panel operator & supervisor backup
PetroRabigh
مجموع سنوات الخبرة :11 years, 5 أشهر
1. As senior field operator in PETRORabigh refinery in rabigh city Saudi Arabia from 4/2008 up to 3/2010, we did precommissioning, commissioning and initial start up to V.D.U vacuum distillation unit.
2. Consol operator familiar with YOKOGAWA system & superviser backup in PETRORabigh refinery in V.D.U.
*Experience in Detail
1. Saudi Aramco- jv with Sumitomo corporation- Petro Rabigh refinery: (Vacuum Distillation Unit)
* The plant is designed to operate at a feed rate of 1435 BPSD of AR atmospheric residue to V.G.O, L.V.G.O & VR vacuum residue.
* Technology: UOP.
1. As junior field operator for two years after that senior operator in Midor refinery in Alexandria city Egypt from 1/2004 to 5/2008 five years - four years and half in S.R.U sulfur recovery unit with T.G.T tail gas treatment system, A.R.U amine regeneration unit, SWS.U sour water treatment unit, spent caustic treatment unit and six months in D.H.T diesel hydro treating unit.
2. Consol operator trainee with FOXBORO system from 5/2007 up to 11/2007.
*Midor refinery Alexandria:
* S.R.U Sulfur recovery unit with T.G.T tail gas treatment system the plant is two trains designed to operate at a feed rate of 8000 m3/hr of acid gas & SWS gas each train.
* A.R.U Amine regeneration unit.
* SWS.U Sour water treatment unit.
* Spent caustic treatment)
Bsc. Of physical education - Helwan university 2001.