General Surveyor
Salini saudia arabia
مجموع سنوات الخبرة :14 years, 7 أشهر
Preparing Survey Data for Surveyor .
Preparing RFI, s(Request for Inspection) For Consultant .
Checking the Survey Data from Subcontractors and then Submit To Consultant
Preparing the as-built Drawing.
Erection of segments installation with launching grader (Used Total station with stakeout coordinates) and also alignments after the complete span epoxy.
Erection of BCM segments (Used Total station with stakeout coordinates) and also alignments with Reference line after the every couple of segments erection.
Precast yard work with precast bolt and checked the alignments and elevation as per draying with digital level and submits all the day progress and as built end of day
Alignments of Colum’s PT Bars and also alignments with Elevation of bearings installation.
Launching Grader assembling load test with manual Elevations and coordinates .
Work of landscaping at line 06 line 05 and line 04.
Make a traverse line open and closed traverse
Topographic survey of Train Station
Topographic
Establish the bench mark with high accuracy.
Layout the centre line.
Prepare the cross section of road.
Layout the Retaining walls and breast walls.
Layout the culvert and causeways.
Work on structure
Sub base course and asphalt
in
courses: SURVEYING INSTRUMENTS •GPS ( Sokkia GRX,TrimbleR6, Leica Icon GPS 60) •Total Station ( Leica,Topcon,Sokkia,Trimble,Nikon,Rude,Gowin) •Digital Level •Auto Level METRIC . Board of intermediate and Secondary Education abbottabod