Tauqeerur Rahman, Mechanical Construction Manager

Tauqeerur Rahman

Mechanical Construction Manager

Expertise Contracting Company

Lieu
Arabie Saoudite - Jeddah
Éducation
Baccalauréat, Mechanical
Expérience
13 years, 7 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :13 years, 7 Mois

Mechanical Construction Manager à Expertise Contracting Company
  • Arabie Saoudite - AlJubail
  • Je travaille ici depuis janvier 2022

Job Title: Mechanical Construction Manager
Job Role:
 To ensure the erection, fit up welding of CS up to 30 inch N.P.S. process and 590 m laying RTR piping of Fire water line, utilities line.
 To ensure the red line drawing as per site modification/re-routing and raise the TQ to design team and prepare the FCN (Field Change Notice) for client approval.
 To ensure the isometric vs M.T.O. quantities and Proposal submitted to client for tie-in point of utility line, prepared the M.T.O. for fire main water line
 Prepared the method statement related to work scope.
 To ensure the welding activity as per approved WPS, follow the approved ITP and pro-actively plan for minimize the occurrence to get weld repair joint after perform NDT at field weld.
 To ensure the proper material handling at site.
 To ensure the implementation of basic safety rule and regulation during site activities.

Key Projects (Construction):

 North Jeddah Bulk Plant Expansion Project, Jeddah, Saudi Arabia

Client: Saudi Aramco
EPC Contractor: SSEM, Jeddah, Saudi Arabia
Project Value: 24 million SAR

Piping Superintendent à Gas Arabian Services Co. Ltd
  • Arabie Saoudite - AlJubail
  • septembre 2018 à août 2020

Job Title: Piping Superintendent
Job Role:
 To ensure the erection, fit up welding of CS, SS up to 30 inch N.P.S. process and utility line.
 To ensure the erection, fit up, welding of 10 inch N.P.S. CS A.G. pipeline (6.1 K.M.) from SASREF fence to Process area.
 To ensure the erection, fit up, welding of 10 inch N.P.S. CS U.G. pipeline (350 M) from SIPCHEM tie-in to SASREF fence through RC Corridor.
 To ensure the red line drawing as per site modification/re-routing and raise the TQ to design team and prepare the FCN (Field Change Notice) for client approval.
 To ensure the isometric vs M.T.O. quantities and Proposal submitted to client for tie-in point of utility line, prepared the M.T.O. for fire main water line
 Prepared the method statement related to work scope.
 To ensure the Pre-assemble, installation of Pipe Rack, Compressor shelter, Dryer Shelter.
 To ensure the installation of Knock out drum, Dryer Skid, Lube Oil Cooler.
 To ensure the close the A-Punch prior to hydro-test and after hydro-test closes the B-Punch, C-Punch, MC Punch and PSSR Punch for plant start-up.
 To ensure the installation of re-routed underground GRE Pipe fire water line including fire hydrant, fire hose reel cabinet, Post indicator valve and Sewerage Drainage System GRE Pipe
 To ensure the Service test of Fire Water Line Sewerage drain system.
 To ensure the excavation, Installation, Backfilling of pipe sleeper and pipe support for 10-inch CS line.
 To ensure the installation of piping insulation scope of work.
 To ensure the welding activity as per approved WPS, follow the approved ITP and pro-actively plan for minimize the occurrence to get weld repair joint after perform NDT at field weld.
 To ensure the proper material handling at site.
 To ensure the implementation of basic safety rule and regulation during site activities.

