ربيح رعد, Project Manager

ربيح رعد

Project Manager

SEG

البلد
ساحل العاج
التعليم
دبلوم, Civil Engineering
الخبرات
13 years, 9 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :13 years, 9 أشهر

Project Manager في SEG
  • ساحل العاج
  • أشغل هذه الوظيفة منذ يناير 2017

Project manager for Construction of 2 high standing commercial residential buildings located at the VGE road with total build up of 16, 000 m2,

Following up the progress with site manager in accordance with the schedule

Regular follow up meeting with consultant, designer and client

Ordering and following up the local and imported materials

Checking the sub-contractors contracts, their site activities and preparing their invoices

Preparing the monthly invoice and variation orders
Checking the quantities prepared by QS department

Dealing with newly imported exterior cladding tile (FRONTEK)

Reviewing the Design Drawings and shop drawings prepared by the Sub-Contractors

Civil Engineer في ARCON Company
  • المملكة العربية السعودية - الخبر
  • مايو 2012 إلى ديسمبر 2016

Project: « Replace of Administration building for Juaymah Gas Plant», Started on 2014

Tasks:

- Working as Site Manager for the construction of the building with total build up area of 10, 000 m^2 with Asphalt Pavement for building Parking and installation of 1.5 Km MV cable, Instrument and telecom cables from admin building to the plant

- Ensure the daily construction in accordance to the plan and the schedule

- Identify site problems and solve the in coordination

- Ensure the team is fully complied with SAUDI ARAMCO standards for Safety and Quality

- Follow up submittals and request ahead materials and assets for site

Project: « Al Nawras village-East Damam Housing Construction »
Tasks:
- Construction of 228 Villas divided into 7 types

- Dealing with new Slab formworks called TABLA Panels

- Working with ARAMCO specifications for safety and quality

Project Engineer في CCE
  • المملكة العربية السعودية - الجبيل
  • أغسطس 2010 إلى أبريل 2012

CCE, Jubail, Saudi Arabia
Project: « Jubail Export Refinery »
Tasks: - Working as civil engineer, Subcontractor of Technip, main contractor of Satorp
(Saudi Aramco/TOTAL)
- 2 Water tight basins: 30m x 20m x 7m (height) each.
- 12 Foundations for Pumps connected to basins and cooling towers.
- 2Km length Pipe rack's foundations.
- Underground works: Manholes, Pits, Duct Ban Trenches, and Ditches.
- Heavy Equipment foundations.
- Various Foundations for flare 175m length.
- Dealing with SATORP approved materials.
- Attending various SATORP safety training.

الخلفية التعليمية

دبلوم, Civil Engineering
  • في Lebanese University
  • يناير 2010

Faculty of Engineering, Branch 1, Tripoli, Lebanon

Specialties & Skills

Refinery
Refining
AUTOCAD
CABLING
ENGINEERING
MATERIALS MANAGEMENT
MICROSOFT OFFICE
MICROSOFT WORKS
QUALITY
SUPERVISORY SKILLS
TELECOMMUNICATIONS

اللغات

العربية
متمرّس
الانجليزية
متمرّس
الفرنسية
متمرّس