Duties included:
* Plant Process Continuous Improvement (MOC)
* Definition, development, and implementation of new process monitoring tools
* Review and approval of design solutions provided by contractors (P&ID, BOD, SLD, CAE, Utility Load Lists and etc.)
* Participation in technological safety meetings (Hazop, SIL, Risk Assessment)
* Support ops. team (on a daily basis)
* Troubleshooting and development of mitigation actions (alarm& trip management etc.)
* Calculations of heat and material balances
* PRV sizing check and depressurization study check for new facilities
* Review and update of technological operating instructions and process operating procedure
* Sharing knowledge with new Novatek LNG projects (supporting in BOD development, PID review)
* Staff training (junior engineers)
Achievements:
* Participation in the engineering studies for the booster compressor station project, Train 4
depressurization integration
* Participation in the engineering of Train 4, LNG truck loading facility and Booster
compressor station (Concept, Pre-Feed, FEED, Detailed Design)
* PDCS system modernization (elimination of design errors, development new tools and KPI’s)
* Increase the capacity of the Nitrogen Production unit by 6% (increase of capacity was
achieved only by changing the process parameters)
* Alarm Management (reducing the total number of alarms by 30% since plant start-up)
Achievements:
* Participation in the engineering of interconnections between Obskiy LNG and Yamal LNG
* Optimize the purging rate of flare stacks (it saves about 13 mln $ per year)
* Alarm Management (reducing the total number of alarms by 30% since plant start-up)
* Assisted the chief technologist in budgeting the department (preparing comparative
analysis, analytic letters, slides)
Achievements:
* Alarm Management (reducing the total number of alarms by 30% since plant start-up)
* Assisted the chief technologist in budgeting the department (preparing comparative analysis, analytic letters, slides)
Achievements:
* Training of new staff
* Participation in operation readiness after unit modernization (increased capacity of vacuum
crude and delayed cocking units)
* Participation in start-up and commissioning activities (plant walk downs, hydro tests and
etc)
* Supervising the construction and safe work performance (SIMOPS activities)
Achievements:
* Participation in operation readiness (was involved in developing startup schedule and
markups for different launch phases)
* Participation in start-up and commissioning activities (plant walk downs, hydro tests,
equipment internal inspections and etc)
* Supervising the construction and safe work performance (SIMOPS activities)
Achievements:
*Studied the construction of electric motors and the centrifugal pumps
Additiona degreee based on my first diploma (chemical engineering)