The scope includes ENGINEERING, PROCUREMENT and CONSTRUCTION of One No: of ASL Stabilizer tank replacement at PS 3 (BI-10-09941) with approx. 1, 52, 544 cu.m storage capacity associated Civil works, Piping connection including tie-ins, Mechanical Works, Electrical Works, Instrumentation Works and Fire Fighting Works. Responsibilities includes

 Setting up the quality management system and monitoring its implementation during all phases of the project execution.
 To ensure that the quality policy of the company is achieved.
 Ensuring that all the specification requirements are maintained, and company own system is compatible.
 Organize and conducted audits on the company operation & Perform internal quality audits.
 Ensure the procedures and methods of testing and inspection are maintained.
 Handle all quality issues with project management and liaise with the project owner representative
 To handle the customer complaints on quality and investigate.
 To train and ensure the competency of the employees.
 Supervising a multi-discipline team of QC staff on site.
 The position also involves setting up and providing quality training for the project personnel.

QC Manager في BONATTI S.p.A
  • المملكة العربية السعودية - الجبيل
  • نوفمبر 2015 إلى يناير 2018

Worked with Bonatti as their QC Manager for the Replacement of KRT-2 Pipeline and Day lighting Lateral lines SJ-1, QJ-2 and QJ-3. The Scope of Work describes the minimum requirements for replacement of KRT -2 Crude Oil Pipeline between Km 106 (Near Kursaniyah Trap Area) and Km 199 (Near RasTanura Refinery) and day lighting of four (3) pipeline laterals ( QJ-2 and QJ-3) between Juaymah Terminal and Trap Area located approximately 400 m outside the terminal fence.
For Day lighting the job consists of fourteen Hot taps along with the line replacement. For KRT-2 pipe line (approx. 92 Kms) must be constructed hydro tested, lay upped prior to handing over the line to the proponent.

QA Manager في DAELIM INDUSTRIAL CO. LTD
  • المملكة العربية السعودية - الجبيل
  • يناير 2015 إلى أكتوبر 2015

Worked as QA manager for SEP, KEMYA project for Sales Gas Delivery System (ARAMCO LINE) under Daelim Saudi Arabia. Al- Jubail Petrochemical Company (Kemya) is a joint ventire between SABIC Company and EXOONMOBIL Company in Jubail Industrial City, Saudi Arabia. Kemya is installing a new chemical complex in the Industrial City to Manufacture Elastomers . Kemya requires Sales Gas (Fuel gas) for their Manufacturing Processes. New Sales Gas Custody Metering System will also be provided under this project.

This Project consists of a hot tie-in and a new custody metering skid will be installed to supply Sales Gas to Kemya.There will also be new flow computer and Communication Equipment will be located inside the excisting metering control room also located within the existing meter station compound.
My responsibilities are to endure:
 Products meet required standards of quality.
 Coordinate quality assurance programs and formulate quality control policies.
 To improve an organization's efficiency and profitability by reducing waste and fulfilling the Client requirements.
 Arranging internal audits and coordinating to correct and fulfill the audit findings and requirements.

QA/QC Manager في AL YUSR INDUSTRIAL CONTRACTING COMPANY AL-JUBAIL (AYTB)
  • المملكة العربية السعودية - الجبيل
  • أكتوبر 2013 إلى يناير 2015

AYTB was established over 30 years ago to provide quality products and services to the petroleum refining, petrochemical and chemical, power and desalination industries throughout Saudi Arabia. Today, AYTB has become one of the leading project management, construction and fabrication contractors in Saudi Arabia and Qatar for the supply of medium sized installations, providing responsive and innovative solutions to these vital industries. AYTB is doing Off plot pipe line project for SADARA as a main contractor and I am deployed as their project QA manager. My responsibilities are:
 Coordinating with Corporate QA Manager and Site QC Manager about the quality assurance requirements of the project.
 Timely Preparation, review and submission of the PQP, Procedures and ITP for the client review and approval as per contract requirements.
 Hydro test package review and approval prior to submission for client.
 MCC package preparation with registration and submission for final acceptance.
 Coordinating and attending the internal QMS and program audits and providing proper dispositions for observations and NCRs after consulting with concerned departments.
 Conducting Management review meeting and submitting the MOM to client as per contractual requirement.

