SR. ENGINEER
HPCL MUMBAI
مجموع سنوات الخبرة :11 years, 4 أشهر
Current work place HPCL MUMBAI
Present position SR. ENGINEER From Year: 1 april 2012
Projects:SULPHER RECOVERY UNIT, HPCL, MUMBAI
Details of Previous Experiences
1. Years: 2013 JANUARY to NOVEMBER2013 Company: Tecnimont ICB Pvt Ltd
Position: sr. Engineer
Responsibility:
leads a group with engineer, supervisers &forman
1.Ready for Energisation of main substation & subsystem
2.Installation and pre-commissioing of electrical equipments
3.Cable glanding &termination
4.Cable tray
5. cathodic protection
6.Manpower management
7.Asbuilt preparation
8.Recancellation statement preparation
9.Earthing, lighning protection
10.Lesson learned preparation
Description: PP&PE SWING PROJCT-ONGC PETROCHEMICAL COMPLEX (polypropylene&poly ethylene Customer: ONGC
Type of Project: PETROCHEMICAL
Location: OPAL REFINARY, DAHEJ, GUJARAT Country: INDIA
electrical equipment installation
2.Years: 2012 FEB TO JAN 2013 Company: Tecnimont ICB Pvt Ltd
Position: Sr. Engineer
Responsibility: leads a group with engineer, supervisers &forman
Energisation of unit 1& unit 2 main electrical system& Electrification of convayor system
a.installation of IPBD
b.installation of spbd
c.installation &pre-commissioning of HT< switchgear
d.installation &pre-commissioning of generator transformer
e. installation &pre -commissioning of unit, utility&Auxillary transformers
f.base frame prep
Description: 2×300 MW COAL BASED CAPTIVE POWER PLANT Customer: RELIANCE INFRASTRUCTURE
Type of Project: POWER PLANT
Location: BUTIBORI, NAGPUR Country: INDIA
3.Years: APRIL 2010 TO JAN 2012 Company: Tecnimont ICB Pvt Ltd
Position: FIELD ENGINEER ELECTRICAL
Responsibility:
responsible for the installation of all electrical equipment installation
• Installation Of all electrical equipments
(spbd, ipbd, generator terminal box, la, pt, convayor system, dc excitation system, generator, esp system, cathodic protection etc)
• As built preparation
• Re-cancellation statement preparation
• Material management
• Labor management
projects: Description: 2*660 MW JAJJAR THERMAL POWER PLANT HARYANA Customer: CHINA LIGHT & POWER (CLP)
Type of Project: POWER PLANT
Location: JAJJAR, HARYANA Country: INDIA
4.Years: NOV2008 TO APRIL 2010 Company: Tecnimont ICB Pvt Ltd
Position: FIELD ENGINEER ELECTRICAL
Responsibility:
leads a group with engineer and forman
• Installation of electrical equipments
• Cable tray, cathodic protection
• Recancellation statement preparation
• Earthing &grounding works of motor and structures
• Earth resiststance checking &recording
Description: pp, panipat naphtha cracker project (POLYPROPLENE) Customer: iocl panipat
Type of Project: petrochemical
Location: panipat refinary, haryana Country: INDIA
5.Years: JAN 2008 TO OCT2008 Company: TECNIMONT ICB PVT LTD
Position: ENGINEER ELECTRICAL
Responsibility
Supervision and guiding of contractor
1. Installation of battery (unit and station) 470 kph2400ah
2. Installation of unit transformer accessories &filteration
3. Generator transformer accessories&oil filteration
Description: 2*300MW Thermal power plant Customer: HPGCL HARYANA YAMUNANAGER
Type of Project: Thermal power plant
Location: haryana, yamuna nager Country: INDIA
6.Years: 2006 jan to 2007 dec Company: honey well automation limited (hail)
Position: LEAD ENGINEER ELECTRICAL
Responsibility
Leading a gruop in
Mumbai hay platform heera &neelam assets in cctv projct
• Material management
• Manpower allotement
• Co-ordination with ongc base
• Arranging the transportation of labor to various riggs
• Safety meassures inspection &document preparation
• Billing
• Safety drills conducting
• Rigging supervision
• As-built Drawing preparation
Description: cctv projct Customer: ongc
Type of Project: automation
Location: ongc mumbai high platform (offshore) Country: INDIA
7.Years: 2004 jan t0 2005 dec Company: neutro power &controls pvt ltd
Position: ELECTRICAL ENGINEER
Responsibility
leads a group with forman for carring out maintenence &project work of HPCL refinary
• Reporting to electrical maintenence department
• Collect daily assignments with permits
• Report preparation &day to day billing
• Workshop assistance to client employes for serviceing of motors, starters, switch gear modules
• Field assistance to operation maintanence for cable foult finding, motor ir checking, assistance to client for racking and rack out of breakers
• Cable joint, termination, hi-pot testing assistance
• Removal&transportation of motor to workshop for repiring
• Trouble shooting and replacement of fussed lamps in all units
Description: 1.lube refinary/HPCL mumbai (annual standing order jobs for maintenence) 2.110 KV gis substaion project 3. gnfc project Customer: hpcl
Type of Project: petrochemical
Location: mumbai Country: INDIA
8.Years: 2002 april to dec2003 Company: advance electrical
Position: electrical supervisor
Responsibility
E&I SUPERVISOR
Maintenence of HPCL refinery
• Reporting to electrical maintenence department
• Collect daily assignments with permits
• Report preparation &day to day billing
• Workshop assistance to client employes for serviceing of motors, starters, switch gear modules
• Field assistance to operation maintanence for cable foult finding, motor ir checking, assistance to client for racking and rack out of breakers
• Cable joint, termination, hi-pot testing assistance
• Removal&transportation of motor to workshop for repiring
• Trouble shooting and replacement of fussed lamps in all units
Description: gnfc projct/standing order jobs /annual maintenece Customer: HPCL
Type of Project: petrochemical
Location: mumbai Country: INDIA
Diploma/Degree University/College Discipline Year of passing 3 Y DIPLOMA IN ELECTRICAL ENGINEERING KERALA GOVT. POLYTECHNIC CALICUT ELECTRICAL 2002