Rico Perdana Putra, Senior Piping Engineer

Rico Perdana Putra

Senior Piping Engineer

Tripatra

Location
Indonesia - Jakarta
Education
Bachelor's degree, Mechanical Engineering
Experience
10 years, 3 Months

Share My Profile

Block User


Work Experience

Total years of experience :10 years, 3 Months

Senior Piping Engineer at Tripatra
  • Indonesia - South Tangerang
  • My current job since November 2023

• Prepare and Review Piping Documentation such as Specifications, Datasheets, Requisition, and Technical Bid Evaluation.
• Prepare and Review Critical line list and marked up P&ID for Critical line.
• Review Pipe Support Standard.
• Prepare FIV and AIV study and assesment.
• Prepare and Review Valve List and Piping Special Item List.

Handled Project:
• Pertamina EP - EPC Pembangunan SP ABG Stage 1 di Lapangan Asia Bagus
• Pupuk Kaltim - EPC for Revamp Ammonia Plant-2 Project

Piping Design Engineer (Stress & Layout) at Technip Energies
  • Indonesia - Jakarta
  • February 2023 to November 2023

• Perform piping stress analysis of critical and complex on wellhead piping systems, drain and vent system and onshore pipeline in accordance with ASME B31.3 and B31.8 code.
• Prepare Critical line list and marked up P&ID.
• Prepare piping documentation such as Specification for Pipe Stress Analysis and Specification for Piping Support Design.
• Assist piping designer to finalize pipe routings and pipe support position.

Handled Project:
• British Petroleum - FEED stage of Ubadari, EGR/CCUS, And Onshore Compression (UCC) Project

Piping Stress & Support Engineer at Saipem
  • Indonesia - Jakarta
  • April 2022 to February 2023

● Perform piping stress analysis of critical and complex piping systems in accordance with ASME B31.3, B31.8 and DNV code.
● Compile, review and develop work package of piping stress analysis activities in accordance with the work instruction and associated standards and procedures on topside piping (wellhead and process), bridge piping, flare piping, etc.
● Prepare pipe support loadings to conclude appropriate piping support design.
● Prepare pipe support loading data to other discipline in project team including structure and mechanical.
● Perform evaluation of nozzle loads in equipment including tanks, vessel, pumps according to various standards.
● Perform flange leakage check using NC-3658.3 Method, ASME Sec. VIII, and API 6A flanges.
● Review and perform pipe isometric checking to maintain consistency between calculation, project standard, recommended practice are implemented in piping support selection and design.

Handled Projects
● Qatargas - Engineering Procurement and Construction Offshore & Looping of North Field Production Sustainability (NFPS EPCOL) Project

Piping Engineer at Meindo Elang Indah
  • Indonesia - Jakarta
  • August 2019 to August 2021

● Prepare piping documentation such as piping material specification, manual valve datasheet, piping special item datasheets, spring support datasheet, pipe support standard, hook-up standard, special item lists, tie-in lists, piping material requisition, piping bulk material take off and manual valve material take off.
● Prepare technical bid evaluation of manual valve, piping special items, and spring support.
● Review vendor documents for piping material (manual valves, special items, spring support, piping bulk material).
● Review piping design, equipment plot plan, piping general arrangement, and isometric drawing.
● Prepare piping wall thickness calculation.
● Prepare piping stress specification, marked up P&ID for critical line and critical line list.
● Perform piping stress analysis of critical piping systems in accordance with ASME B31.3 and ASME B31.8 code requirements.
● Prepare piping support loading data for structure implementation.
● Prepare estimated manhour for piping scope of work and estimated material take off during upcoming project bid or proposal stage.