QA/QC Manager في WOONGNAM E&C, STFP, JUBAIL
  • المملكة العربية السعودية - الجبيل
  • أكتوبر 2012 إلى أكتوبر 2013

Woongnam is subcontractor to Daewoo EPC for their mechanical works for fabrication of Tanks for this Sadara Project. Here my responsibility includes
 Monitoring and implementing site inspection activities of QC inspectors, coordinating with SATORP QC team, Project Management Team and Construction representatives.
 Coordinates with third party NDT services, Sub contractors and client inspectors.
 Proposing the corrective and preventive action for non-confirmations raised during construction phase, internal audits and SADARA assessments.
 Review and approval of QC documents as per the project requirements & co-ordinate with third party for the procedure qualification, welder qualification etc.
 Review and approval of QC documents as per the project requirements & co-ordinate with third party for the procedure qualification, welder qualification etc.

QC Manager في DAYIM PUNJLLOYD, KFIP, JUBAIL
  • المملكة العربية السعودية - الجبيل
  • أكتوبر 2011 إلى أكتوبر 2012

The project scope is spread across five main areas of King Fahad Industrial Port (KFIP) area like the Royal Commission Corridor, the SASREF Pipe Corridor, the Tank Farm Area, Berth 54 and Jetty Corridor from RC Corridor, Berth 62 and Jetty Corridor To Berth 62 from RC Corridor, including the fabrication and installation of piping /pipeline spools installation of equipment, erection of structures, Civil activities and pipe racks.

 Worked as QC Manager for the said project, assigned to monitor and implement site inspection activities of QC inspectors, coordinate with SATORP QC team, Project Management Team and Construction representatives.
 Assisting QA manager in MQMR preparation and assuring the submission of the same to the client every month before fifteenth. Also involved in reviewing and achieving the two week look ahead inspection schedule for construction activities through required quality. Reviewing and approving weekly welder performance report, weekly weld rejection and weld summary report etc.
 Assigning the job to QC engineers and inspectors. Coordinates with third party NDT services, Sub contractors and client inspectors, hence helping QA Manager.
 Assist with the internal, SATORP and ISO audit team during project assessment Planning, coordinating and conducting the internal audit as per schedule including sub contractors.
 Proposing the corrective and preventive action for non confirmations raised during construction phase, internal audits and SATORP assessments.
 Monitoring the smooth operation of document control. (DCC)
 Review and approval the QC related documents like procedures, ITP’s, WPS of vendors, subcontractors and ensure the inspections are carried out as per the inspection level requirements.
 Review and approval of QC documents as per the project requirements & co-ordinate with third party for the procedure qualification, welder qualification etc.

QA/QC SUPERVISOR في SALIM AL-JOAIB & PARTNERS Co, Saudi Arabia (SJC)
  • المملكة العربية السعودية - الدمام
  • مارس 2011 إلى سبتمبر 2011

Worked for the above Saudi Aramco Project, Qatif as QC supervisor for M/S Al- Joaib & Partners Co. This project consists of flow lines for water injection wells at Qatif well site W-21.
As QC Supervisor my responsibility is to
 Lead and manage a team of QC Engineers and Inspectors to support in Quality activities.
 Deals with the Client regarding the Quality matters for the smooth running of the activities to assure the productivity with quality.
 Attending the progress meetings and progress meeting with the client and implementing the requirements through meetings with QC department.
 Coordination with client and contractors for NDE activities.
 Coordinate with client inspection department / third party inspection department for quality issues
 Manage to Compile reports and documents for QA/QC Document Control
 Monitor performance of the welders on the basis of radiographic inspection and promote corrective action where necessary through inspectors.

QA/QC MANAGER في KARAN PIPELINE PROJECT, Khursaniyah
  • المملكة العربية السعودية - الجبيل
  • أكتوبر 2010 إلى ديسمبر 2010

Worked for FMQ as a QA/QC manager for their Aramco pipe line project at Khursaniyah. This is pipeline of about twenty five kilometer from sea shore to Khursaniyah Gas Plant (KGP).
 Lead and manage a team of QC Engineers and Inspectors to support in Quality activities.
 Deals with the Client regarding the Quality matters for the smooth running of the activities to assure the productivity with quality.
 Attending the progress meetings and progress meeting with the client and implementing the requirements through meetings with QC department.
 Coordination with client and contractors for NDE activities.

