Assistant Manager
SHIMIZU CORPORATION INDIA PVT. LTD
Total des années d'expérience :19 years, 8 Mois
PreContract
•Preparation of Tender Documents, Estimation
•Validation for vendor Qualification(PQ), Floating of Tender
•Arrangement of Pre-bid & post bid meeting, Techno commercial comparison & evaluation of the Contract or bid Submission
•Recommendation to client
•Preparation of Service level agreement, Tender report & Tender Document
•PostContracts
•Payment Tracker, CMI/Variation tracker.
•Purchase Orders/SLA/Contract Document.
•Statutory compliance:-ABG, PBG, RBG, CAR, Labour Licence, Workmen Compensation Policy, any other insurance.
•Site Progress Review Meeting(MOM)-(Attend the weekly site progress meeting).
•Important/Email Communication-Critical Issue.
•NNC(Notice of Non-Compliance).
•Payment Certificates(With Contractor Corrected and original submitted Invoice).
•Contractor Submission-CMI’sImpact, Quantity Breakups, Rate Analysis(For New items).
•Signed/Approved Variation Order.
•Payment Certification:-As per SOP and agreed Billing Cycle.
•Variations/Agreed CMI impacts:-As Per SOP
Type of Project:Brownfield
•HUNTSMANPURSANCHEMICALS Project Cost : @15crs. Project location:Ataturk, Turkey
Project Name
Client Name Project cost ProjectLocationProjectDuration
: Metso Mineral Plans(Mineral Spare parts manufacturing plants, Industrial project)
: METSO MINERAL INDIA PVT. LTD. (Finland government Company)
: 60crore
Project Name
Client Name Project Cost ProjectLocation
: IndianAirForceResidentialProject(Colony, ResidentialProject)
: IndiaAirForce
: 32crore
: Baroda, Gujarat.
•Responsible for bill checking, MOM, drawing register, MOM register, bill register, site instruction register
•Built and nurture relations with clients for site execution and planning work
•Overseeallphasesofprojectexecution;approveengineering/designchanges, troubleshootandresolvecomplextechnicalproblems, consistentlymeetingprojectdeadlinesandhighestpossiblequalitystandards
•Organize and manage resources while creating estimates for the project, Work Breakdown Structure, Project Plan, Contingency Plan & Schedules, identifying risks with in defined scope, quality, time and cost constraints
•Coordination for Building Services with consultant, Architect, contractor and design team
•Meticulously handled execution work & bill checking for HVAC (central AC), installation of chiller, AHU, piping & ducting work, supply & return line, fire fighting, installation of header line, dropper, sump connection, sprinkle system, fire hydrant system, plumbing work, installation piping and fittings
Shouldered the responsibility of monitoring maintenance of 1600KVAX’mer-3, 1000 KVA-2 & 500KVA-1D.G. Set, 120KVA UPS System-2, PLC, PCC, ELDB, EPCC, LDB & Indoor& Outdoor Lighting, Mechanical valves, ETP & R.O.Plant, 11KV SubStation, Motor, Pumps, Starter, ventilationfan and compressor
Built and nurtured relations with government authorities and companies like IRIL-VERAVAL, KRIBHCO, IFFCO, GAIL, ONGC, GRASIM-NAGDA, BINANICEMENT, JKCEMENT, SANGHICEMENT, ALEMBIC, SUZLON, ENERCONetc
•Assumed responsibility for testing of Electrical protection relays, Electromechanical, static&numerical types of various makes, commissioning of outdoor as wel las indoor substation, relay co-ordination & power system studies .
MaintenanceEngineer
•Operationand Maintenance of HT & LT System, Operationand Maintenance of DG
•External Street Lighting system operation and maintenance
•Indoor & Outdoor Lighting distribution operation & maintenance
Motor
(
(
.