Manager E-Power (Telecom Electrical System + Solar System)
Somcable Limited.
Total years of experience :19 years, 1 Months
https://www.somcable.com/
Major projects during the period 2017 to 2021:
==============================================
* Somcable HQ Panel Design & Installation + Connection of Digital Power Analyzer 250 Amps. (SIEMENS)
* Somcable HQ 02 Nos. of new ATS Installation 400 Amps. (Magnetic Type) (Schneider)
* Somcable HQ Interfacing of 04 Nos. ATS to each other for three power sources in for HQ Building (Grid-1, Grid-2, and Standby Gen Set)
* Somcable HQ Feed-B installation - 04 Nos. Power Racks (AC/DC) in the Data Center as a redundant power source for the network.
* Backhaul Site with Solar Power 1.5 kWh Energy at Sharub Complete Installation - termination/connection - Commissioning of 36 Solar Panels and 24 Batteries and Power and control panel with 06 Nos. PV Chargers - 03 Nos. Rectifiers - 01 Nos. Inverters, 01 No. Gen-Set (10kVA)
* Backhaul Site with Solar Power 3.0 kWh Energy at Burao Complete Installation - termination/connection - Commissioning of 72 Solar Panels and 48 Batteries and Power and control panel with 09 Nos. PV Chargers - 03 Nos. Rectifiers - 02 Nos. Inverters, 01 No. Gen-Set (10kVA) with ATS.
* Backhaul Site with Solar Power 3.0 kWh Energy at Berbera Complete Installation - termination/connection - Commissioning of 72 Solar Panels and 48 Batteries and Power and control panel with 09 Nos. PV Chargers - 03 Nos. Rectifiers - 02 Nos. Inverters, 01 No. Gen-Set (10kVA) with ATS.
* MSG Group Stone Crusher at Balligaas Area MCC Panel Installation - Cable laying - All the Motors connection - Gen-Set (400kVA) Installation and Commissioning etc
https://www.somcable.com/
Major projects during the period 2015 to 2017:
==============================================
* Somcable HQ 02 Nos. of ATS Installation 400 Amps. (Rotary Type) (Westhomes)
* Somcable HQ 08 Nos. Electrical Panel Diagram for the whole building (As Build)
* Somcable HQ 05 Nos. Racks in Data Center detail block diagram (As built - DC & AC Circuit)
* SO! LTE Towers 20 Nos. SO! LTE Towers Complete Electrical Installation & Commissioning (Power Rack with Rectifiers and Inverters and Controller, AC/DC wiring & Circuit Breakers +Panel box, Cable Tray, wiring Connections, etc.)
* SO! Gasho Branches 10 Nos. SO! Gasho Branches Complete Electrical Installation, CCTV Installation & Commissioning (Power Panel, Cable Trunking, UPS Installation, ATS Installation CCTV Installation with DVR & wiring Connections, etc.)
Major projects Electrical & Instrumentation during the period 2012 to 2015:
===========================================================================
* Metro Cash Carry Pakistan. Project of Centralized Energy Metering - Energy Monitoring for different loads in the building and centralize all of them with industrial network and make ready to get access all data in Germany through Data Gateway. We did the same in all the Stations in Karachi, Lahore, and Islamabad.
* Lucky Textile Mills. Project of Centralized Energy Metering - Energy Monitoring for different loads of industrial textile machines in the factory and centralize all of them with industrial network and make ready to get access all data in the control room through Data Acquisition System.
https://www.gel1947.com/
Major projects of Boilers & Gen-Sets Electrical & Instrumentation during the period 2011 to 2012:
=================================================================================================
* ASL Paper Mills, Karachi. 02 Nos. of WHRS Boiler 10 Bar on Engine Exhaust
* Astro Plastic, Port Bin Qasim Karachi. 04 Nos. Oil Heaters on Engine Exhaust
* Rajbi Textile Mills Landhi Karachi. 01 No. of WHRS Boiler 10 Bar on 1 Mega Watt Engine Exhaust - Caterpillar Natural Gas Engine
* SNGPL Gen-Set - Lahore. Gas Gen-Set complete installation and commissioning with ATS Panel. (Doosan Gas Engine & Bokuk Alternator)
https://www.progas.cc
https://www.linkedin.com/company/progas-energy-limited/
During Installation/Commissioning of LPG Tanks & Jetty
======================================================
* Inspection of all the Electrical, Instrumentation, Firefighting systems, PLC controls & communication systems Including Optical Fiber cables lying & installation activities as per standards (NFPA/NEMA)
On this Project Working with topmost Engineering Construction Companies:
************************************************************************
o SNC LAVALIN International (Main Contractor of Progas Pakistan Limited.)