QA/QC MANAGER في NATIONAL CONTRACTING
  • المملكة العربية السعودية - الجبيل
  • يناير 2009 إلى سبتمبر 2010

 Lead and manage a team of QC Engineers and Inspectors to support in Quality activities.
 Deals with the Client regarding the Quality matters for the smooth running of the activities to assure the productivity with quality.
 Attending the progress meetings and progress meeting with the client and implementing the requirements through meetings with QC department.
 Monitor performance of the welders on the basis of radiographic inspection and promote corrective action where necessary through inspectors.
 Review the effectiveness of the quality plan and make adjustments as required.
 Interface with the Engineering Department on problem resolution, NCR, and changes
 Assure that adequate training of Quality Control personnel is done to ensure optimum utilization of Inspectors and NDE Specialists
 Manage to Compile reports and documents for QA/QC Document Control
 Ability to read, interpret and apply engineering drawing requirements
 Reviewing and checking of welding procedures for welding Carbon steels, Stainless steels and Alloy steels materials
 Conduct procedure qualification (PQR) test as per welding procedure specification (WPS)
 Coordinate with client inspection department / third party inspection department for quality issues
 Involved in preparation, fabrication and documentation for ASME review Audit for attaining the “A” and “PP” stamp for the company.

QA/QC INCHARGE في SINOPEC- Second Construction Company, China - SAUDI KAYAN
  • المملكة العربية السعودية - الجبيل
  • مارس 2008 إلى ديسمبر 2008

 Lead and manage a team of Welding Inspectors to support in Quality activities and report every activity (daily task) to QA/QC Manager
 Direct the preparation and implementation of Quality Control procedures and processes
 Review the effectiveness of the quality plan and make adjustments as required.
 Interface with the Engineering Department on problem resolution, NCR, and changes
 Assure that adequate training of Quality Control personnel is done to ensure optimum utilization of Inspectors and NDE Specialists
 Review all contract proposals to identify any special quality requirements and advise appropriate departments. Conduct contract specification reviews both at the proposal phase and contract execution stage to assure that requirements have been clearly defined and can be met
 Compile reports and documents for QA/QC Document Control
 Ability to read, interpret and apply engineering drawing requirements
 Reviewing and checking of welding procedures for welding Carbon steels, Stainless steels and Alloy steels materials
 Conduct procedure qualification (PQR) test as per welding procedure specification (WPS)
 Organize and conduct welder’s qualification test as per ASME Section IX and client specifications
 Inspection of electrodes, filler wires and gas used for welding
 Control welding consumables and documents
 Visual Inspection of pipe fit up and weld joints and reject/accept as per acceptance criteria of ASME B 31.3
 Visual Inspection of structural members fit up and weld joints as per acceptance criteria of AWS D 1.1
 Monitor preheating prior commencement of welding and interpass temperatures during the welding
 Monitor performance of the welders on the basis of radiographic inspection and promote corrective action where necessary
 Coordinate for Non Destructive examination of welds(RT/UT/MT/PT), pressure tests in accordance with approved procedures and QC plans
 Coordinate for Post weld heat treatment of welds, monitor the heating rate, soaking time and cooling rate during heat treatment
 Liaise with client, Authorized Inspector and Third party
 Prepare inspection test plans and Preparation of project welder performance/rejection report
 Coordinate technical queries with project management team on daily basis
 Coordinate with client inspection department / third party inspection department for quality issues

THIRD PARTY INSPECTOR في VELOSI Certification, Qatar.
  • قطر - الدوحة
  • ديسمبر 2006 إلى يناير 2008

Worked with Qatar Petroleum (QP) as lead QC inspector Mechanical in Dukan area. Also got opportunity to work in Bahrain as Qatar Gas representative for their Ship loader which is fabricated and pre commissioned at Nass Mechanical Contracting Company W.L.L. The main Contractor is Voest Alpine Material Handling, Austria. As a resident engineer for Qatar Gas my duties includes the overall work assessment which consists of fabrication, NDT check, pre-commissioning and the factory acceptance before transporting to Doha.
Also I worked as TPI for CTJV (Chiyoda Technip Joint Venture) for their work at Ras Lafan plant Qatar from Dec 2006 to March 2007. My responsibilities are the inspection of the Air Cooled Heat Exchangers during there assembly and installation. It includes the material inspection while received at site, dimensional checks, the shaft verticality, blade angle, tip clearance, alignment between fan and motor etc. as per API 661.

في Ras Lafan plant Qatar
  • ديسمبر 2006 إلى مارس 2007

My responsibilities are
the inspection of the Air Cooled Heat Exchangers during there assembly and
installation. It includes the material inspection while received at site,
dimensional checks, the shaft verticality, blade angle, tip clearance, alignment
between fan and motor etc. as per API 661.