Key Projects (Construction):

 CO2 Feedstock Supply from SASREF to SIPCHEM (IMC), Jubail, KSA

Client: SIPCHEM
EPC Contractor: GAS Arabian Services Co. Ltd., Jubail, K.S.A.
Sub-Contractor: ANABEEB/Al-FANAR/PAN GULF/AL-MUZAIN
Project Value: 30 million USD

Construction Manager à Petromen Contracting & Oil Field Services L.L.C
  • Émirats Arabes Unis - Abu Dhabi
  • septembre 2015 à juillet 2018

Job Title: Construction Manager
Job Role:
 To ensure the prefabrication, erection, NDT test, Hydro-test, Re-instatement, CS, SS, LTCS, duplex up to 10 inch NPS (Approx.10, 000-inch dia), SCH 10 to 80.
 Installation of Underground GRE Piping 675 m, Installation of CS galvanized threaded joint (855m)
 To ensure the sand blasting, painting, color coding, stenciling of piping approx. 800m for flare modification.
 To ensure the Installation of pipe bridge, Trestle foundation structure, Cross over bridge, Installation of pump with alignment, Installation of seal drum for flare modification.
 To be ensure Tie-in Connection 48 Inch SDSS and LTCS with Flares.
 To be ensure 80 Ton Steel structure & Pipe support installation.
 To ensure the prefabrication, erection, NDT test, Hydro test, of CS, SS, Duplex up to 36-inch NPS SCH 10 to 80 piping project (12, 100-inch dia.) of Desalination Unit A & B.
 To ensure the installation work of ½ inch NPS C.S. lead piping (13k.m.) and ½ inch NPS S.S. steam tracer tube (13k.m.) on the Pipe rack.
 To ensure the installation, pigging test, pneumatics test of sect piping ¾ inch NPS CS heat tube pipe SCH.40 (5.1 k.m.) on carrier pipe including installation of Pull /Splice box, splice junction box, Sleeve coupling.
& B.
 Co-ordinate with client to make any change against drawing.

Key Projects (Construction):

 Takreer CBDC Project, Package-3 Samsung Engineering Co. LTD., Ruwais, U.A.E.
Client: Ruwais Refinery, Takreer (ADNOC)
EPC Contractor: Samsung Engineering Co. Ltd
Main Contractor: Petromen Contracting & Oil Field Services
Project Value: 4 million USD

 CME&I Works of HP Flare Modification at CDES, ADCO ASAB, Petrofac, Asab, U.A.E.
Client: ADCO
EPC Contractor: Petrofac
Main Contractor: Petromen Contracting & oil Field Services
Project Value: 6 million USD

Mechanical Engineer à Abdullah A. Al-Barrak & Sons Group of Companies
  • Arabie Saoudite - AlJubail
  • mai 2012 à août 2015

Job Title: Site In-Charge (Piping & Mechanical)
Job Role:
 To ensure the prefabrication, erection of CS, Alloy Steel, SS Piping up to 24-inchNPS (8600-inch dia.) SCH. 10 to 160, XS, STD, XXS.
 To ensure the laying, jointing, Hydro test of pipeline up to 20 inch NPS Riser installation, concreting, backfilling, asphalting of fire water supply line underground CS pipe to RTR pipe.
 To ensure the prefabrication of sump covers checkered plate, monkey ladder, and support for transmitter, manhole cover & modification of R.T.R. (Reinforced transmitted resin) pipe (28”, 30”) and painting of sump cover plate, monkey ladder, sump, sand blasting and relocation of motor push button, level transmitter, pressure transmitter.
 Pipe replacement up to 20 inch N.P.S. and valve (Gate, Globe, Ball, Butterfly) replacement, Reposition of valve, steam trap replacement.
 To ensure strip out of well head piping and accessories including fence as per scope of work and re-installation of well head piping followed by hydro testing.
 To ensure the Heat exchangers (De-blinding, hydro-jetting, inspection, hydro-test, blinding, bolt tightening & leak test).
 To ensure the Columns, vessels, tanks, (De-blinding, Hydro jetting, blinding, and bolt tightening).
 To ensure the Psv’s, Motor’s, Rupture disc’s, Mechanical valve’s, Instrument’s, Control valves, (Dismantle, Isolate, Pre-inspection, Post-inspection, Re-installed), Piping (Blinding, cut & remove line, welding of joints, hydro test, de-blinding)
 Completion of shutdown as per plan job of static equipment like column, drums, vessels, heat exchangers as per industry standards and specification.
 Co-ordination with main stores for the necessary arrangement of material, consumables and tools through material requisition and follow up for PTW issuance on time at site.
 Check the quality of work participated in maintenance of mechanical (Pressure vessel, Piping, heat exchanger, Column) & Painting, sand blasting. Work controls the safety environment, control the manpower satisfied the client and our company management.
 Attend the progress and planning meeting for daily progress and interact with the client engineers for the modification as per required at site.
 To ensure the implementation of basic safety rule and regulation during site activities.
 Manage manpower and controlling the site Mechanical Activities.

