Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


User unblocked successfully
Saad Dalibalta, Director

Saad Dalibalta

Director·Bahra International for Contracting & Construction.

Kuwait

Higher diploma, Project Management Professional PMP

Work experience

Total years of experience: 35 years, 2 months

Director

September 2023 - Present

Bahra International for Contracting & Construction.

Al Ahmadi, Kuwait

September 2023 - Present

Company industry:
Construction & Building
Job role:
Management

Projects Director

July 2021 - September 2023

K- LAMOR

Al Ahmadi, Kuwait

July 2021 - September 2023

Corporation. Client: Kuwait Oil Company (KOC)
PMC : WORLEY
PROJECT: ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION.
EXCAVATION, TRANSPORTATION AND REMEDIATION FOR (SKETR) PROJECT (ZONE-1) & (NKETR) PROJECT (ZONE1).

Company industry:
Oil & Gas

Project Manager

November 2017 - March 2020

Al-Ghanim International General Trading & Contracting Co.W.L.L.

Al Ahmadi, Kuwait

November 2017 - March 2020

CLIENT: Kuwait Oil Company (KOC) PMC : FLOUR PROJECT: KOC NRP Feed Pipelines for New Refinery Project from Ahmadi to Al Zour (450 KM of pipe lines)

Company industry:
Construction & Building
Job role:
Construction and Building

Project manager

March 2014 - September 2016

ALGHANIM INTERNATIONAL GENERAL TRADING AND CONTRACTING W.L.L. Kuwai

Al Ahmadi, Kuwait

March 2014 - September 2016

for two projects (New Underground 20 From Wafra To Mina Saud & Excavation &
Transportation of heavily oil contaminated soil to landfill in north Kuwait

Company industry:
Construction & Building
Job role:
Management

Construction Manager

July 2011 - March 2014

CCC

Al Ahmadi, Kuwait

July 2011 - March 2014

Scope of Works
• Covers Design, Engineering, Procurement, Supply, installation, testing, pre-commissioning and
commissioning of Pipelines with pigging facilities as listed below:
- 60 km service road.
- Infrastructure for access road and buildings.
- Control buildings.
- Control valve pits.
• 60 Km of 24” Gas Export Line from BS-171 to AGRP at MAA.
• 60 Km of 14” Condensate Export Line from BS-171 to AGRP at MAA
• 15 Km of 8” Pigging Liquids Disposal Line from AGRP at MAA to New Intermediate Sludge catcher 19 -
near GC.
• Tie-in of the above pipeline with existing pipelines.
• 500 M of 8” pipeline (jump over) from liquid condensate pipeline of GC-28 up to the new trap
location.
• 500 M of 18” pipeline (jump over) from gas export pipeline of GC-28 up to the new t rap

Company industry:
Construction & Building
Job role:
Engineering

Senior Construction Manager

July 2011 - March 2014

CCC

Al Ahmadi, Kuwait

July 2011 - March 2014

for all civil works
Project: KOC PL from BS 171 to AGRP at MAA facilities.
Client: Kuwait Oil Company (KOC)

Company industry:
Construction & Building
Job role:
Management

Senior Construction Manager

July 2011 - March 2014

CCC

Al Ahmadi, Kuwait

July 2011 - March 2014

Project: KOC Gas Pipe Lines from BS 171 to AGRP at MAA facilities. Client: Kuwait Oil Company (KOC)

Company industry:
Construction & Building
Job role:
Construction and Building

Senior Construction Manager

July 2011 - March 2014

CCC

Al Ahmadi, Kuwait

July 2011 - March 2014

Project: KOC Gas Pipe Lines from BS 171 to AGRP at MAA facilities. Client: Kuwait Oil Company (KOC)

Company industry:
Construction & Building

Project Engineer

December 2010 - July 2011

CCC

Riyadh, Saudi Arabia

December 2010 - July 2011

Scope of Works
Princess Noura Bint Abdelrahman University For Women Project. Comprises the package to provide
Infrastructure & Utility Plant for the new University. The project includes 4 million m3 excavation, 5.5 million
m3 fill, 6km tunnel, concrete 425, 600m3, 16 Utility building of area 227, 500m2, Paving (interlocking and
stone) 924, 000m2, Road works (asphalt) 1, 100, 000m2, Soft landscaping 1, 500, 000m2, extensive
underground services distribution. Major road and pedestrian bridges and underpass / roundabouts.
Duties
• Supervise all civil works in the Faculty Sport Area, including all kind of foundations, roads,
infrastructure, underground piping, 2 Mosques, 9 play grounds one main admin building, soft and
hard landscaping, tiles work and final paving.
• Assigns duties to section Engineers, Surveyors and Foremen on site, and ensures execution of work
according to specifications and craft standards. Specifies working methods and interprets
specifications and formal drawings. Also, ensures local and overseas material requisition for the
project.

