ZAFAR IQUBAL, Planning Engineer

ZAFAR IQUBAL

Planning Engineer

Arabian Industries

Location
Qatar - Doha
Education
Bachelor's degree, Mechanical Engineering
Experience
12 years, 3 Months

Share My Profile

Block User


Work Experience

Total years of experience :12 years, 3 Months

Planning Engineer at Arabian Industries
  • Oman - Muscat
  • My current job since February 2019
Sr. Planning Engineer at Manco International (Qatar Petroleum)
  • Qatar - Doha
  • August 2017 to December 2018

Understanding and finalizing the Scope of work.
Development of Project Schedule by using PRIMAVERA (P6).
Preparation Project Plan, Milestone, and Level 4 Scheduling.
Developing the Activities for Steel Structural, Piping, Tanks, E&I, Rubber lining etc.
Estimating the Man-hours, Quantity, Productivity, and Duration based on Company norms. etc.
Development of resources mobilization Schedule & Histogram.
Submission Baseline Schedule for approval.
Preparation of Look Ahead Schedule for 2weeks, 4weeks or as per requirement.
Updating and monitoring Progress on daily basis.
Preparation of Daily Progress Report and submitting to client.
Monitoring of manpower allocated on site.
Estimation of Manpower Requirement.
Updating the Schedule and providing work front to execution team.
Prepare Tracking Sheet to get activity status.
Progress Measurement using S-Curves.
Maintaining the S-Curve for Discipline wise as well as overall.
Preparation of appropriate Recovery Plan if such delay appears and taking approval from client
Developing, updating, monitoring and reviewing over All Project Schedule based on Work Packages established with various disciplines and Project schedule utilizing Primavera
Involvement of throughout the project duration and coordinating with QS, QA/QC, Site Execution and HSE department.
Monitoring progress and control project activities. Verification of Milestones. Identify potential delays, analyze and issue proposed corrective actions as required.
Preparation of appropriate Recovery Plan if such delay appears and taking approval from client.
Participate in the preparation of Weekly and Monthly Reports; ensure a continuous and timely flow of information to the Planning and Reporting Coordinator.
Producing Site progress Report and finding critical work for minimize time.
Organizing daily internal meeting with all department.

Project Planner at TATA Steel Limited INDIA
  • India - Mumbai
  • October 2016 to July 2017

Preparation Project Plan, Milestone, and Level 4 Scheduling.
Developing the Activities for Steel Structural, Piping, Tanks, E&I, Rubber lining etc.
Estimating the Man-hours, Quantity, Productivity, and Duration based on Company norms. etc.
Development of resources mobilization Schedule &Histogram.
Submission Baseline Schedule for approval.
Preparation of Look Ahead Schedule for 2weeks, 4weeks or as per requirement.
Updating and monitoring Progress on daily basis.
Preparation of Daily Progress Report and submitting to client.
Monitoring of manpower allocated on site.
Estimation of Manpower Requirement.
Involvement of throughout the project duration and coordinating with QS, QA/QC, Site
Execution and HSE department.

Project Planner at DODSAL E&C –DUBAI
  • United Arab Emirates - Dubai
  • November 2015 to September 2016

Developing the Activities for Steel Structural, Piping, Tanks, E&I, Rubber lining etc.
Estimating the Man-hours, Quantity, Productivity, and Duration based on Company norms. etc.
Development of resources mobilization Schedule &Histogram.
Submission Baseline Schedule for approval.
Preparation of Look Ahead Schedule for 2weeks, 4weeks or as per requirement.
Updating and monitoring Progress on daily basis.
Preparation of Daily Progress Report and submitting to client.
Monitoring of manpower allocated on site.
Estimation of Manpower Requirement.
Updating the Schedule and providing work front to execution team.
Prepare Tracking Sheet to get activity status.
Progress Measurement using S-Curves.
Maintaining the S-Curve for Discipline wise as well as overall.
Monitoring progress and control project activities. Verification of Milestones. Identify potential
delays, analyze and issue proposed corrective actions as required.

Planner Cum Site Engineer at DENHOLM YAM LLC- ABU DHABI
  • United Arab Emirates - Abu Dhabi
  • January 2012 to November 2015

Understanding and finalizing the Scope of work.
Development of Project Schedule by using PRIMAVERA (P6).
Preparation Project Plan, Milestone, and Level 4 Scheduling.
Developing the Activities for Steel Structural, Piping, Tanks, E&I, Rubber lining etc.
Estimating the Man-hours, Quantity, Productivity, and Duration based on Company norms. etc.
Development of resources mobilization Schedule &Histogram.
Submission Baseline Schedule for approval.
Preparation of Look Ahead Schedule for 2weeks, 4weeks or as per requirement.
Updating and monitoring Progress on daily basis.
Preparation of Daily Progress Report and submitting to client.
Monitoring of manpower allocated on site.
Estimation of Manpower Requirement.
Updating the Schedule and providing work front to execution team.
Prepare Tracking Sheet to get activity status.
Progress Measurement using S-Curves.
Maintaining the S-Curve for Discipline wise as well as overall.
Preparation of Cash Flow Chart.
Monitoring the critical Activity and taking appropriate consideration over it.
Preparation Daily, weekly and Monthly progress report.

Education

Bachelor's degree, Mechanical Engineering
  • at RVD
  • December 2012

Specialties & Skills

MS Office tools
AutoCAD
Structural Design
AUTO CAD
MS OFFICE
Primavera

Languages

Hindi
Expert
Urdu
Expert
English
Expert

Memberships

Role: Team
  • Member

Training and Certifications

ACHIEVED (Certificate)
Date Attended:
May 2012
Valid Until:
January 2030