Project Controls and Scheduling Supervisor
Parsons Brinckerhoff
Total years of experience :23 years, 4 Months
Almost $ 4 Billion dollars program to replace existing Tappan Zee Bridge. It is the longest bridge in the State of New York. The total length of the bridge and approaches is 16, 013 feet (4, 881 m). Responsibility entails managing the Integrated Project Master Schedule, assist the Design-Builder (D-B) to develop D-B’s WBS, review D-B’s 90-day schedule, BL schedule and Updates and report to the NYSTA.
Project Controls Engineer for 63rd Street Station reconstruction project
Project controls engineer