Sherif Marzouk Hamed القطرونى, Project Construction Manager

Sherif Marzouk Hamed القطرونى

Project Construction Manager

ADES Group

Location
Egypt - Mansoura
Education
Bachelor's degree, Mechanical Engineering
Experience
22 years, 11 Months

Share My Profile

Block User


Work Experience

Total years of experience :22 years, 11 Months

Project Construction Manager at ADES Group
  • United Arab Emirates - Dubai
  • My current job since February 2023

Project at Dubai Drydocks

It is Rig ADM-266 SPS 5 Years Overhauling with budget 19 million $ including

Project Site Manager at ADES Group
  • Egypt - Suez
  • August 2022 to January 2023

It is Rig ADM-8 SPS 5 Years Overhauling with budget 18 million $ including
1- replacement of 5000 inch dia, 120 tons steel repair
2- Leg bent braces replacement
3- Leg Brocken teeth replacement
4- drilling equipment certification ( Mud pumps, top drive, draw work, Elmago, irone roughneck, rotating table
5- main engines # 1& 4 overhauling
6- install a new water maker.
7- install new 4 mud agitator.
8- DC motors inspection and certifications
9- Derrick CAT III closing and COC
10- BOP closing unites recertification
11- STBD& PS cranes
12- Shall shaker overhauling
13- Painting of hull, bottom and tanks
14- Accommodation upgrading

Project Site Manager at ADES Group
  • Egypt - Ras Gharib
  • January 2022 to August 2022

* Rig ADM-260 intended to extend the area of its cantilever with a movable extension
3m width * 12 m Length connecting with the existing cantilever by 4 pivot pins
* Rig ADM-4 intended to install 4 nos of Radiators with its connection piping (2000-inch dia) to increase the cooling rate of the Rig main engines

Construction Site Manager at ADES Group
  • United Arab Emirates - Dubai
  • August 2021 to January 2022

Project at Duabi drydocks

pursuant to ARAMCO requirement for Rig ADM-657 to be fit to work in shallow water a major modification executed for the Rig to meet the requirements such as adding 4 drill water tanks, relocate the STBD & PS cranes, extend the Helideck, relocate the STBD & PS Life boats, relocate the STBD & PS life rafts, relocate the FRC
piping modifications approx. 30, 000-inch dia for all lines (firefighting, sounding tubes, greylines, tank vents, drain lines, HP cement lines), leg bracing replacement

Site manager at ADES Group
  • Egypt
  • January 2019 to July 2019

PETROZNIMA intends to develop MUZHIL Oil Filed installation of a Wellhead
Platform (MWHP) Jacket with its boat landing, barge bumper & Top side facility with
total weight 700 tons as well as the Mobile Offshore Process Unit (MOPU)
Install the production skids (Production and test Separators, water treatment Unit,
chemical injection Packages, heater treater, Crude oil desalter, Vent gas boot and
vent stack, Water injection system ) plus the piping activities of the platform and
MOPU 7000 “
Job Descriptions
It is an EPC contract with total budget 200 million $
• Interface with my construction team and the Clients, including attending project
meetings.
• Ensure the correct application of the terms and conditions of the ongoing contracts.
• Monitoring of project resources identifying potential optimizations.
• Support the Procurement and Engineering Teams and manage material & drawings
delivery based on the project priorities & schedule
• Coordinate and manage the subcontractor’s activities and generates the SIMPOS plan to
ensure the smooth flow for the work activities
• Prepare reports, consolidating progress and highlighting areas of concern.
• Monitor the overall project/s performance in terms of scheduling, cost, quality and HSE
requirements.
• Oversee budget and ensure financial accountability.
• Identify potential contractual Change Orders and Claims and coordinate their
preparation: negotiate with Client and control the pricing variations of the contract.
• Ensure the Company Safety Standards applied in the site and the subcontractors
complied with it
• Maintain relationships with Top Management of the Clients.
• Foresee clients’ requirements and be able to provide appropriate and precise solutions.

site manager at East Zeit Petroleum (Zeitco)
  • Egypt - Ras Gharib
  • June 2018 to January 2019

Project description
1- Upgrading of Platform A phase 1 fabrication & installation a new Piping with 3000 inch
which almost completed and preparing for phase 2
2- Modification for the separator SEP 200 to change outlet from 4’ to 8’ and to be
applicable to add GLCC and Scrubber
3- 2 pipelines 5 & 8 km connecting between wells OMAR & ABDOS s to Petro Karim

site manager at PICO International Petroleum
  • Egypt
  • June 2016 to June 2018