Mechanical Engineer في KHALDA PETROLEUM
  • مصر
  • فبراير 2006 إلى نوفمبر 2006

Worked with Khalda Petroleum Company (KPC), a joint venture between
Apache Crop and the Egyptian General Petroleum Company (EGPC) plan to
develop the QASR gas field in the Western Desert of the Arab Republic Of
Egypt.
❖ The QASR gas and condensate field is initially planned to consist of eight
wells with a further eight to follow after first gas, linked to a manifold and
processing facilities at QASR. The part of development also includes the
export of gas and condensate from this manifold to manifold at Shams
followed to the exciting processing plants at Tarek and Obayied through new
pipe line. The design is done by JP KENNY.
❖ As a Mechanical Engineer my duties includes arrangement of the work as per
the P and ID, Isometrics as per the required specifications, Installation, Punch
listing, Hydro testing and pre Commissioning before handing over the system.
Inspection and Installation of equipments like Test Separators, Three phase
production Separators, Oily Water treatment and Degassing equipment, Flare
system, Air-cooled heat exchangers, process and utility pumps etc comes
8
under my responsibility.

QA في TECHNIP
  • المملكة العربية السعودية
  • فبراير 2004 إلى مارس 2005
Documentation Engineer في Alstom Projects India Ltd
  • الهند
  • أكتوبر 2001 إلى نوفمبر 2003

MechanicalQC /

Construction Engineer في Indian Oil Corporation Ltd
  • الهند
  • مايو 2000 إلى سبتمبر 2001

includes
supervision of Tanks and Pipings as per IS, API & ASME Codes.
❖ Supervision of Product Tanks having a total capacity of 70, 000MT and
inplant Pipeline works including shot blasting, fabrication, and erection,
Interpretation of Radiography, Hydrostatic testing and painting before
commissioning
❖ In charge of fabrication, erection and welding of Storage tanks (ULP, SKO,
HSD) and Fire water tanks for Fuel Handling System, Product piping and Fire
protection system (as per OISD-117) for entire Oil storage tanks and piping
system
❖ Equipment erection and commissioning of entire system. The job involved
planning of the entire work, ensuring adherence to schedules and inspection
and quality control of the job. Involved in welding procedure and welder
performance qualification of the Storage tanks as per API 650/, IS 803.

Junior Engineer في Ray Constructions Limited
  • الإمارات العربية المتحدة
  • يوليو 1999 إلى أبريل 2000

BPCL) Site Irimpanam under FEDO
supervision - Nature of duties includes supervision of sand blasting, painting,
fabrication, erection and hydrostatic testing of product pipelines, fire hydrant
lines etc, before commissioning as per IS Code.
❖ Responsibilities also include supervision of coating of underground pipes
ranging from 80 NB dia to 600 NB dia.
❖ Interpretation of radiography, Maintaining records, Billing with Clients

Apprentice في Travancore Cochin Chemicals Ltd. Udyogamandal
  • الإمارات العربية المتحدة
  • ديسمبر 1997 إلى يونيو 1998

11
Education
Tips
❖ Undergone training in mechanical maintenance, which includes maintenance
of pumps, compressors, blowers and refrigeration equipments.
❖ Duties include maintenance of utilities like Boilers, Cooling Towers, Air
❖ Compressors and Water Treatment etc., fabrication and erection of pipelines
like Fire hydrant lines, PVC lines, FRP lines and Steam lines.

الخلفية التعليمية

بكالوريوس, MECHANICAL ENGINEERING
  • في Mahatma Gandhi University
  • يناير 1997

 Certified API-510 inspector.  Certified Welding Inspector, CSWIP(3.1) from TWI  ISO 9001:2015 Transition training Certified by IRCA (17901) MATRICULATION 1993 –1997. Mahatma Gandhi University, Kottayam, Kerala.  B.TECH in MECHANICAL ENGINEERING.  First Class. 63%. 1990 Board Of Public Examinations, Kerala.  Secondary School Leaving Certificate.  High First Class.  81.6%. Passport No : G 4405466. Father's Name : Markose M Zachariah. Religion : Christian. Driving licence No : EKL 475/96 Date of birth : 13/09/1974.

الثانوية العامة أو ما يعادلها, MECHANICAL ENGINEERING
  • في Board Of Public Examinations
  • يناير 1990

Specialties & Skills

Controls
Interviewing
CUSTOMER RELATIONS
MECHANICAL
MICROSOFT WORKS
OIL PAINTING
PERSONNEL
PROCUREMENT
PROJECT MANAGEMENT
QUALITY
QUALITY CONTROL

اللغات

الانجليزية
متوسط

التدريب و الشهادات

B TECH IN MECHANICAL ENGINEERING (الشهادة)
تاريخ الدورة:
October 1997

الهوايات

  • Watching television, searching internet for new activities happening in the world
    API 510, ISO 9001:2015, CSWIP 3.1