Piping Engineer
Worleyparsons - Saudi Arabia
مجموع سنوات الخبرة :13 years, 11 أشهر
• Site visit for Safaniyah debottlenecking plant world’s largest de-salter.
• For confirm of Tie-In points as per process PID and meeting with Aramco clients.
• Routing lines near pig launcher and receiver area piping and detail engineering.
• Complete all piping & equipment layout for facility remote header & Gas gathering manifolds.
• Making of safety instruction sheet, Hydrostatic test diagram and valve data sheets.
• Piping routing from study of Plot Plan, P&ID, Equipment layout, Vendor doc, Mechanical data sheet, Civil drawings for structure, equipment foundations, roads, etc..
• Nozzle orientation, Platform arrangement clip drawings according to maintenance & accessibility.
• Done various types of piping (Pump piping, Heat Exchanger piping, Pipe rack piping etc.
• Continuously updated project drawings & documents in 3D model to final as built.
• Review the plant 3D model from design, accessibility, maintainability aspects using Smart Plant Review.
• Co-ordinate between New Delhi and Farnborough office for modules updating in KPJV project.
• Resolve and incorporation of 60% & 90% model review comments. Finalizing Breathing air station, vendors tie in point and location according to plot plan & PID.
• Extraction, checking and issue of IFC isometrics to client for HPU & SRU,
• Preliminary study of pipe rack, plot plan, piping routing and utility station location plan. Checking all Nozzle orientation of equipment’s from vendor data sheet and PID.
• Resolve all modelling related issues with Cad Administrator as well as with Area leads.
• Giving isometric for stress analysis for critical lines & keeping ready isometrics for construction.
• Nozzle orientation, Platform arrangement clip drawings according to maintenance & accessibility.
• Prilim Piping and Equipment study, Preliminary MTO From plot plan and P&ID as per job instruction.
• Checking all Mechanical data sheet of equipment from process data sheet and P & ID.
• Resolve all modelling related issues with Cad Administrator as well as with Area leads.
• Worked in Proposal Project Like ADCO and RAPID.
• Piping routing using P & ID with latest piping software SP3D.
• Extraction, checking and issue of IFC isometrics to client.
• Resolve and Incorporation of 30%, 60% and 90% review comments.
• Releasing of Isometric for stress analysis after checking support feasibility.
• Review of lines, equipment’s and supports by using SPR to ensure sound and accurate design.
• Equipment and Piping Component Handling layout drawing for maintenance.
• Piping routing from study of Plot Plan, P&ID, Equipment layout, Vendor doc, Mechanical data sheets
• Nozzle orientation, Platform arrangement clip drawings according to maintenance & accessibility.
• Done various types of Pump piping, Heat Exchanger piping, Pipe rack piping, Utility piping
Vessel trims etc.
• Underground piping and Firefighting piping system design.
• Continuously updated project drawings & documents in 3D model to final as built.
• Reviewing modeling work of team on Smart plant Review Software to ensure quality of work.
• Isometric extraction using Isometric drawing manager to ensure quality of work.
• Checking of Isometrics with respect to P&ID’S, vendor docs, client information etc.
• Attained 60 & 90% Inter discipline Inter-office as well as Client review.
• Production of various types of acid like Acetic acid, Acetyl dehyde and Ester using distillation column and reactor by oxidation process.
• Handling of Catalytic vapors phases Reaction for Acetyl dehyde, Acetic Acid and Ester.
• Supervision during maintenance of equipment and instruments like shell & Tube heat exchangers, reactors, carburettor, blower, pumps, boiler, chillers, Compressors.
Bachelor of Technology in Chemical Engineering.