Company industry:
Construction & Building
Job role:
Engineering

Area Estimation

June 2010 - December 2010

CCC

Al Ahmadi, Kuwait

June 2010 - December 2010

Provide technical support for Estimation, Procurement and Construction activities.
3. Position: Project Manager
Project: MRSP 178.
Owner:

Company industry:
Construction & Building
Job role:
Secretarial

Consultants

July 2009 - June 2010

CCC

Al Ahmadi, Kuwait

July 2009 - June 2010

Scope of Works
Includes: Maintenance of Roads, infrastructures, parking and Public Utilities of Hawali,

Company industry:
Construction & Building
Job role:
Information Technology

Senior Project Engineer

March 2009 - July 2009

CCC

Al Ahmadi, Kuwait

March 2009 - July 2009

Scope of Works
The project consists of the construction of the new flour silo, new temper bin silo and kilo-packer silo for
Kuwait flour mills and Backeries Company:
• New Flour Silo
Size = 29.61 X 24.25 M, Height Approximately = 45 M
• New Kilo Packer Silo
Size = 25.4 x 24.25 M, Height Approximately = 25 M
• New Temper Vin Silo
Size = 7.4 X 6.20 M, Height Approximately = 27 M
• Total quantity of concrete = 6000 M3
• Total reinforcement steel = 1000 TON.
Duties
• Control the engineering and documents of the project.
• Coordination regarding design and correspondence between the project and main client
5.

Company industry:
Construction & Building
Job role:
Engineering

Construction Manager

March 2009 - July 2009

CCC

Al Ahmadi, Kuwait

March 2009 - July 2009

Project: Construction of New Grain and Flour Silo Complex (NGFC). Client: Kuwait Flour Mills &Bakeries Company

Company industry:
Construction & Building

Construction Manager

March 2009 - July 2009

CCC

Al Ahmadi, Kuwait

March 2009 - July 2009

Project: Construction of New Grain and Flour Silo Complex (NGFC). Client: Kuwait Flour Mills &Bakeries Company

Company industry:
Construction & Building

Senior Project Engineer

August 2006 - March 2009

CCC

Al Ahmadi, Kuwait

August 2006 - March 2009

Scope of Works
The scope includes: Earthworks, Concrete works, Buildings construction, Piping fabrication and erection
A/G & U/G,

Company industry:
Construction & Building
Job role:
Engineering

Senior Project Engineer

August 2006 - March 2009

ccc

Al Ahmadi, Kuwait

August 2006 - March 2009

Project: Equate 2 Ethylene Plant - OL2K. Main contractor: Technip Italy Consultants: Equate. Contract Value: US$ 114 Millions

Company industry:
Construction & Building

Senior Project Engineer

August 2006 - March 2009

CCC

Al Ahmadi, Kuwait

August 2006 - March 2009

Project: Equate 2 Ethylene Plant - OL2K. Main contractor: Technip Italy
Consultants: Equate. Contract Value: US$ 114 Millions

Company industry:
Construction & Building

Section Engineer

August 2004 - August 2006

ccc

Al Khiran, Kuwait

August 2004 - August 2006

Scope of Works
Construction, completion & maintenance of inner roads, public utilities, landscaping works, 11 KV
Transformer substations, communication networks & equipment as well as fiber optic lines.
Duties
• Control and supervise Road, infrastructure,

Company industry:
Construction & Building
Job role:
Engineering

Senior Project Engineer

August 2004 - August 2006

CCC

Al Khiran, Kuwait

August 2004 - August 2006

Project: Al Khiran New Town infrastructure works for Block 2, 3 & 7 Neighborhood - 1 Contract (KTIP).

