTERNAIONAL HOLDING CO.)
Designation Mechanical Foreman
Job Period 18 Aug.2005 to 20 Aug 2007
Job Responsibility
➢** Pump house periodic and breakdown maintenance.
➢**R.O. Water treatment plant schedule maintenance.
➢**Boiler house periodic and breakdown maintenance.
➢**Nitrogen gas storage tank maintenance.
➢**Maintaining warehouse log sheet.
➢**Cracking reactor agitator maintenance.
➢**Cooling reactor agitator maintenance.
➢**Cracking and cooling reactor annual chemical cleaning.
➢**Gearbox maintenance.
➢**Forklift operating and maintenance.

Company Khaitan Agro Ltd
Designation structural fabrication Supervisor
Job Period 2 June 2005 to 10 Aug. 2005.
Job Responsibility

➢**Checking fabrication drawing.
➢**Preparing Bill Of Material according to drawing.
➢**Fabricate erection MKD according to drawing.
➢**Inspection of each fabricated item according to drawing.
➢**Erection of fabricated item according to erection drawing

Company Pitle Engg. Private Ltd
Designation Installation Supervisor
Job Period 25 Jan. 2005 to 30 May 2005.
Job Responsibility
➢**Checking the foundations pockets according to the erection drawing.
➢**Assembly the machines parts according to the assembly drawing.
➢**Erect the machines, level the machines according to the erection drawing.
➢**Checking the swing of each roller of each machine to pass line given in the drawing.
➢**Fabrication & erection of hydraulic pipeline network.
➢**Fabrication & erection of pneumatic pipeline network.
➢**Commissioning total line.

Company Aluminum Africa Ltd., Dar Es Salaam, Tanzania
Designation Mechanical Supervisor
Job Period 5 Oct. 2004 to 8 Dec. 2004.
Job Responsibility
➢**Checking through points and center points and preparing drawing.
➢**Checking levels of different rolls and preparing drawing.
➢**Removing oil and coolant (oil) from lubrication network.
➢**Checking distance between different couplings.
➢**Dismantling rotating machines from their prime movers.
➢**Assembled machines parts.
➢**Loading all parts of 4 hi aluminum rolling mill in container.


Company Dassnagar Precision Engg. Pvt. Ltd
Designation Mechanical Supervisor
Job Period 1 Aug. 2004 to 10 Sep. 2004.
Job Responsibilities
➢**Estimating total length of the pipe according to network drawing.
➢**Hydraulic drawings reading.
➢**Fabrication of hydraulic lines.
➢**Errection of hydraulic lines.Commissioning of the hydraulic network.

Company Ispat Metallic India Ltd (Technological engineering contractor)
Designation Mechanical Supervisor
Job Period 25 May 2004 to 28 July. 2004.
Job Responsibilities
➢**Sorting Material according to construction drawing.
➢**Preparing bill of material according to drawing.
➢**Fabricate items following drawing.
➢**Preparing templates for similar items.
➢**Inspection of items fitted by fitters according drawing.
➢**Preparation for mobilizing fabricated items from yard to sight.
➢**Erection of fabricated items according to erection drawing.

Company Ispat Metallic India Ltd
Designation Mechanical Maintenance Technician
Job Period Jan. 8 2002 to 24 May 2004.
Job Responsibilities
➢**Hydraulic Piping leakage removing; fabricating new pipeline network according layout diagram.
➢**Coolant system back flushing.
➢**Heat exchange replacement. (tube exchanger, plate exchanger)
➢**Hydraulic pump (Gear pump) disassembly, assembly, alignments, test run.
➢**Hydraulic valves refurbishment installation &it's hydraulic testing.
➢**Hydraulic oil refurbishments by oil purifier.
➢**Hydraulic hose connection.

Job role:
Maintenance, Repair, and Technician

Education

National integrated institute of management and engineering

January 2013

January 2013

Bachelor's degree, Mechanical Engineering

India

GPA (percentage): 70%

GPA (percentage): 70%

Mechanical engineering

Delhi College of Engineering

January 2013

January 2013

Bachelor's degree, Mechanical Engineering

India

GPA (percentage): 70%

GPA (percentage): 70%

Mechanical engineering degree

Govt. Polytechnic College

January 2000

January 2000

Bachelor's degree, Mechanical Engineering

India

GPA (percentage): 52%

GPA (percentage): 52%

Educational Qualification: ➢**Completed Diploma in Mechanical Engineering from Govt. Polytechnic College, Pen, Mumbai University in the year 1999-2000.

Private High School & Jr. College

January 1997

January 1997

High school or equivalent, Physics And Technical Science

India

GPA (percentage): 47%

GPA (percentage): 47%

➢**Completed H.S.C. (Science) from Private High School & Jr. College, Pen, Mumbai Board with Second Class in the year 1996-1997.

Skills

Construction & Property

Expert

Turnarounds

Expert

Start up Operations

Expert

Plant Commissioning

Expert

Pre Commissioning

Expert

BOILER

Expert

ENGINEER

Expert

FITTER

Expert

LNG

Expert

MAINTENANCE

Expert

MECHANICAL TECHNICIAN

Expert

Air Blowing, Steam Blowing,Chemical Cleaning,Water flushing,Lube Oil Flushing

Expert

Nitrogen Blanketing, Flushing,Inerting,Blowing

Expert

Mechanical Run Test, Final Box-up

Expert

Construction & Property

Expert

Turnarounds

Expert

Start up Operations

Expert

Plant Commissioning

Expert

Pre Commissioning

Expert

Languages

Marathi

Expert

English

Expert

Training and Certifications

Training
Safety
OSHA
Jun 2009

Hobbies and interests

Exploring

Meet new technologies experience