Planning Engineer
XYZ
مجموع سنوات الخبرة :11 years, 10 أشهر
Baseline review.
Progress reporting
Delay analysis
Contract administration
Resource analysis
1. Identification of Major Deliverables & Preparation of Baseline.
2. Progress Reporting.
3. Preparation of actual vs planned progress and S-Curve.
4. Delay analysis.
5. Contract administration.
Overall technical supervision, Site management, planning and scheduling, Estimation, Quantity surveying, Budgeting.
Working as a planning engineer at 2x660MW coal fired power plant in sahiwal
Planning and Scheduling, Project Monitoring and Controlling
i got scholarship at university level.