Gas Network System Optimization:
1. Collected and developed a list of Titas Gas Transmission & Distribution Company Ltd (TGT&DCL)
2. Supported the simulation impacts on hydraulic capacity and develop list of opportunities
3. Prioritized nodes on pipeline model and visit top priority locations
4. Developed/updated the gas network drawings (P&ID, network drawing) including future projects
5. Supported network simulation/modeling to estimate impacts on network capacity for all on-going and future expansion projects
Developing the three new well pads and surface facilities installation under the Bibiyana Drilling Program (Project cost is about US$ 110 M)
Project Management
1. Submit FE progress reports for respective projects by month end including monthly update of cost and schedule estimates
2. Follow CPDEP process for all projects at each phase or have a DRB approval for deviations
3. Follow fit-for-purpose OA for all projects, acceptable OA score at end of each phase, including score in all DSPs
4. Establish and monitor key performance indicators (KPIs) and risk mitigation plan (RMP) for CHESM on all contracts
5. Ensure that engagement meetings, Interim Reviews and End of Contract Evaluations are completed, reviewed and documented per CHESM process
6. Maintain all green lights in the CHESM Contract Owner Responsibility Log,
Procurement Management
2. 3. Manage Panalphina Expeditor & their report: Schedule weekly meeting with Expeditor & review report in detail;
4. Understand site logistics: Make quarterly trip to Field;
5. Develop a process/procedure for review ( delivery documents - QA/QC, tax, schedule etc.) of all PO before bid-out
6. Develop an approved vendors list for BPC (foreign & local)
Local Logistics Tracking
7. Tracking of all materials through the Chevron system and external: Schedule 2 training sessions with local logistics group; Input all local logistics forecast dates in the Expediting report; Obtain JDE Database Access- to collect data for expediting report
8. Understand in country logistics: Develop resource list - Chittagong & Dhaka
9. Expedite materials through customs: Call customs directly to expedite materials with logistic dept approval
10. Expedite materials while in transit from Chittagong/Dhaka to site: Make 1 trip to Chittagong and arrange with logistic lead
Expediting Management
11. Consistent Correspondence with vendors: Schedule & lead weekly meetings with current LLI and bulk material suppliers,
QA/QC Management
12. Arrange TPI inspectors with Moody Intertek/SGS: Coordinate with inspectors 1 to 2 times per week. Contact Abie Mathew to schedule Moody inspector 14 business days before each inspection; Track & review all inspection reports; Handle all QA/QC issues
13. Develop Project QA/QC Schedule & Tracker Sheet as per chevron approved supplier’s ITP
Cost Management
14. Manage, input & report monthly Capital Spend for assigned projects as per monthly Cost Management Meeting
15. Provide C&E forecast for assigned projects; Provide inputs on cost estimates for assigned project
16. Comparison of all material costs to the original budget estimates: Develop cost comparison table
17. Track QA/QC & Freight Forwarding Costs for all materials and equipment: Develop tracking cost spreadsheet
18. Track all invoices for materials and equipment: Develop progress payment spreadsheet; Create folder of invoices for Procurement items only
Organization: Bangladesh Gas Fields Company Ltd, Brahmanbaria, Bangladesh
Duration: November 1998 to March 2012
Designation: Various positions including Project Engineer for four small (US$ 10-15 M) gas plant development projects
Projects: Installation of new TEG gas process pants, construction of gathering pipelines from wellheads with associated facilities
Organization: Bangladesh Gas Fields Company Ltd, Brahmanbaria, Bangladesh
Duration: November 1998 to March 2012
Designation: Various positions including Project Engineer for four small (US$ 10-15 M) gas plant development projects
Projects: Installation of new TEG gas process pants, construction of gathering pipelines from wellheads with associated facilities
1. Provided support to engineers in planning, developing, and execution for each phase of the project thereby ensuring a successful completion of each phase.
2. supervised personnel, prepared schedules, estimated the budget, and conducted design reviews
3. Developed initial concept of the project for conceptual study (FEED), preparing detailed engineering drawings, installing and commissioning equipment, and modifying equipment.
4. Provided support to the engineering staff in peer technical review, resolution of Process Hazard Analysis (PHA), heating and cooling components, and in other I&E work.
5. Documented the project from the conceptualization and implemented it accordingly.
6. Ensured that the work was carried in accordance with the Health, safety and environment regulations.
7. Scheduled the time frame for delivery and updated all the purchase orders.
8. Assisted the Facility Operations department and managed the budget.
9. Organized the data and track systems and updated it regularly.
10. Managed material storage systems.
11. Prepared work plan for the project team.
12. Managed project costing
13. Proven track record of finishing the projects within time and according to project plans.
Norwegian Govt. Scholarship (NORAD felloship) July, 2003-June, 2005 Thesis: Study of Drag Reduction in Single Phase and Multiphase Flow. Grade: A