Key Projects (Construction):
 Replacement of underground CS by RTR Pipeline of OWLS Project, GOSP, Qateef, Saudi Aramco
 Replacement of Sub-Standard CS firefighting by RTR Pipeline (3.3 K.M.), J.T.F., Saudi Aramco
 To Stripout and re-mainingfold of Gas Well head at South Ghawer (60 No.’s), Saudi Aramco

Key Projects (Maintenance):
Sea water intake & Utility line Sohar, SUCI
Module A & B turn around Hadeed, SABIC
Polyethylene TA Equate Petrochemical, Kuwait
IWS (Inspection work Sheet TRS 2014 Yanbu refinery, Saudi Aramco
EDC & IWS Piping modification/replacements works TRS 2014 Riyadh refinery, Saudi Aramco
T/A 2013 Static & Rotary Equipment in PC, EC &DMC TA Saudi Kayan, SABIC

Site Engineer (Mechanical) à Satnam Global Infra Project Ltd
  • Inde - Delhi
  • juin 2009 à mai 2012

 To ensure the pre-fabrication, erection, fit-up, welding of C.S., S.S., Duplex Piping
 To ensure the pre-commissioning activities hydro-test, air blowing of Piping.
 To ensure the close of A-Punch prior to do hydro-test, B-punch, C-punch after hydro-test for PSSR.
 Co-ordination with the planning team for the progress monitoring and preparing of BOM & BOQ after drawing studies and clients for the material, approved drawing, and work scope related activities.
 Prepared as built drawing and checked the work done as per drawing given plan/schedule.
 Cross checked fabricated spool, pipe support and welding, fabrication activities at site.
 Isometric free hand drawing making and did the special arrangement for the separate storage of Duplex, S.S. & C.S. materials.
 Deal with client to make any change against drawing and prepare the FCN (Field Change Notice) for client approval.
Key Projects:

 Reliance Industries Ltd., Mumbai
 Barouni refinery (Indian oil corporation Ltd.), Bihar
Client: IOCL
Main Contractor: Satnam Global Infra Project Ltd.

Éducation

Baccalauréat, Mechanical
  • à Magadh University
  • avril 2009

Specialties & Skills

Team Player
Achieving Targets
Team Handling
Project Coordination
Project Control
Client Co-Ordination
Safety and Quality in Job
Pre-Commissioning activities
Execution the Piping Pre-Fabrication, Erection activities
Team management
Planning & Scheduling
Painting

Profils Sociaux

Site Web Personnel
Site Web Personnel

Le lien a été supprimé pour non-respect des conditions d'utilisation. Veuillez contacter l’équipe d'assistance pour plus d'informations.

Langues

Arabe
Expert
Anglais
Expert
Hindi
Expert
Urdu
Expert

Formation et Diplômes

AUTOCAD 2D & 3D (Certificat)
Date de la formation:
March 2010
Primavera P6 (Certificat)
Date de la formation:
January 2021
IOSH Managing Safely (Certificat)
Date de la formation:
March 2021
Diploma in Piping Engineering (Certificat)
Date de la formation:
November 2009

Loisirs

  • Listening To Music
  • Cricket
  • Team Player,