Senior Quantity Surveyor (Team Leader)
Wajood Cont. LLC
Total years of experience :24 years, 2 Months
Construction Stage (Post - Contract)
Site Visits & Analysis
Budget estimate and Cost Control
Attendance at meetings
Interim Payments (Contractors, Subcontractors & Suppliers )
Variation and EOT claims
Update cash flow & Monthly financial report (CVR)
Maintain contractual records and documentation.
Final Account
------------------------------------------
Tender Stage (Pre - Contract)
Prepare tender documents incorporating the Client's
requirements
Prepare Bills of quantities & Quantities take off
Arrange delivery of tender documents to selected
tenderers.
Price tender documents to provide an estimate
comparable with tenders.
Review of Tender documents to identify exact
requirements and potential issues
Prepare tender documents for sub contract & suppliers
Tender pricing and Rate Analysis
Value : UAE Dirham 61 million
Scope : Construction of BSP Substation - 220kV & 66kV
Employer : Electricity & Water Authority (EWA)
Architect / Consultant : ESB International
---------------------------------------
Responsibilities (Post Contract)
Quantities take off by complying with standards.
Preparation, presentation and negotiation of Variation and EOT claims.
Preparing of interim valuations for Contractor,
subcontractors and suppliers in accordance with contract requirements.
Maintain contractual records and documentation.
Manage all internal and external commercial
correspondences.
Update cash flow, CVR and identify financial risk.
Maintain good working relationship with / and
between internal team and client / Consultant
team through regular progress meeting
attendance.
Pre Contract: (Design Stage & Tender Stage)
Project : Duqm Material Market, Oman (Area 100, 000 sqm)
Duties : * Tender BOQ (full details) & Quantity
take off
* Compiled Tender & Contract Document
* Cost Planning * Preliminary & Budget
Estimate
Employer : Oman Wanfang LLC & Al Thabat Holding LLC
Value : UAE Dirham 3, 200 million
Project : ITCC (Information Technology and Communications Complex)
Employer : Al Ra'idah Investment Company /
Public Pension Agency (PPA)
------------------------------------------------------------
Managed variations / claims and payment applications.
--------------------------------------------------------------
Responsibilities (Pre Contract & Post Contract)
Preparation of initial budget estimate from
feasibility proposals.
Preparation of overall project cost calculation &
cash flow projections.
Preparation of tender & contract documentation.
Preparation of pre-tender cost estimate.
Arrange delivery of tender documents to selected
tenderers.
Price tender documents to provide an estimate
comparable with tenders.
Review & evaluation of Interim Payment Application
and finalizing of final Account.
Value : UAE Dirham 210 million
Scope: Construction of Multiplex Mall, Apartment & civil
(IWPP Civil work - Seawater Desalination Plant - 69, 000 m3 / day and Gas-Fired Power Plant - 445 MW Capacities)
LuLu Hypermarket and Chedi Hotel Staff Apartment
---------------------------------------------------------
Responsibilities (Pre & Post Contract)
• Review of Tender documents to identify exact
requirements and potential issues
• Preparation of tender documents for sub contract works and specialist suppliers
• Evaluating Sub Contractors quotations.
• Preparation of plant, labour budgets & cost reports
• Preparation of preliminary cost plan & Budgetary cost Control.
• Measure and price variations and Claims for submission to the Client's representative
• Preparation of applications for interim payments
• Preparation of sub-contractor agreement based on company procedure.
• Monitor cost implications during construction stage
Value : UAE Dirham 200 million
Scope : Construction of UAE University Building and Barsha Boutique Office Building
Client : Al Barsha Real Estate Company and Mubadala Development Company
Architect / Consultant : ZAS / PSE Architect Cox Group PTI Architect
------------------------------------------------------
Value : UAE Dirham 950 million
Project : Discovery Gardens, Mogul 1 & 3
Client : Nakheel
Architect / Consultant : ECG / Turner (PM)
----------------------------------------------------------
Responsibilities (Post Contract)
• Preparation of interim payments certificate
• Preparation of final account
• Negotiate and approve variation claims.
• Preparation of monthly financial report (CVR)
• Preparing, update & maintain logs for all contracts details including variations & claims.
• Participating the site progress meetings and reporting.
Value : UAE Dirham 7.5 million
Scope : Construction of Hospital Building
Responsibilities
• Preparation of Bill of Quantity.
• Evaluate and Certify interim payment Certificate.
• Negotiate and approve variation claims.
• Site Visits & Analysis
• Preparation of specification & details drawing
• Monitoring progress and quality of work
• Providing technical advice and solving problems on site
• Prepare and submit the bar bending schedule of reinforcements steel
Client : Royal Commission, Jubail,
Value : UAE Dirham 60 million
Scope : Operation & maintenance Services Irrigation, Potable water systems, and Landscaping projects.
Responsibilities:
• Preparation of quantity take off and estimated (materials, labour and equipment)
• Preparation of initial budget estimate for construction stage.
• Preparation of interim payment certificate and negotiations.
• Preparation of preliminary cost plan, bill of quantity and other pricing documents
• Evaluating, Negotiating and finalizing Provisional
Sum and Prime Cost in accordance with Contract
requirement and issue Instruction.
• Support the planning coordination programming
design engineering and construction of project
• Ensures all insurances; bonds and Warrantees
are in place as compliance with contract.
Value : UAE Dirham 50 million
Scope : Construction of Hospital Building & warehouse
50 bed Al Qassim Buraida,
Responsibilities
• Quantities take off by complying with standards
• Preparation of Sub Contractors payment
• Preparation of variation.
Module 0: Introduction Module 1: Post contract cost control procedures – commercial management • Project Estimating – • Financial Reporting • Interim Valuations and Recommendations • Change Management & Reporting • Final Accounts • Claims – Loss & Expense • Insolvency & Bankruptcy Module 2: Partnering and joint venture in practice Module 3: Professional ethics and challenges in construction Module 4: Review & Reflect