Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


User unblocked successfully
zulfihar Ahamed, Senior Planning Manager

zulfihar Ahamed

Senior Planning Manager·Azizi Developments

United Arab Emirates

High school or equivalent, Construction Claims

Work experience

Total years of experience: 13 years, 6 months

Senior Planning Manager

February 2018 - Present

Azizi Developments

Dubai, United Arab Emirates

February 2018 - Present

 Project Control process implementation and monitoring for 5 Billion value projects. Meydon 35 projects, Furjan 9 projects, Dubai Health care city 4 projects, Palm 2 projects, 4000 Town Houses.
 Planning Guild line, manuals, Reporting templates prepared and implemented to have uniform project data reporting.
 Managing Project Management Office to advice the project and guideline to Senior Project Managers, Project Managers on progress, EOT claims and project control measures.
 Claims Evaluation - Evaluation of Consultant Programme review, EOT review, Contractor EOT review and advice consultant on programme and EOT claims.
 Claims Analysis - Forensic planning, Detailed analysis of claims including:
Contract/entitlement analyses / Cause & effect analyses / Schedule analyses / Schedule Impact analyses.
 Assess potential time impacts for the delay events and advice senior project manager for correct decision making.
 Attend project Kick-off meeting, progress meeting, EOT review meeting and input advice from client prospective.

Company industry:
Real Estate
Job role:
Consulting

Consultant Planning Manager

January 2016 - January 2018

James Cubitt and Partners Co.

Dubai, United Arab Emirates

January 2016 - January 2018

Responsibilities:
- Program Review/Approve, Contractors’ and Sub-Contractors Programs (Baseline/Recovery and regular updates), including cost and resource.
- Perform Schedule Validation using Risk Analysis tool for any basic schedules problems, such as broken logic or lag.
- Perform Pre-Analysis check.
- Develop and import Risk Models.
- Run Risk Analysis.
- Review the results.
- Monitor construction progress and analyze Earned Value and associated Key Performance Indicators.
- Review Contractor’s submittals (Actual vs. Planned).
- Review Authority Approval Matrix, Procurement log, Look ahead program.
- Raise Early Warnings when actual performance of the Works falls short of the target.
- Issue Delay notice to contractor progress performance.
- Prepare contract letters on contractor manpower shortage, Rate of progress, engineering submittals delay.
- Identify project risks, propose mitigation measures and develop project wide risk register and report to Client and consultant team.
- Review Contractors’ Daily, Weekly, Monthly reports.
- Review and assess delay events and provide Impact Assessments.
- Review and assess time aspects of Contractors’ Extension of Time claims.
- Prepare Project Controls Management Plans and Procedures.
- Analyze critical path on progress report, record and reports to Client and Consultant team.
- Attend progress review meetings.
- Prepare monthly progress reports for client in collaboration with project team.

Company industry:
Business Consultancy Services
Job role:
Engineering

Planning Manager

December 2012 - December 2015

Ghantoot Group

Dubai, United Arab Emirates

December 2012 - December 2015

Responsibilities:
- Preliminary evaluation of contractor, subcontractor, and owner claims for entitlement.
- Preparing contractor claims-chronology of delay events.
- Detailed analysis of claims including:
Contract/entitlement analyses / Cause & effect analyses / Schedule analyses / Schedule Impact analyses.
- Assess potential time impacts for the delay events.
- Assess potential time impacts of variations.
- Preparation of comprehensive claims for delay, disruption, and/change order and prolongation, Establish entitlement for extension of time (EOT).
- Responsible to defend / counter any contractual claims with respect to scheduling issues.
- Responsible for all the pre-construction planning review, baseline line, construction, revised/recovery programs review prior to handover planning team.
- Performs and manages complex and sensitive professional planning projects, and analysis.
- Identify the constraint of a project critical chain, and demonstrate the schedule impact to project execution team to perform the activity 50% duration to ovoid possible schedule overrun due to uncertainty of schedule.
- Demonstrate project team for Buffer management to utilize the available resource utilization to project.
- Provides overall management of related planning issues.
- Implement project control plan and monitor project cost and schedule activities of all phases of the project.
- Report to Project Director/PM on all planning-related matters.
- Assigns work to planning staff and ensures appropriate training is provided
- Evaluates operations and activities of assigned responsibilities.
- Prepares reports on operations and activities, recommending improvements and modifications
- Handles sensitive personnel matters
- Attends substantial number of evening and weekend meetings
- Assists project management in the transition of each project from its planning phase to construction.
- Works in support of project management during materials procurement to ensure compliance with construction plans and specifications.
- Provides diagnostic monitoring of baseline estimates during project construction.
- Validates planning metrics upon project completion
- Preparation of project planning control plan in accordance with procedures and object ties.
- Working closely with the project team assisting and guiding on any planning issues.
- Responsible to raise early warnings to alert the project team for their awareness and prompt action taking for any scheduling related issues.
- Providing project planning summary report to client and consultants.
- Reporting to the construction management teams.
- Review progress status, updates and productivity through daily reports.
- Review S-curves for planned and actual progress.
- Follow up procurement team for status for long lead items and communicate with procurement team to make early alert.
- Ensures all parties are fully aware of project schedule activities, delays.
- Monitoring milestones activities and critical paths for timely actions.
- Reviewing commissioning schedule.
- Attend meetings with subcontractors as required.
- Identify potential issues and ways to overcome them.
- Recommendations to overcome project issues and sequencing as required.
- Review and analyze subcontractor’s schedule and submission logs/reports.
- Manages the performance and service delivery of the deliverables.

Company industry:
Construction & Building
Job role:
Engineering

Education

Prime Consulting

October 2014

October 2014

High school or equivalent, Construction Claims

Poland

BTEC

May 2014

May 2014

Higher diploma, Civil Engineering

India

Stonebridge college

March 2009

March 2009

Diploma, Project Management and Planning

United Kingdom

GPA (point): 5 out of 5

GPA (point): 5 out of 5

Barathidasan University

April 1989

April 1989

Master's degree, Physics

India

GPA (percentage): 70%

GPA (percentage): 70%

Skills

Inspection
Expert
Inspection
Expert
Waste
Expert
Waste
Expert
Risk
Expert
Risk
Expert
Risk Assessment
Expert
Risk Assessment
Expert
Production
Expert
Production
Expert
Stakeholder management
Expert
Stakeholder management
Expert
Project Control, Earned Value Management, Planning , Scheduling, Monitoring, Control
Expert
Project Control, Earned Value Management, Planning , Scheduling, Monitoring, Control
Expert
Inspection
Expert
Inspection
Expert
Waste
Expert
Waste
Expert
Risk
Expert
Risk
Expert
Risk Assessment
Expert
Risk Assessment
Expert
Production
Expert
Production
Expert

Languages

English
Expert

Memberships

Project Management Institute USA

Member

June 2014

Charter Institute of Building

Member

May 2017

Hobbies

  • Browse net for knowledge