electrical commissioning engineer
CSI (Commissioning Service International)
Total years of experience :7 years, 5 Months
- Preparing the Testing and Commissioning Method Statements.
- Direct contact and involvement with Sub-contractors.
- Perform the pre-commissioning activity and highlight the issues that will affect commissioning process.
- Prepare the installation site redness report and highlight the delayed systems based on the
commissioning schedule.
- Lead the subcontractor and vender commissioning team at site to perform the commissioning activity as
per the commissioning procedure and standers.
- Implement system performance review, to ensure that prior to handover for witness to the Engineer that
the systems are operating within the design intended conditions and project specification requirements.
- Witness all the commissioning functional and integration test on the site and ensure a smooth handover
to the client representative.
- Prepare and submit the testing and commissioning report and reply to the consultant and client
representative comment.
- Review all the Sub-Contractor submittals to ensure compliance with the contract documents and the
commissioning plan prior to be submitted to the engineer for the final approval.
- Prepare a daily and weekly report foe the commissioning activity and highlight the comments and issues.
- Establish schedules for O&M submittals, O&M training schedules and the final handover documentation
submittals required from each Sub-contractor.
- Prepare and submit the close out documents such as (Operation & Maintenance manual, Training
Manual, Test Procedure ... etc.) for Electrical and Mechanical System.
- Certify that works are complete and systems are tested as per the Contract Documentation and project
specification requirements.
- Perform other duties instructed by Department Head or Sr. Engineer.
- Attending project progress review meetings, technical meetings and Coordinate accordingly
- Perform LV test (MDB, SMDB, MCC)
- Perform TAB (Testing Adjusting Balance) for HVAC
- Design review.
- Material Submittals review
- Evaluate the project progress for LV and Low Current system (Power system, Lighting system, Access
Control system, Telephone system, Fire Alarm system, CCTV and public health system)
- Review the shop drawing, as built drawing and check the system in the site
- Prepare the list of equipment to the main contractor.
- Prepare SOR (Site Observation Report) to the main contractor.
- Perform TAB (Testing Adjusting Balance) for HVAC system.
- Testing and commissioning for AHU’s, FCU’s, exhaust fans, smoke fan, chillers, pumps and
chilled water system.
- Fire Staircase Test.
- Material Submittals review
- Design review.
- Control System installation and maintenance, CCTV and DCS.
- Design and Execution for solar system and control panel.
- Design all Electrical Work
- Pricing of electrical equipment
- Install and maintain CCTV system
- Design and Execution for LV
- Testing and Operation
For university building, calculate all loads for lighting and power after that Select Transformer by calculation.
Design all single line diagram for lighting and power.
Select protection device and know rated current by calculation.
Design lighting by DIALUX program.