Handled Projects
● Pertamina Hulu Mahakam (Formerly Total E&P Indonesie) - Jumelai Sisi Nubi Project
● Petronas Carigali Ketapang II Ltd. - Bukit Tua Fase 2B Project
● Pertamina Hulu Energi Onshore West North Java - KLD Field Development Project

Piping Engineer at Royal HaskoningDHV
  • Indonesia - Jakarta
  • October 2017 to August 2019

● Prepare piping documentation such as manual valve datasheet, piping special item datasheets, piping support standard, hook-up standard, line lists, piping special item lists, tie in lists, piping bulk material take off and manual valve material take off.
● Prepare piping wall thickness calculation.
● Perform flexibility analysis of steam pipe, jacketed pipe and other critical line.
● Prepare piping support loading data for structure implementation.
● Review piping design, equipment plot plan, piping general arrangement and isometric drawing.
● Review P&ID regarding incomplete and/or consistency information like line numbers, tag numbers, flow directions, instrument details, equipment details, Continuation P&ID etc.

Handled Projects
● Indika Energy & ExxonMobil Lubricants Indonesia - Emily-2 Project Fuel Terminal and Jetty Lamongan
● Indika Energy & ExxonMobil Lubricants Indonesia - Emily-1 Project Fuel Terminal and Jetty Balikpapan
● Cargill - Lotus Project (Starch and Sweeteners Production Plant)
● EcoOils Sdn. Bhd. - Hijau Lestari Project Dumai Plant (Vegetable Oil Recovery & Residual Clay Processing Facility)
● Barry Callebaut Services Asia Pacific - Barry Callebaut Rancaekek Plant Development
● Adaro MetCoal - Maruwai Coal Port Expansion Project
● EcoOils Sdn. Bhd. - Hijau Lestari Project Gresik Plant (Vegetable Oil Recovery & Residual Clay Processing Facility)

Piping Mechanical Engineer at Euroasiatic
  • Indonesia - Jakarta
  • December 2016 to October 2017

● Review P&ID and prepare pipe wall thickness calculation for service line and utility line.
● Review pipe route and layout for piping installation.
● Prepare and check fabrication drawing for piping, tank, pressure vessel and package.
● Prepare material take-off piping bulk and manual valves.

Handled Projects
● HM. Sampoerna Sukorejo Plant - Gas Engine Generator 4 MW Complete With Boiler and Chiller Project
● HM. Sampoerna Karawang Plant - Gas Engine Generator 4 MW Complete With Boiler and Chiller Project

Pipe Stress Engineer at Daewoo Shipbuilding and Marine Engineering Ltd.
  • Indonesia - Jakarta
  • May 2013 to September 2016

● Compile, review and develop pipe stress analysis of critical piping systems in accordance with ASME B31.3
● Prepare isometric drawing and pipe support loading data.
● Review piping design and pipe support design according to stress calculation result.
● Review subcontractor piping stress calculation package.
● Check and review markedup P&ID for stress analysis, line lists and critical line lists.

Handled Projects
● BW Offshore - 173, 400 M3 LNG Carrier Project
● Chandris (Hellas) Inc. - 173, 400 M3 LNG Carrier Project
● SEA-Tankers Shipping S.A - 173, 400 M3 LNG Carrier Project
● Mariner Project - Statoil ASA
● INPEX Operations Australia Pty. Ltd. - Ichthys Venturer FPSO Topside Project

Education

Bachelor's degree, Mechanical Engineering
  • at Institut Teknologi Bandung
  • April 2013

Bachelor of Science in Mechanical Engineering from Institut Teknologi Bandung (ITB), Bandung, Indonesia Final Project Thesis : Re-Design and Piping Stress Analysis on Storage Tanks Crude Palm Oil 3000 Metric Tons by Using Software Coade Caesar II

Specialties & Skills

Flexibility
Plant Layout
Basic Materials
CAESAR II
Stress Analysis
PDMS review
Caesar II
Microsoft Office
Naviswork Review
Engineering, Procurement and Construction
Teamwork

Languages

English
Expert
Indonesian
Native Speaker

Memberships

The Institution of Engineers Indonesia
  • Member
  • January 2022

Training and Certifications

PV Elite (Certificate)
Date Attended:
August 2016
Caesar (Certificate)
Date Attended:
April 2014
Aveva Marine (Certificate)
Date Attended:
August 2013

Hobbies

  • Watching Movies
  • Jogging
    Several 10K finisher Medals