It is EPC and turnkey project to build and install new offshore platform “PFM-C” Jacket with its boat landing, barge bumper & Top side facility (1055 ton ) in Gulf of Suez in a water depth of 25 m, adjacent to the existing platform PFM-B. In addition to lay a 10" * 1.3 km Pipeline from the new platform to the existing platform “Amal-A” Other required related topside modifications on both existing platforms A & B with 3000 “

Construction manager at Consolidated Contractors Company (CCC)
  • United Arab Emirates
  • December 2014 to May 2016

The main job was EPC and turnkey project of BP-Khazzan-CPF Project.
With 800, 000 inch dia & 17, 000 Tons steel structural of central process facility
area
• Manage and oversee the day-to-day construction management of the project.
• Control and monitor the site mobilization (Equipment, manpower and fabshop
readiness)
• Supervises and approves the development of PEP \[from construction point of view\], and
its implementation plus ensuring Lessons Learned are properly documented throughout
the life of the project including Project Close-out
• Liaise with the engineering & procurements for the material delivery to be matched
with the iso’s have been issued and the priorities
• Follow up & monitor the issuing of iso’s by engineering at head office in Sharjah to meet
the plane and priorities
• Reviews & approve method statements, TRA and provides comments related to piping
engineering designs
• plan, develop and organize the construction effort to formulate the most cost-effective
plan to Timely completion within budget and to implement the execution of that plan.
• Responsible for implementation of the scope of work as related to construction/
fabrication, and pre-commissioning facilities in conformance with project specifications,
Scope of Work, and in accordance with the approved Project Schedule.
• Monitor and report to Project Manager of project details, including progress, risks and
opportunities in a timely manner.
• Ensures all changes to specifications, work scope and drawings are documented
• Define clear roles & responsibilities and deliverable requirements in terms of both scope
and schedule to all the team members.
• Review man-hours and duration forecasts to completion for construction
• Monitor construction productivity and schedule performance and investigate reasons
for less than satisfactory performance. Provide recommendations and institute
measures for improvement by Modification to operating procedures/work instructions.
• Adhere to Company Safety Standards and promote safety culture among the ranks
throughout the Company.
• Any other ad-hoc projects and duties as required by the management.

Head at Consortium TR-CCC
  • United Arab Emirates
  • May 2013 to September 2014

Studying and checking contract documents related to the piping section
• Review and studying the budget assigned and planning stages and assuring that work is
completed on time and within budget
• Preparing the resources required (man power and equipment)
• Coordinating and monitoring the construction schedule for mentioned department with
other disciplines to insure that the schedule will be implemented and achieved without
delay
• Assuring that the works conducted is as per project quality and safety standards
• Directly in contact with the client to assure that all the obstacles and problems are
solved with the company standard
• Internal audits are conducted frequently to assure that construction work as per the
specification
• Providing the necessary technical advice for the overseen problems
• Establishing and effective reporting and monitoring system that comply with project
requirements
Identifying the priority areas and arranging the work to meet the schedule

section Head at Abu Dhabi Company for Onshore Oil Operation (ADCO)
  • United Arab Emirates
  • April 2011 to December 2012

The main job was EPC and turnkey project of SAS Project. Responsibilities
included all Subcontractor Construction duties and Follow up all Piping and
Piping Supports Construction activities, Daily report of piping erecting progress,
Controlling the subcontractor manpower, checking the Safety Procedure and
Material Tack-Off. Solving the field Construction Problems. Check & review the
piping test packs & punch list, Witnesses for all Piping Pneumatic & Hydrostatic
test, Clear punch items & Reinstatement, modifications. Checking isometric
DWG`s, procedures & design for Under and Above ground pipes according to
pipe Project Specifications & Standard Code (ASME B31.3 & ADCO
specification), Reviews method statements, TRA and provides comments related
to piping engineering designs

Mechanical Engineer at Alamal petroleum company (AMAPETCO)
  • May 2010 to April 2011

