GM
UT pvt ltd
Total years of experience :43 years, 10 Months
General arrangement OF construction cycle of project, team building, sub contractors engagement their prgress verification finalizing claims, claim settlement with client,
drawing verification submission to client approval before execution, man machinery deployment for its optimum use etc
all water supply industry related infrastructure activities as intake structure, sump wells WTP, pump houses, water reservoir over head & ground, cross country pipe line, distribution system. SCADA base automation etc operation & maintenance of supply system
office admn. tendering, estimating, DPR, meeting with administration, vendors, sub contractors, worker union, public representative & other public deputations
ETP. STP, sewer lines CI & DI. chamber etc
irrigation structure like head weir, canal. aqueduct, siphon etc
flood control structure
installation of fire fighting system like water tanks. gi pipe line, fire hydrants etc
Tehri dam tunnel, horse shoe shape, drill & bore, quantity take off, sub contractors bills ete.
Sardar Sarovar Dam Bharuch Gujrat concrete gravity dam main site, quantity survey, petty contractor bills, client meeting
NALCO admistrative building, security& auditorium construction etc,
meeting with vendors, sub contractors & client
RCF Mumbai plant Alibag ETP, Onshore & off shore pipe line from etp,
other building costruction, sun conteacrors billing & meeting
civil engineering