o China Shanghai (Group) Corporation for Foreign Economic & Technological Cooperation (SFECO) (Sub Contractor by SNC)
o China Petroleum First Construction Company(CPFCC) (Sub-Contractor by SFECO for Electrical, Instruments & Mechanical work)
o China Harbour Engineering Company Ltd. (CHEC) (Sub-Contractor by SFECO for all civil work)
After the Installation/Commissioning, Completion of LPG Tanks & Jetty
*********************************************************************
* Working as a Shift & Control Station Incharge of the Terminal.
* Official Correspondence & maintain records of Daily Operation & Maintenance Reports. Responsible for the preventive maintenance of the Jetty & Bulk Storage of all the E&I equipment.
* During offloading LPG from the Ship, monitor overall Operation, process, and safety under Ship offloading Operation.
* Monitor utility requirements and depute the staff on Jetty Head on Marin Loading Arm (MLA), Quick Release Hooks (for Ship ropes), Static Grounding Control Panel, Emergency Shutdown Valve (ESDV), and Fire Fighting Pumps Control System.
* Arrangement of the Fire Extinguishers & Fire Blankets at the Jetty Head at the proper location.
* Follow the security response plan, Safety Hazardous & Spillage Plan during ship offloading and reported to Manager Terminal Operation & Administration (MTO&A) in an emergency.
* Responsible for the Calculation of LPG discharge from the ship to Spherical Tanks after bulk transfer.
* Responsible for PLC control system including firefighting system.
* Responsible for all communication on the VHF wireless system with Port Muhammad Bin Qasim Authority (PQA). Planning and scheduling planned and unplanned work.
* Diagnosing breakdown problems.
* Supervising day-to-day Electrical/Instruments operation & maintenance activities at the Jetty & Bulk Storage area.
* Responsible for the preventive maintenance program of 02 Nos. of 100kVA and 01 No. of 45kVA Gen-Sets at the Jetty.
https://www.gel1947.com/
Mentioned below are major projects of Boilers & Co-Generation Power plants Electrical & Instrumentation during the period 2003 to 2006:
=======================================================================================================================================
* Gatro Power HRSG Boiler 60 Bar on Turbine Exhaust - Turbine: TURBOMACH, Switzerland - Co-Generation Power Plant at Gatro Power (Pvt.) Limited a subsidiary of Gatron (Industries) Limited, Hub, RCD Highway, Balochistan.
* MCB Tower (Tallest Building of Pakistan 2005-2012) (WHRS Boiler 10 Bar on Turbine Exhaust) (Turbine: Kawasaki, Japan) at I.I Ch. Road Karachi.
* Friendship Textile Mills, (HRSG Boiler 10 Bar on Turbine Exhaust - Co-Generation) (Turbine: Kawasaki, Japan) at S.I.T.E., Karachi.
* GATRON-2 (G-2) 03 Nos. of WHRS Boiler 10 Bar on 1 Mega Watt Engine Exhaust - Engine - DEUTZ Diesel Engines & Jenbacher Gas Engine
* Siddique Sons Ltd. Site Karachi. 03 Nos. of WHRS Boiler 10 Bar on Engine Exhaust
* Rajbi Textile Mills Korangi, Karachi. 01 No. of Water Tube Boiler 10 Bar on Natural Gas.
* Ismail Industries Ltd. (Candy Land) Hub, Balochistan. 03 Nos. of WHRS Boiler 10 Bar on Engine Exhaust
* Mustaqeem Dying Mills 01 No. of WHRS Boiler 10 Bar on Engine Exhaust.
* SSGC HQ- Rohri Gas Gen-Set complete installation and commissioning with ATS Panel. (Doosan Gas Engine & Bokuk Alternator)
Bachelor of Technology (Hons) in “Electronics” Passed in 2009, with “CGPA of 3.58” Dadabhoy Institute of Higher Education Karachi. Recognized by the Higher Education Commission and Chartered by the Government of Sindh, Pakistan.
From Government College of Technology Hyderabad, under Sindh Board of Technical Education (SBTE), Karachi. Passed in 2001, with “First Division”
Higher Secondary Certificate (H.S.C) / Intermediate (Pre-Engineering) Passed in 1997 - under the Board of Intermediate and Secondary Education Hyderabad
URL removed due to policy violation. Please contact support for further information.