Company industry:
Construction & Building

Senior Project Engineer

August 2004 - August 2006

ccc

Al Khiran, Kuwait

August 2004 - August 2006

Project: Al Khiran New Town infrastructure works for Block 2, 3 & 7 Neighborhood - 1 Contract (KTIP). Client: Council of Ministers, Divided Zone Agreements & Kuwaiti Islands & Major Projects Development Contract Value: US$ 66, 009, 422

Company industry:
Construction & Building

Construction Manager

June 2004 - August 2004

CCC

Al Ahmadi, Kuwait

June 2004 - August 2004

Scope of Works
The project involves the construction & pre-commissioning of a new booster station BS-131 & related
facilities as described below:
• New Booster (BS-131) comprises the following elements
- Two LP & one HP compressor with associated equipment.
- Gad Dehydration Package.
- Chemical Injection Package.
- Pig Launchers & Receivers.
- All Utility Systems associated with the above.
• Upgrading of the existing BS-130, Gathering Centers GC-15, GC-23, & GC-25 involves the following
improvements:
- Chemical injection Packages.
- New Fuel Gas Treatment Skid.
- Pig Launchers & Receivers.
- Tie-Ins.
• Interconnecting Pipelines as follows:
- 44 Kms. of Pipelines ranging from 8 to 42 in size.
- Approximately 5, 000 Pipeline Joints.
Duties: Control and supervise all civil work involved in the project.

Company industry:
Construction & Building
Job role:
Engineering

Project Engineer

June 2004 - August 2004

CCC

Al Jahra, Kuwait

June 2004 - August 2004

Project: NEW BS-131&INTERCONNECTING LINES WITH GCs&BS-130 (BS131). Client: Kuwait Oil Company (KOC)/ SNAMPROGETTI. Contract Value: US$ 31, 300, 000

Kingdom of Saudi Arabia

Company industry:
Construction & Building

Section Engineer

August 2002 - May 2004

CCC

Ras Tanura, Saudi Arabia

August 2002 - May 2004

Scope of Works
The project comprises the construction of the following:
• 2 Gas oil separation plants (GOSP): QATIF & ABU SAFAH (Total capacity 800 MBCD),
• 1 Water Separation Plant (WOSEP),
• Condensate Recovery Unit,
• Gas Gathering Unit,
• TEG Dehydration Unit,
• Utilities include Power Generator & heat recovery steam generator,
• Offsite facilities (including flares & pits).
Duties
Supervises precast yard, main fence work and the construction works on site such as formwork, rebar,
concreting; co-ordinates and assigns duties to site Engineers, Surveyors and Foremen on site, and ensures
execution of work according to specifications and craft standards. Specifies working methods and
interprets specifications and formal drawings. Also, ensures local and overseas material requisition for the
project.

Company industry:
Construction & Building
Job role:
Engineering

Project Engineer

August 2002 - May 2004

ccc

Qatif, Saudi Arabia

August 2002 - May 2004

Project: QATIF GOSP 1, (QGP1). Client: SNAMPROGETTI Contract Value: US $ 152.846, million

Company industry:
Construction & Building

Section Engineer

August 2001 - August 2002

CCC

Ras Tanura, Saudi Arabia

August 2001 - August 2002

Scope of Works
The Project involves the engineering, procurement, construction & pre-commissioning of the complete
process plant for gas processing facilities.
Duties
Supervises the construction works on site such as formwork, rebar, concreting; co-ordinates and assigns
duties to Junior Engineers, Surveyors and Foremen on site, and ensures execution of work according to
specifications and craft standards. Specifies working methods and interprets specifications and formal
drawings. Also, ensures local and overseas material requisition for the project.

Company industry:
Construction & Building
Job role:
Engineering

Project Engineer

August 2001 - August 2002

CCC

Khobar, Saudi Arabia

August 2001 - August 2002

Project: Haradah Gas Processing Facilities Project, (HDGP). Client: Saudi Aramco. Main EPC Contractor: JGC of Japan. Contract Value (CCC Portion): US $ 101.5 Millions.

Company industry:
Construction & Building

Section Engineer

December 2000 - August 2001

CCC

Alqasim, Saudi Arabia

December 2000 - August 2001

Scope of Works
Bulk site filling and structural / trench excavation. Concrete works of of various classes. Civil,
architectural, plumbing and electrical works for 23 buildings. Roads, asphalting and fencing.
Duties
Planned and organized the work package. Identified and proposed solutions to problems encountered,
and recorded and reported on variances. Monitored quality and usage of materials. Supervised
foundation of concrete structure, roads, building, masonry works. Excavation and back filling works in
progress and ensured compliance with drawings and specifications.
5.

