فيناي لوكيش, Planning Engineer

فيناي لوكيش

Planning Engineer

Yashaswi Engineering Consultant Pvt. Ltd.

البلد
الهند
التعليم
بكالوريوس, Civil Engineering
الخبرات
12 years, 2 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :12 years, 2 أشهر

Planning Engineer في Yashaswi Engineering Consultant Pvt. Ltd.
  • الهند - Tumkur
  • أشغل هذه الوظيفة منذ فبراير 2021

• Project planning, baseline scheduling, monitoring, tracking, and reporting activities. Analyses and reports project economics including costs, operational budgets, staffing requirements, resources, and risk
• Prepare the project-wide master program reflecting the project phasing and packaging strategy and including engineering procurement construction handing over the project
• Track the delivery of long-lead materials into stage-wise requirements at the site, highlighting the priority of materials to the Project Manager, as per the agreed schedule
• Establish the delay analysis by capturing the delay analysis, notification and EOT claim accurately in line with the project requirements
• Prepare the Look-ahead schedules, KPI tracker, and progress updates based on the QC approval
• Setup presentation of the Progress updates, including Schematic layout illustration
• Collate and analyse reports from the site team to ensure that delays, stoppages, constraints, and deviations are being recorded in line with the project requirements
• Monitor and analyze Earned Value and associated Key Performance Indicator

Production Planning Engineer في Energy Technical Services WLL
  • قطر - الدوحة
  • أكتوبر 2019 إلى ديسمبر 2020

• Project planning, baseline scheduling, monitoring, tracking, and reporting activities. Analyses and reports project economics including costs, operational budgets, staffing requirements, resources, and risk
• Prepare the project-wide master program reflecting the project phasing and packaging strategy and including engineering procurement construction handing over the project
• Track the delivery of long-lead materials into stage-wise requirements at the site, highlighting the priority of materials to the Project Manager, as per the agreed schedule
• Establish the delay analysis by capturing the delay analysis, notification and EOT claim accurately in line with the project requirements
• Prepare the Look-ahead schedules, KPI tracker, and the progress updates based on the QC approval
• Setup presentation of the Progress updates, including Schematic layout illustration
• Collate and analyse reports from the site team to ensure that delays, stoppages, constraints, and deviations are being recorded in line with the project requirements
• Monitor and analyse Earned Value and associated Key Performance Indicator

Production Planning Engineer في BCIM Engineering Pvt. Ltd.
  • الهند - Tumkur
  • يناير 2018 إلى ديسمبر 2019

• Track and monitor major equipment
• Participate in project meetings and discussions with the clients as required
• Assists in preparing work program, cash flow, manpower histogram, S- Curve
• Manpower and equipment deployment chart
• Develop variance analysis and responsibility float consumption
• Reflect change order scope on schedule and perform variance analysis
• Link and modify linkages of proper sequence in planning software
• Track and monitor project manpower levels to include direct, indirect, support, and idle
• Assign cost components and cost types to create graphs to illustrate actual performance and project status
• Package the project into the scope of work
• Develop levels1 to 7 of the schedules
• Prepare weekly/monthly look-ahead plan, progress schedule, recovery plan, and accelerate plans

Production Planning Engineer في Al Khalili Construction LLC
  • عمان - مسقط
  • مايو 2017 إلى ديسمبر 2017

• Preparing the master program reflecting the project phasing and packaging strategy and including procurement, construction, commissioning, and handing over
• Update the program (baseline vs. updates), including cost and resource loading
• Demonstrable track record in the delivery of large multidisciplinary projects.
• Monitor construction progress and analyze earned value
• Prepare weekly and monthly reports and report to the project control manager any deficiency or non-compliance
• Attend weekly progress meetings and monthly meetings and participate in preparing the agenda
• Review and assess time aspects for extension of time claims
• Report weekly/monthly progress along with delays/slippages and provide resolution
• Monitor the status of all purchases and invoicing and delivery up to the closure of the project

Planning Engineer في Yashaswi Engineering Consultant Pvt. Ltd.
  • الهند - Tumkur
  • مايو 2014 إلى مايو 2017

• Prepared a detailed program of works in accordance with contract key dates
• Developed work breakdown structure and defined work packages and coding of the scheduled activity
• Identified and managed all interface, milestones, and major activities, the relationship between activities, and created budget estimates
• Coordinated in preparation of drawing submission schedule and followed up the delivery material as per the schedule

Site Engineer في M/s Karnataka Test House Pvt. Ltd.
  • الهند - Chitradurga
  • يناير 2013 إلى مايو 2014

• Collected the soil samples from the project intended site using bores and test pits
• Conducted laboratory testing performed as per the relevant part of IS 2720
• Performed geotechnical analysis and study to assess construction sites based on substructure conditions revealed from field investigation

Site Planning في M/s Larsen and Turbo Ltd.
  • الهند - Tumkur
  • فبراير 2012 إلى ديسمبر 2012

• Worked as a Site Engineer for a service provider of water and sewage projects- UGD construction works, municipal
• Managed supervision of civil works which involve excavation of trenches for laying water pipes, construction of break pressure tanks

الخلفية التعليمية

بكالوريوس, Civil Engineering
  • في Belgam
  • يوليو 2012

B.E. (Civil Engineering) Sir MVIT College (Bangalore), VTU (Belgaum University), Karnataka

الثانوية العامة أو ما يعادلها, kannada, hindi
  • في University Of Florence
  • يناير 2010

A grade

دبلوم, PCMB
  • في SCHRADRI PURAM
  • يناير 2004

80 %

Specialties & Skills

AutoCAD 2D
microsoft project
Primavera P6
Schedule Planning
Planning Engineer
Microsoft Project (MSP)
AutoCAD
E Survey Softest
Oracle Primavera P6- PPM & EPPM
MS Office

اللغات

الانجليزية
متمرّس
الهندية
متمرّس
الكانادا
متمرّس
العربية
مبتدئ

العضويات

ETS WLL
  • PLANNING ENGINEER
  • November 2019

التدريب و الشهادات

5.E SURVEYING Certification of Appreciation (الشهادة)
4.E SURVEYING Certificate (الشهادة)
3.National Employable Skill Certificate (الشهادة)
2.Auto Cad Certificate (الشهادة)
1.Master Diploma in Project Planning and Management certificate (الشهادة)

الهوايات

  • Singing
    OK
  • REEDING
    SOMETIME
  • Dancing
    GOOD