abdullah shazly, Construction Manager

abdullah shazly

Construction Manager

MASCO

Location
Saudi Arabia - Khobar
Education
Bachelor's degree, Civil Engineering
Experience
13 years, 7 Months

Share My Profile

Block User


Work Experience

Total years of experience :13 years, 7 Months

Construction Manager at MASCO
  • Saudi Arabia
  • My current job since October 2015

is a general contractor specialized in different field of construction that
range from infrastructure to building, water, environmental and power projects.

Project Manager at Al-Khobar
  • Saudi Arabia
  • My current job since October 2015

The Scope of WORK was Execution of infrastructure works for

Project Manager
  • My current job since September 2013

The Scope of WORK was construction of (water tank, S.T.P area, transformer buildings, chillers
buildings, Gates, boundary wall, 3 zones of hospital building, landscape, AC foundations.
Key Accountabilities: Key Accountabilities includes but not limited to:
 Supervision of Project/Site in all respects including Labors, Materials, Machineries,
Concrete...Etc
Which come under in the entire Project.
 Site Mobilization.
 Excavation works.
 Review of Structural Drawings such as STEEL & FORMWORK drawings and execute the works
according to approved codes from the Designer & Consultants.
 Giving Directions to Foreman’s for Proper Execution & Schedule of Working in the Project.
 Preparing Bar Bending (Cutting List) prior to work.
 Arranging materials needed for Formworks.
 Arranging Concreting to required areas.
 Getting approval from Consultants for further works like Shuttering & Concreting.
 Preparing & Submitting BOQ’s, Estimation, bar bending Schedules to General Contractors.
 Maintaining Quality & Safety Procedures in the Site.
 Preparing Daily Reports which undergoing in the Site.
 Preparing Shop Drawings wherever it requires.
 Testing of Concrete in the Site as well as in the Laboratory for desired Strength, Slump &
Temperature.
 Testing of Soil in Backfilling areas for desired Compaction & Moisture content.
 Execute tasks according to time schedule
 Excellent experience in construction (structure and finishes)
 Execute S.T. P area and landscape works

civil site engineer at Al-Khodari Sons
  • Saudi Arabia
  • September 2013 to October 2013

Projects:
1- 100 Bed Abqaiq General Hospital
Project

Civil Site Engineer
  • United Arab Emirates
  • April 2012 to June 2012

The Scope of The Egyptian Army in this project was construction of supervising the implementation
of project such as (Raise the efficiency of Sinai Development Authority headquarters in Ministry
Planning and International Cooperation
Project Details:
Client : Ministry Planning and International Cooperation
Consultant : The Egyptian Army
Project Value : 1.1 Million
Role in the Project

at The Egyptian Army
  • Egypt
  • April 2012 to June 2012
Civil Site Engineer at The Hotel and Club Helmey
  • Egypt
  • July 2012 to February 2012

The scope of work on the project includes excavation and enabling works, construction of the structural
frame, masonry works, complete architectural works including metal works, wood works, thermal and
moisture protection, doors and windows, aluminum and curtain wall finishes, landscape.
Page 4 of 5
Project Details:
Client : The Egyptian Army
Consultant : The Egyptian Army
Project Value : 115 Million EGP
Role in the Project

Project Manager
  • September 2008 to March 2011
Civil Site Engineer at Arab Contractors Company
  • Egypt
  • January 2009 to June 2010

3.Samalout Water Plant, EL-Minia, Egypt:
The scope of work on the project as sub-contractor with (

Civil Site Engineer at 2012 2. Abou El Makarem Bridge on Al-Yousifi sea , EL-Mini
  • Egypt
  • September 2010 to March 2010

The Contract of this project is including in not limited to excavation and enabling works,
construction of the structural frame, masonry works, soft landscape, sidewalks, and road works
Project Details:
Client : Ministry of Irrigation
Consultant : Ministry of Irrigation (Protection of the Nile administration)
Project Value : 7 million EGP
Role in the Project

Civil Site Engineer at Farouk Ibrahim engineer for General Contracting
  • Egypt
  • September 2008 to March 2008

The scope of work on the project includes excavation and enabling works, construction of the
structural frame, complete architectural works including, water proofing and testing, , backfilling
after pass of water test at layers.
Project Details:
Client : Ministry of Irrigation
Consultant : Ministry of Irrigation (Protection of the Nile administration)
Project Value : 5 million EGP
Role in the Project

SR
  • to
CIVIL Engineer
  • to
Project Manager at Hill International
  • United Arab Emirates
  • to
Project
  • to

Client : Saudi Ministry of Housing.
Consultant : Saud consult.
Project Value : 62 million SR
Role in the Project

Consultant at Khatib & Alami
  • United Arab Emirates
  • to
Project Manager
  • to
Project Manager
  • to

Education

Bachelor's degree, Civil Engineering
  • at EL
  • January 2011

Specialties & Skills

MICROSOFT WORKS
CONTENT MANAGEMENT
MATERIALS MANAGEMENT
QUALITY
SUPERVISORY SKILLS
BUDGETING
CONSULTING
CUSTOMER RELATIONS
ENGINEERING

Languages

English
Expert