Company industry:
Construction & Building
Job role:
Engineering

Section Engineer

December 2000 - August 2001

ccc

Jeddah, Saudi Arabia

December 2000 - August 2001

Project: Shoaiba Power Plant Phase II. (SPP2). Client: Bechtel Power Corporation Contract Value: US $ 61 Millions

Company industry:
Construction & Building

Section Engineer

January 1998 - December 2000

CCC

Jubail, Saudi Arabia

January 1998 - December 2000

Scope of Works
The project consists of the complete execution of the Civil Works far a 4 x 600 MW Oil Fired Turbine
Generator Power Plant comprising: Building Works, Marine Works, Roads, Fencing and 2 nos. chimneys.
7 of 9
Duties
Plan and organized the work package. Co-ordinates and assigns duties to Junior Engineers, Surveyors
and Foremen on site Identified and proposed solutions to problems encountered, and recorded and
reported on variances. Monitored quality and usage of materials. Supervised foundation of concrete
structure, roads, building, masonry works. Excavation and back filling works in progress and ensured
compliance with drawings and specifications.
6.

Company industry:
Construction & Building
Job role:
Engineering

Section Engineer

November 1996 - January 1998

CCC

Ras Tanura, Saudi Arabia

November 1996 - January 1998

RTPC).
Client:

Company industry:
Construction & Building
Job role:
Information Technology

Section Engineer

November 1996 - January 1998

ccc

Ras Tanura, Saudi Arabia

November 1996 - January 1998

Project: Ras Tanura Port Control Center Project (RTPC). Client: Saudi Aramco Contract Value: US $ 9.89 Million

Company industry:
Construction & Building

Site Engineer

July 1995 - November 1996

CCC

Ras Tanura, Saudi Arabia

July 1995 - November 1996

Project: RasTannura Refinery Upgrade, Package 3 & Package 4, (RTRU). Client: Saudi ARAMCO (BECHTEL being the main Contractor). Contract Value: US $ 73.5 Millions

Company industry:
Construction & Building

Site Engineer

July 1995 - November 1996

ccc

Ras Tanura, Saudi Arabia

July 1995 - November 1996

Project: RasTannura Refinery Upgrade, Package 3 & Package 4, (RTRU). Client: Saudi ARAMCO (BECHTEL being the main Contractor). Contract Value: US $ 73.5 Millions

Company industry:
Construction & Building

Civil Engineer

July 1994 - June 1995

CCC

Jubail, Saudi Arabia

July 1994 - June 1995

Project: Samad 2 - EthulHexanol Plant (S2EH). Client: Saudi Davy/ Al Jubail Fertilizer Co. (SAMAD) Contract Value: US $ 45.4 Millions

Company industry:
Construction & Building
Job role:
Civil Engineering

Civil Engineer

July 1994 - June 1995

CCC

Jubail, Saudi Arabia

July 1994 - June 1995

Scope of Works
Work scope includes the construction of 2-Ethyl Plant at SAMAD Fertilizer Plant (Jubail) which consists of
the following:
• Synthesis Gas Unit
• Butyraldehyde Unit
8 of 9
• 2-Ethylhexanol Unit
• Offsite Facilities and Services
• Two Compressor Houses
• Control Building
• Substation
• Analyzer House
• Mosque
Plus all electrical, HVAC and instrumentation works.
The Port Facilities Package involves the complete engineering, detailed design, procurement of
materials, construction and commissioning of the following:
• Carbon Steel Storage Tank (37m diam. X 18m high)
• 6 Stainless Steel Transfer Line, 800 m
• 12 Stainless Steel Loading Line, 3500m
• Installation of 3 no. Pumps, 1 no. 8 Loading Arm and 1 no. Drain Vessel
• Construction of an Electrical/Control Building and a

Company industry:
Construction & Building
Job role:
Security

Civil Engineer

July 1994 - June 1995

ccc

Jubail, Saudi Arabia

July 1994 - June 1995

Project: Samad 2 - EthulHexanol Plant (S2EH). Client: Saudi Davy/ Al Jubail Fertilizer Co. (SAMAD) Contract Value: US $ 45.4 Millions

Company industry:
Construction & Building

Site Engineer

June 1993 - June 1994

al rami for contracting

Saidon, Lebanon

June 1993 - June 1994

Supervised the construction of a seven storey building & a secondary school, both in Saida.
• Checking and analyzing drawings.
• Preparing sketches.
• Giving necessary guidelines to the crew.
• Ensuring availability of manpower, materials and equipment.
• Checking the work progress.
• Preparation of progress reports.

