Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


User unblocked successfully
Waleed Mostafa, Project Manager

Waleed Mostafa

Project Manager·NWWC

Saudi Arabia

Bachelor's degree, Mechanical design & production engineering

Work experience

Total years of experience: 20 years, 0 months

Project Manager

September 2020 - Present

NWWC

Jeddah, Saudi Arabia

September 2020 - Present

Project Manager
National Water Works Company NWWC, Jeddah, KSA
• Working in the Project Management in infrastructure projects.
• Implemented formal project management processes based on industry best practice but tailored to the company vision.
• Project manager for Khomra waste water treatment station 3, 4 upgrade project (NWC) projects in wastewater projects.
• Administered and implemented Primavera in project scheduling in all projects to optimize project activities and monitor and developed custom workflows to deliver projects in the required time and within its budget.
• Lead purchasing department to supply required materials and machinery,
• Manage and implement PMO practices to optimize project schedule .
• Communicate with all stakeholders and fix periodic meetings to monitor and control project activities with client, main contractors, sub contractors and suppliers .

Achievements:
• Execution of all long lead items in project and following with suppliers to adhere with delivery period
• Approve all main layouts for project after detailed follow-up with consultant and owner.
• Implement PMO practices in the project
• Apply Primavera in project schedule
• Submit all project reports required to the owner

Company industry:
Mechanical Engineering
Job role:
Mechanical Engineering

Projects Planning Manager(PMO)

September 2018 - August 2020

Water and power projects

Dammam, Saudi Arabia

September 2018 - August 2020

Project Manager
Water and Power Projects Contracting WPPCO, Dammam, KSA
• Working in the Project Management in infrastructure projects.
• Implemented formal project management processes based on industry best practice but tailored to the company vision.
• Lead several National Water Company (NWC) projects in water and wastewater projects.
• Administered and implemented Primavera in project scheduling in all projects to optimize project activities and monitor and developed custom workflows to deliver projects in the required time and within its budget.
• Lead purchasing department to supply required materials and machinery,
• Lead warehouse department to apply FIFO, monitor material expiry dates, ease of storing materials and meet storage requirements and apply 5S.
• Internal ISO quality auditor.

Achievements:
• Atheer project Plant installation, 10Km network and 5 wells for NWC with consultant ETS Eng. Hesein El Sagheer.
• STP Dammam administered plant rehabilitation
• Raka wastewater plant and network installation for NWC and owner Aramco with consultant Khatib and Alami Eng. Mohamed Najib.
• Acquiring ISO quality certification to the company,
• Establish the web site for the company and the company profile.
• Implementation of data server to store all projects history.

Company industry:
Construction & Building
Job role:
Construction and Building

Supply Chain Manager

July 2017 - September 2018

SHM Industries

Cairo, Egypt

July 2017 - September 2018

Supply chain Manager:-
Responsible of Primavera project schedule based on sales orders for fuel tanks, fuel stations, oil tanks production and accessories.
Lead planning department to prepare material requisition, min project cost and the requested time.
Lead purchasing department to supply required materials and factory machinery repair
Lead warehouse department to apply FIFO, monitor material expiry dates, ease of storing materials and meet storage requirements.

Company industry:
Manufacturing
Job role:
Manufacturing

Project Manager

July 2007 - July 2015

Electrolux

Cairo, Egypt

July 2007 - July 2015

Electrolux, Multinational Home appliances manufacturer company, 10th of Ramadan city, Egypt

• Completed a gas cooker factory 60, 000m² to produce 1, 000, 000 cookers per year including water, wastewater and firefighting networks.
• Implement and install of complete firefighting & alarm network to
several factories to comply with the local authorities and insurance company.
• Designed and installed complete air network including compressors
Up to detailed assembly line utility to fulfill the production needs.
• Installation of hydraulic and mechanical presses and their utilities
(Firefighting system).
• Designed and installed of complete painting line (pretreatment, drier, paint booth and furnace including productivity calculations and bidding).
• Designed and installed a complete enamel workshop and main factory utility phase 1 (2011-2012) total investment 50 million Egyptian pounds.
• Designed and installed a research and development lab monitoring civil and electromechanical works till hand over (Jan 2015-june 2015) of total investment 2 million Egyptian pounds, in washing machine factory.
• Implemented and solved safety requirements to prevent hazards
on new and old factories to meet requirements of local authorities.

Company industry:
Manufacturing
Job role:
Construction and Building

Planning Manager

July 2004 - August 2007

Universal

Cairo, Egypt

July 2004 - August 2007

Universal, Home appliances manufacturer company, 6th of October city, Egypt
• Project manager - Installation of new factory for gas cooker assembly 2007 of total investment 5 million Egyptian pounds to maximize production with optimal cost.
• Design and installation of firefighting and alarm systems in several factories to comply with local authorities.
• Head of Research and Development Department (gas cooker & washing machine & water heaters & exhaust)
• Completed new gas cookers design, technology, processes, assembly sheets and bill of materials (BOM).
• Planning production orders based on sales and marketing needs
• Making new design for a series of gas and electric cookers to meet European and Australian market standards of British Standards Institution (BSI).

Company industry:
Manufacturing
Job role:
Purchasing and Procurement

Education

Cairo University

November 1995

November 1995

Bachelor's degree, Mechanical design & production engineering

Egypt

GPA (percentage): 61.9%

GPA (percentage): 61.9%

Training in General Motors factory, Nagahamady Aluminum factory, and phosphat Abu tartur Project. Made Comuter Aided drafting 3D under Autocad for mechanical elements
View attachment

Languages

Arabic

Native Speaker

English

Expert

Spanish

Intermediate

French

Beginner

Training and Certifications

Training
EBOSH
Udemy
Apr 2020
Show credentials
PMP training
Ain Shams University
Mar 2017
Show credentials

Hobbies and interests

CNC

Make laser engraving and small item milling at home

PHP & SQL & HTML programming

At Water and Power Projects made a web based inventory system

MS Database programming

At SHM industries made several programs that are running till now serving the production planning