SUB ENGINEER
FPCL A Project of FFBL
Total years of experience :11 years, 2 Months
To look after the operational matters of 118 MW industrial & commercial power plant having 02 coal fired boilers (CFBC, capacity of each boiler 250TPH @ 90 Bar working pressure) and 04 numbers of steam turbines (10MW, 24 MW, 24 MW & 60 MW) along with all auxiliaries/utilities.
Supervise and maintain the performance chractristics of steam boilers, Air heaters, water purification plants(Reverse Osmosis), Air Compressors, ammonia compressors, steam absorption & hot water chillers, Gensets (HFO & Diesel engines), Nitrogen plant, Fire hydrant system and Deep well water turbines.Prepare and maintained the Preventive and corrective plans.
Courses: DMAIC GSTD BDA SRs Preparations