Responsible for all variation orders and potential change notices to Client.
Review tender documents and changes made by IFC drawings and RFI’s
Review Engineer’s Instruction.
Assign task to subordinates for the preparation of potential change notice (PCN) and variations order request (VOR).
Review/finalize PCNs & VORs prior to sending to client.
Attend client joint assessment and consolidate final value of variations.
Participate in commercial meetings.
Prepare commercial correspondence.
Prepare financial and cost report.
Maintain logs.
Review variation for subcontractors and recommend approval.
Part take in preparation of interim payment certificates.
Sr. Quantity Surveyor
Aug. 2008 ~ August 2012
Employer: Canadian Project Managers (Project Management)
Client: Al Saqer Property Management
Project/Location: Abu Dhabi, U.A.E.
The project involves the construction of a 5 towers (14 level each, 1 Hotel, 1 Serviced Apartment, 1 Office Building & 2 Unfurnished Apartments) including Retail and 5 level Basement/Parking.
Project Worth: AED 2.5Billion (UAE Dirham)
Main Consultant/Engineer: Cox Group (Design and Supervision), Cost Consultants: Page Kirkland Group (PKG) and Blair Anderson
Main Contractor - Habtoor Leighton Group
Other Client's Direct Contracts: 30 independent contractors with 40 different contracts.
• Report directly to the Project Manager.
• Reviews Tender Documents for Client direct works and invite Bidders
• Reviews Engineer's Tender Analysis, negotiate with bidders and recommend to Client
• Keep records/logs of Contract documents for commercial related references.
• Reviews Engineer's recommendation on Contractors interim payment certificates and further certify/recommend to Client for approval and payment. Maintain payments log.
• Review Engineer's assessment on cost variations and certify/recommend to Client for approval. Maintain Variation Order log.
• Review Engineer's proposed Work Instructions (WI) on the related cost impact for Client approval prior to issuing the WI to Contractors. Maintain WI log.
• Review and assess Consultant's payment application, prepare payment certificate and recommend to Client for payment.
• Review and assess Consultant's claims on variation and recommend to Client for approval.
• Maintain a monthly updated project overall budget and expenditures. Prepare monthly cost report to be included in the overall project periodical report.
• Attend commercial meetings. Prepare commercial correspondence.
• Prepares final account of finished contracts.
• Communicates effectively with clients, as and when required.
Quantity Surveyor
Feb. 2007 ~ Aug. 2008
Employer: QP International, Project Management
Project/Location: Sas Al Nakhl Commercial Development Phase II/ Abu Dhabi, U.A.E.
The project involves the construction of a 484 number of villas which includes: Club House, Mosque, Supermarket and Staff Accommodations.
Project Worth: AED 500Million (UAE Dirham)
• Report directly to the Project Manager
• Review and check works in accordance with Contract Documents.
• Reviews and approve Contractor's payment
• Reviews and approve Consultant's payments.
• Reviews and approve Variation Orders.
• Reviews of Budget and Cost Control Report as per Owner's requirement.
• Conducts Cost meetings.
• Prepares monthly cost report.
• Prepares final account.
• Maintain updated logs of payments, VO's and Work Instructions.
Quantity Surveyor
Sept. 2004 ~ Jan. 2007
Employer: Arabtec Construction LLc (General Contractor)
Project/Location: Jumeirah Beach Residence (JBR) /Dubai, U.A.E.
The project involves the construction of a 13 number towers in two sectors JBR 1 and JBR 3 (6 and 7 number towers respectively ranging from 27 to 45 floor levels) These towers are interconnected through the formation of a podium structure containing 3 levels of car parking and 2 levels of retail and auxiliary function space.
• Prepares documentation like take-off quantities, Bills of Quantities as per Specification.
• Prepares estimates for varied works.
• Prime Cost and Provisional sum settlement.
• Prepares payment application.
• Evaluates Subcontractors payment application.
• Assess Subcontractors Cost Variations.
Quantity Surveyor (Engineer/Consultant)
August 2003 ~August 2004
Project Consultant - in association with De Leuw, Cather International, Katahira & Engineers International, Tonichi Engineering Consultants Inc., Sir William Halcrow & Partners Ltd., Proconsult Engineers Co., DCCD Engineering Corporation and Schema Konsult, Inc.
Employer: Light Rail Transit Authority (LRTA) thru DEMCOR Engineering Consultant
Project/Location: Metro Manila Strategic Mass Transit Development (Line 2) Project / Metro Manila, Philippines
The project involves the construction of a 13.8 kilometer elevated light rail train line having eleven passenger stations (10 elevated and 1 underground station on 1.2km tunnel) and 1 Depot with support facilities.
• Review and check works in accordance with Contract Documents.
• Prepares Contract Documents - Addenda and Direct Cost Control for Site Work.
• Reviews and recommend Contractor's payment.
• Reviews and recommend Variation Orders.
• Prepares and issue Job Site Instructions (JSIs) and estimation of Site Work Instructions.
• Checks work progress for payment purpose.
• Reviews, Prepares and recommend Variation Orders
• Reviews of Budget and Cost Control Report as per Owner's requirements
Quantity Surveyor
July 2000 ~ Mar 2003
Emplore: RSEA Engineering Corporation
Project/Location: Cable-Stay Bridge and Highways / Tempisque, Guanacaste, Costa Rica, Central America
The project involves the construction of 100 km highway and 870 meters bridge in a steel box girder construction suspended by pre -stressed cables attached to the H-shaped Pylon's head. The pylon rests on caissons on bored pile foundation.
• Prepares estimates for varied works.
• Prepares payment application.
• Evaluates and prepares Subcontractors payment application.
• Assess Subcontractors Cost Variations
• Prepares monthly cost report.
Quantity Surveyor
Dec 1999 ~ Jun 2000
Employer: AVIA Construction and Development Corporation
Project/Location: La Insula Residential Condominium Project / Panay Ave. Quezon City, Philippines -
The project involve the construction of a high rise "state of the arts" residential tower for JV Williams Realty & Development Corporation, Inc.
Project Quantity Surveyor
1992 ~ 1999
Employer: Asian Construction and Development Corporation (ASIAKONSTRUKT)
Project/Location/Description:
• GLOBETEL BACKBONE Project / Bacolod and Iloilo sites, Negros Occidental and Panay island, Philippines. - The project involves the construction of self-supporting Antenna Towers and foundations; Tower erections and Solar panel foundations for solar energy. Owner: Global Telecommunications Inc. (GLOBETEL), Philippines
• Regional Telecommunications Development Program Phase-C (RTDP-C) / Region I & II, Philippines.
• National Telephone Program (NTP Phase I-1) / Regions III, IV, V & NCR, Philippines - The project involves the construction of Support Facilities (Exchange buildings, relay stations, access roads and Antenna towers and foundations) for the Department of Transportation and Communications (DOTC) telecommunications project, Philippines
References can be provided upon request.
3 years in Costa Rica, Central America 8 years in United Arab Emirates (U.A.E.) Bachelors Degree in Civil Engineering Registered Civil Engineer (License No. 57770) Associations/Trainings: Association for the Advancement of Cost Engineers International (AACEI) Philippine Institute of Civil Engineers (PICE), Manila Philippines Chapter Overseas Filipino Civil Engineers' Association (OFCEA), Dubai UAE Chapter Certification for Cost Engineers (CCE)