Company industry:
Construction & Building
Job role:
Civil Engineering

Site Engineer

June 1993 - June 1994

Ali Dalibalta Office

Saidon, Lebanon

June 1993 - June 1994

Company industry:
Construction & Building

Site Engineer

August 1991 - June 1993

South for Construction

Tyre, Lebanon

August 1991 - June 1993

Water Project: The project involved the establishment of a water network in ten southern villages.
Excavations, pipe laying, testing and backfilling were the main items of work.
• Rehabilitation of Darb Al-Siem School: The work involved all kinds of rehabilitation including
concrete work, plastering, tiling, painting, and all finishing works.
• Construction of a seven storey building in Bir-Hasan, Beirut: The type of contract was a turnkey job.
• Rehabilitation of the Islamic Council Building located in Beirut: The works involved all kinds of
rehabilitation and finishing works included a new extension of two floors.

Company industry:
Construction & Building
Job role:
Civil Engineering

Site Engineer

January 1990 - August 1991

Al Rami Contractors

Saidon, Lebanon

January 1990 - August 1991

9 of 9
Duties:
• Assisted in the design of two blocks in Bramieh, Saida.
- The works included excavation, concrete works, blocks work as well as finishing works,
landscaping of the site was a main issue to tackle with Zaidaniat, Magdloun (Consultant).
- The works included the establishment of a real estate zone.
- The area was 25000 m2 divided into 200 square pieces, with the necessary electrical, water and
sewer system.
- It also included the construction of gutter inlets, curbstone units on borders. Fencing of the land
was the first item of works to begin with.

Company industry:
Construction & Building
Job role:
Civil Engineering

Civil Engineer

January 1988 - January 1989

ali dalibalta office

Saidon, Lebanon

January 1988 - January 1989

Company industry:
Construction & Building
Job role:
Architecture

Junior Engineer

January 1988 - January 1989

ali dalibalta

Saidon, Lebanon

January 1988 - January 1989

Company industry:
General Engineering Consultancy

Education

Project Management Institute

September 2024

September 2024

Higher diploma, Project Management Professional PMP

United States

California town university

June 2024

June 2024

Master's degree, Management

United States

California Town University

January 2017

January 2017

Master's degree, Master's Degree in Management,

United States

California Town University

January 2017

January 2017

Master's degree, Master's Degree in Management,

United States

Beirut Arab University

January 1989

January 1989

Bachelor's degree, Bachelor of Civil Engineering,

Lebanon

Skills

Work Environment
Expert
Work Environment
Expert
Landscaping
Expert
Landscaping
Expert
Industrial Buildings
Expert
Industrial Buildings
Expert
Infrastructure Projects
Expert
Infrastructure Projects
Expert
Oil and Gas
Expert
Oil and Gas
Expert
COUNCIL
Expert
COUNCIL
Expert
CUSTOMER RELATIONS
Expert
CUSTOMER RELATIONS
Expert
ENGINEERING
Expert
ENGINEERING
Expert
GC
Expert
GC
Expert
MATERIALS MANAGEMENT
Expert
MATERIALS MANAGEMENT
Expert
MICROSOFT WORKS
Expert
MICROSOFT WORKS
Expert
NETWORKING
Expert
NETWORKING
Expert
OIL PAINTING
Expert
OIL PAINTING
Expert
PAINTING
Expert
PAINTING
Expert
PROCUREMENT
Expert
PROCUREMENT
Expert
REHABILITATION
Expert
REHABILITATION
Expert
CONTROL CENTER
Expert
CONTROL CENTER
Expert
PUBLIC WORKS
Intermediate
PUBLIC WORKS
Intermediate
EMPOWERMENT
Intermediate
EMPOWERMENT
Intermediate
Work Environment
Expert
Work Environment
Expert
Landscaping
Expert
Landscaping
Expert
Industrial Buildings
Expert
Industrial Buildings
Expert
Infrastructure Projects
Expert
Infrastructure Projects
Expert
Oil and Gas
Expert
Oil and Gas
Expert

Languages

Arabic

Expert

English

Expert

Memberships

kuwait society engineering

civil

September 2004