Project Description : increasing the plant capacity to produce 25, 000BBL/D oil & 70 MMSCF/D by
upgrading the onshore plant & offshore platforms :
Offshore Activities
A-Installing new four subsea P/L as follows including:
1- 24” subsea producing P/L “Total length 16.5 Km”.
2- 4” gas lift P/L between Amal A & on shore facilities piggybacked to the 24”
line.
3- 8” subsea inter connecting production P/L “Total length 1.3 Km” between the
two platforms.
4- 4” water injection subsea inter connecting P/L between the two platforms”
Total length 1.3 Km”. Also supervising fabrication & installation activities “on
PMS 12 barge” of sea P/L riser’s spools, riser’s spools clamps & spools
required for new pipelines tie-in to exist facilities. 5- Fabrication &
installation of P/L risers & riser’s clamps using PMS-12. 6- Fabrication &
installtion of P/L spool pieces & closing spools using PMS-May
B- New deck extension for existing PFM -A:
• Fabrication & installation of new deck extension at main & lower decks
supported to existing platform piles, as it was designed to contains the top
side facilities that is 24” producing P/L pig launcher, 4” gas lift P/L pig
receiver, 8” producing P/L pig receiver & 4” water injection P/L pig launcher
& also all connecting piping, also it was done using PMS-12.
• Fabrication & installation of new deck extension sea fastening beams to PMS-
44
• Also it was designed to contain new production & test headers, as it was
resized to handle the new expected producing rates
Onshore Activities
Extension for the existing onshore plant, by installing
1-New 2 oil metering tanks with Max. capacity 15, 000 BBL
2- New vessels & equipment such as slug catcher, HP scrubber, HP flare, new utility
& instrument air compressors & receivers etc...
3- Install 16" x 10 km Gas Export U/G pipeline Carbon steel API X-65 from GOSP to
GUPCO U-104
Job Descriptions
My responsibilities as a Sr. Mechanical engineer with PMC team to ensure
that contractual requirements regarding the discipline technical & HSE
related issues are fully adhered to:
• Monitor mechanical progress & testing activities on site, and report to the Line
Supervisor any abnormalities regarding discipline contract scope, requirements
and site queries.
• Apply specialist knowledge of international safety standards and procedures
applicable to the Oil & Gas industry are essential .
• Utilize experience supervision.
• Interpret technical drawings & write technical reports in the appropriate
engineering discipline.
• Monitor & report on all discipline quality issues, and prepare NCR’s if any.
• Maintain a daily site diary.
• Participate in technical audits.
• Ensure that the company’s interests are safeguarded.

Section Head
  • August 2008 to March 2010

Project Description : Construction of New Gas Plant (Responsible for the construction of 2 trains (
DGA LP100 and DGA LP200 With More Than 270, 000 Inch dia )
Job Descriptions
• Reporting to Construction Manager
• Site mobilization of equipment, tools and manpower; and review of construction
drawing and specification as per the contract.
• Attend the meeting with client to discuss the progress and assign the priorities.
• Assign the work scope to Jr. Engineer and General Foreman according to
schedule.
• Arrange delivering the spools from painting to the area based on the priorities.
• Monitoring site activities and site Supervisors.
• Monitoring the daily progress of spools and inch diameter as per the planed
scheduled.
• Ensuring that the safety precautions are implemented during the construction
activities at site.

Section Head
  • June 2007 to July 2008

Project Description : Construction of New NGL Plant 3 NGL trains, utilities area and product surge
area (Responsible for The Construction of the third NGL train (NGL3) with
350, 000 inch dia
Company : The Petroleum Projects and Technical Consultation Co. (PETROJET

at DAMIATTA
  • Egypt
  • November 2006 to June 2007
  • October 1998 to June 2007

Through 9 years my service in PETROJET I have been worked in 11 projects listed
below and I promoted from junior engineer to Mechanical section engineer with
different

at SULPHAT AMOUNIA PLANT
  • April 2006 to November 2006
at HA’PY COMPRESTION STATION
  • Egypt
  • July 2005 to April 2006
at JORDANIAN GAS PIPE LINE
  • Jordan
  • July 2004 to July 2005
at SEGAS L.N.G. Project………………….DAMIATTA
  • Egypt
  • June 2003 to July 2004
at EL Ariesh
  • Egypt
  • September 2002 to June 2003
at SCARABE SAFFRON Developmen
  • Egypt
  • November 2001 to September 2002
at CENTURION TIE
  • Egypt
  • June 2001 to November 2001
at Waste Water Treatment Unit…………….
  • Egypt
  • January 2001 to June 2001
Section Engineer at MIDWATER Station
  • Egypt
  • August 2000 to January 2001

Position holds and assignments through my service in PETROJET

Education

Bachelor's degree, Mechanical Engineering
  • at Mansoura University
  • January 1998

:

Specialties & Skills

Planning
Mobilization
CLOSING
CUSTOMER RELATIONS
ENGINEERING
MICROSOFT WORKS
PAINTING
SCHEDULING
SPECIFICATION
UPGRADES
BUDGETING